Professional Documents
Culture Documents
Historical Background
Procurement Planning
Preparation of Bidding Documents
Procurement thru Competitive Bidding
Alternative Modes of Procurement
AMERICAN LAWS ON
PROCUREMENT
CONTRACTS
PHILIPPINE PUBLIC
PROCUREMENT
5
1917 ADMINISTRATIVE NEDA GUIDELINES ON
CODE OF THE PHILIPPINES PROCUREMENT OF
CONSULTING
SERVICES
PD 1594 ON N
ENT OF 62 O NT OF
PROCUREM 2
EO EME
S
GOODS CIVIL WORK C U R OD S
PRO
G GO
U LTIN
CO NS SERV
ICES
FRA
IN
PE BEFORE THE
ENACTMENT OF GPRA
6
ENACTMENT OF GPRA
Implementing
Rules and
Government Procurement Reform
Regulations
Act
10 January 2003
Executive Orders
Implementing Rules and
Regulations (IRR) Part A
8 October2003
Memorandum
Circulars
7
PROCUREMENT REFORMS
PROBLEMS REFORMS
• Confusion caused by • Enactment of the Government
fragmented legal system Procurement Reform Act (GPRA)
• Use of PhilGEPS
• Lack of transparency (Philippine Government Electronic
Procurement System)
8
KEY FEATURES OF GPRA
9
CLARIFICATION OF TERMS
SATISFACTIO
NEEDS
N
− advance deliveries
− suki system
− unwarranted resort to alternative methods procurement
2020
SECTION 7.1 OF IRR
Procurement Planning and Budgeting Linkage
22
ACTORS IN PROCUREMENT PLANNING
TECHNICAL WORKING
END USER GROUP (TWG)
BUDGET OFFICE
Estimated Budget
Quantity SCHEDULE/MILESTONE OF ACTIVITIES
P.R. No. 1 General Description Mode of Procurement
Size Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Total Budget Amount Php
PREPARED: EVALUATED BY: APPROVED:
(To be included in the DPWH
Budget Proposal)
Service/RO/PMO :
Division/District/City :
TOTAL DISTRIBUTION BY QUARTERS
GOODS UNIT CALENDAR 1ST QTR. 2ND QTR. 3RD QTR. 4TH QTR.
Category / Nature and Description / Specification UNIT PRICE QTY AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
PROGRAM AMOUNT
PPMP vs PR
27
ANNUAL PROCUREMENT PLAN (APP)
28
ANNUAL PROCUREMENT PLAN (APP)
All procurement should be meticulously and judiciously planned by
procuring entity
A review and updating of the individual PPMPs and the APP shall be
done regularly, at least once every 6 mos. or as often as necessary. The
end-user or implementing units shall be responsible for the changes to
the PPMPs, while the BAC Secretariat shall be responsible for the
consolidation of these PPMPs into an APP
29
ANNUAL PROCUREMENT PLAN (APP)
1 2 3 5 7
4 6
30
PREPARATION OF APP
n
tio
APP
ra
re pa
et P
u d g
n gB When GAA,
D u ri Corporate Budget
or Appropriation
Upon approval Ordinance
of HOPE, becomes final,
Submit Budget Budget Office PPMPs will be
Proposal to will forward finalized and
HOPE PPMPs to BAC submitted to BAC
Submit to
Secretariat for Secretariat for
Budget
Consolidation consolidation and
Office for
and Review approval of the
evaluation
HOPE.
Prepare Project
Procurement
Management Budget Office HOPE &
Plan (PPMP) BAC Secretariat
End-User Unit
31
PREPARATION OF APP
HOPE/Approving
APP
When GAA, Corporate
Body Budget or
BAC & Appropriation
Secretariat Submit Indicative
Ordinance becomes
final, PPMPs will be
Budget APP and budget finalized and submitted
proposal to to BAC Secretariat for
Office Consolidation of HOPE/oversight
PPMPs to consolidation, to BAC
body for approval for final
Indicative APP by
End-User Submit to BAC Sec and recommendation of
recommendation modality and final
Unit Budget
by BAC of approval of the HOPE
Office for
evaluation modality
Prepare Project
Procurement
Management
Plan (PPMP) During Budget Preparation
32
PPMP CONSOLIDATION
• Checking of • Recommendation of
procurement procurement methods
methods by the BAC
• Propose procurement
methods (End-user)
3333
REVISIONS ON APP
Update
End-User /Supplement
PPMP
Consolidate
BAC & BAC Sec PPMP to
Updated/
Supplemental
APP
Approve
Updated
/Supplemental
HOPE APP
34
ANNUAL PROCUREMENT PLAN FOR FY ___
Code Procurement PMO/End-User Mode of Schedule for Each Procurement Activity Source of Estimated Budget (Php) REMARKS
(PAP) Program/Project Procurement
Ads/Post of
IB/REI
Sub/Open of
Bids
Notice of Award Contract Signing
Funds
TOTAL MOOE CO
TOTAL
37
APP-CSE
38
PURCHASE REQUEST (PR)
39
Appendix 60
PURCHASE REQUEST
Stock/ Property No. Unit Item Description Quantity Unit Cost Total Cost
Purpose: ____________________________________________________________
_______________________________________________________________
_______________________________________________________________
Requested by: Approved by:
Signature : _________________________ ___________________________
Printed Name : _________________________ ___________________________
Designation: _________________________ ___________________________
41
TECHNICAL SPECIFICATIONS
Consult Stakeholders
In developing the project requirements and TS, the Procuring
Entity may engage the services of technical experts, whether in-
house or consultants, to ensure that the requirements and the TS
are adequate to achieve the objectives of the particular
procurement.
Set clear Specifications:
– Generic and flexible
– Clear and unambiguous
– Reminder on Reference to Brand Names (Section 18)
– Updated, where technology is taken into account
– Fits the actual requirements of the PMO/End-user
42
REQUIREMENT SPECIFICATION
43
MAJOR TRAPS IN THE SPECIFICATION PHASE
1. Over Specifying
2. Too vague or incomplete
specifications
3. No focus on best value of
money
44
HOW TO WRITE TECHNICAL SPECIFICATIONS?
FUNCTIONAL DESCRIPTION
- description of the functions for which the Goods are to be
utilized
EXAMPLE:
The ballpen is expected to write 1.5 km
of straight, continuous lines.
45
HOW TO WRITE TECHNICAL SPECIFICATIONS?
PERFORMANCE DESCRIPTION
- refers to the manner that the Goods are required to
perform the functions expected of them
EXAMPLE:
A ballpen that writes at 1.5 km
continuously and smoothly.
46
HOW TO WRITE TECHNICAL SPECIFICATIONS?
ENVIRONMENTAL INTERFACE
- refers to the environment in which the required
functions are performed at the desired level
EXAMPLE:
The ballpen should write continuously
for 1.5km on a notebook, but not
necessarily on a white board.
47
HOW TO WRITE TECHNICAL SPECIFICATIONS?
DESIGN
- refers to the technical design or drawing of the goods
being procured
EXAMPLE:
The ballpen should be
comfortable to use by left-hand
writers.
48
Green Public Procurement (GPP)
GPPB Resolution No.25-2017
Green Procurement is
Responsible Procurement
10 CSEs 10 non-CSEs
Market readiness
Environmental impact
Cost implications
Practicability
Support to government
Environmental objectives
Support to the local economy
GPP: Non-Common-use Supplies
and Equipment (Non-CSEs)
FIRST SET OF PRIORITIZED
PRODUCTS (non-CSEs)
ASSESSMENT MATRIX
Market readiness
Environmental impact
Cost implications
Practicability
Support to government
Environmental objectives
Support to the local economy
NON-CSE PRODUCT: COMPUTERS, MONITORS
AND LAPTOPS
SCOPE:
Environmentally-friendly ICT equipment including desktop PCs, laptops
(Notebooks), palmtop and computers and computer display devices like
CRT, LCD, and LED monitors.
KEY ENVIRONMENTAL IMPACT
• Energy consumption, especially during use phase;
• Resource consumption related to the production of IT products;
• Harmful emissions related to the production of IT products
• Generation of waste material through packaging and end-use.
GPP APPROACH
• Purchase energy efficient models;
• Purchase products with a restricted amount of hazardous
constituents;
• Design for recycling, longer life and promote take back options;
• Safe disposal
NON-CSE PRODUCT: COMPUTERS, MONITORS
AND LAPTOPS
PRODUCT SPECIFICATIONS:
• Fulfills at least ENERGY STAR 6.1 for computers and 7.0 for monitors
criteria;
• With visible on/off switch;
• In case of desktop computers – memory, hard disk and CD drive are
readily accessible and can be changed easily for upgrades;
• Availability of replacement batteries and power supplies is guaranteed
for at least 5 years after end of production
• Recyclable packages and shall provide a packaging take-back service
NON-CSE PRODUCT: COMPUTERS, MONITORS
AND LAPTOPS
JUSTIFICATION:
• Reference to Energy Star for computers and similar products is very
common in GPP. The same regards criteria referring to product
lifetime/resource efficiency.
EVIDENCE:
• Must meet the latest Energy Star standards for energy performance.
• If without Energy Star label, suppliers are required to submit an
appropriate means of energy consumptions levels (e.g. technical
dossier, test report)
• The supplier shall declare that requirements concerning the longer-life
of the products are met by providing warranty certificates, and
guarantees on the availability of replacement parts.
• Supported by other relevant documentation (eg. packaging take-back
service)
NON-CSE PRODUCT: COMPUTERS, MONITORS
AND LAPTOPS
VERIFICATION:
• www.energystar.gov provides a list of products certified by the energy
star.
• Testing facilities reports
• Independent testing can be carried out by TUV Rheinland
• Judged by technician (accessibility of memory, hard disk and CDD has
to be judged by a technician
NON-CSE PRODUCT: REFRIGERATORS AND
FREEZERS
SCOPE:
Refrigerators, freezers and refrigerator/freezer combinations
PRODUCT SPECIFICATIONS:
• Fulfills at least ENERGY STAR 5.0;
• Supplier shall ensure that the products do not contain “controlled
refrigerants” as defined under the Ozone Layer Protection Regulation.
• Ensure that products are repairable and the replacement parts are
available (for minimum of 10 years after end of production)
• Recyclable packages
NON-CSE PRODUCT: REFRIGERATORS AND
FREEZERS
JUSTIFICATION:
• Most GPP schemes refer to the energy star. Once the new national
system for energy efficiency classification of refrigerators and freezers
has been introduced, there is no need to further refer to the Energy
Star.
• Exclusion of ozone depleting substances.
EVIDENCE:
• Evidence that specifications are met especially those concerning ozone
depleting substances.
• Other proof e.g technical dossier, test reports from recognized body
• Supported by other relevant documentation (eg. Energy star
certification, take-back service)
NON-CSE PRODUCT: REFRIGERATORS AND
FREEZERS
VERIFICATION:
• www.energystar.gov provides a list of products certified by the energy
star.
• Testing facilities reports
• Independent testing on energy efficiency can be carried out by TUV
Rheinland.
NON-CSE PRODUCT: PAINTS AND VARNISHES
SCOPE:
Water-, Solvent-, and oil-based.
GPP APPROACH
• With restricted amount of hazardous substances
• Minimize negative environmental impact
• Low waste generation
NON-CSE PRODUCT: PAINTS AND VARNISHES
PRODUCT SPECIFICATIONS:
• Must not contain mercury, lead, cadmium, hexa-valent chromium,
barium, antimony as well as tributyltin (TBT) and triphenyltin (TPT)
• If the above chemicals exist in the product, the total weight must be
less than 0.1% of the product
• Packaging must contain a brief statement discouraging improper
disposal and encouraging consultation with local authorities for
disposal requirements or recycling opportunities as specified in RA
9003
NON-CSE PRODUCT: PAINTS AND VARNISHES
JUSTIFICATION:
• Substance related specifications correspond to GPP specifications in
Malaysia and Hongkong, and specifications of GCP.
• Mercury and most of its compounds are extremely toxic. Their use is
banned in many parts of the world.
EVIDENCE:
• Statement that product does not contain hazardous substances.
• Supplier must submit Material Safety Data Sheets (MSDS)
• Declaration of compliance to recycling and safe disposal of waste
NON-CSE PRODUCT: PAINTS AND VARNISHES
VERIFICATION:
• Independent testing can be carried out by Intertek Testing Services
Philippines Inc. and for some substances by Sentrotek and SGS
Philippines.
NON-CSE PRODUCT: FOOD AND CATERING
SERVICES
SCOPE:
Which range from Quick Service Restaurants, Canteens and Cafeterias, to
Catering Services, Casual Dining Establishments, and Fine-Dining
Restaurants.
KEY ENVIRONMENTAL IMPACT
• Consumption of raw materials and destruction of ecosystems related
to the purchased products;
• Water and energy consumption during processing of food
• Generation of waste through packaging and food waste.
GPP APPROACH
• Purchase of environmentally responsible food and beverages
• Ensures water and energy efficiency
• Offered under sustainable practices
• Decrease the quantity of packaging used and waste produced
NON-CSE PRODUCT: FOOD AND CATERING
SERVICES
PRODUCT SPECIFICATIONS:
• Supplier shall have its own environmental policy (environmental
procurement, reduction of waste and energy consumption, and water
saving)
• Produced in sustainable way eg produced according to good
agricultural practices, organic, no products from threatened species)
• Supplier shall provide vegetarian offer
• Eliminate use of non-essential disposable products like plastic bags,
single-use utensils, etc.
• Use of recycled materials
NON-CSE PRODUCT: FOOD AND CATERING
SERVICES
JUSTIFICATION:
• Asking for an environmental policy provides direction and requires the
supplier to reflect on the environmental impact.
EVIDENCE:
• Statement that service suppliers have met criteria.
• Submit a copy of the environmental policy signed by their Director or
counterpart and indicate how is it made accessible to guests and staff
personnel.
• Packaging samples
• Proof of internal waste reduction management initiatives
NON-CSE PRODUCT: FOOD AND CATERING
SERVICES
VERIFICATION:
• On-site visit
• For the characteristics of food, invoices can be checked
• Energy efficient indoor lighting relates to the use of compact
fluorescent lamps and LEDs.
NON-CSE PRODUCT: VEHICLES
SCOPE:
Light duty vehicles and light-duty trucks for ordinary use
FUTURE CRITERIA:
The ABC is the budget for the contract duly approved by the Head of
the Procuring Entity, as provided for in:
1. The GAA and/or continuing appropriations, in the case of NGAs;
2. The corporate budget for the contract approved by the governing
board, pursuant to E.O. No. 518, series of 1979, in the case of GOCCs
and GFIs; and R.A. No. 8292, in the case of SUCs; or
3. The budget approved by the Sanggunian in the case of LGUs.
Thus, the ABC referred to in R.A. 9184 and its R-IRR basically refers to
the proposed budget for the project approved by the Head of the
Procuring Entity based on the APP as consolidated from various PPMPs.
75
APPROVED BUDGET FOR THE CONTRACT (ABC)
76
DETERMINING THE ABC
77
DETERMINING THE ABC
Cost for securing all types and forms of securities other than
cash (e.g. premiums for surety bond, bank fees and other
charges to be incurred by the bidder in obtaining bid,
performance and warranty securities); and
Currency valuation adjustment for contracts with foreign
component.
Acquisition Cost
Operation Cost
Replacement/Repair Cost
Disposal Cost
78
PROCUREMENT MILESTONES
79
PROCUREMENT MILESTONES
80
PROCUREMENT MILESTONES
81
METHOD OF PROCUREMENT
82
COA – GUIDE ON AUDIT OF PROCUREMENT
(GAP)
3.2. Annual Procurement Plan (APP) – the requisite document
that the agency must prepare to reflect the entire
procurement activity (i.e., goods, services, civil works to be
procured) that it plans to undertake within the calendar year.
This document contains the following information:
3.2.1. Name of the procurement program/project;
3.2.2. Project management office or end-user unit;
3.2.3. General description of the procurement;
3.2.4. Procurement method to be adopted;
3.2.5. Time schedule for each procurement activity;
3.2.6. Source of fund; and
3.2.7. Approved Budget for the Contract.
83
COA – GAP CHECKLIST
84
COA – GAP CHECKLIST
85
Two girls ate dinner together. They
both ordered iced tea. One girl drunk
them very fast and had finished five in
the time it took the other to drink just
one. The girl who drunk one died while
the other survived. However, all of the
drinks that were serve turned out to
contain poison. How did the girl who
drank the most survive?
ANSWER:
The poison was in the ice. When
the girl drank the iced tea, the ice
was still fully frozen. Gradually,
as the ice cubes melted, the
poison was released into the
drink.
PREPARATION OF
BIDDING DOCUMENTS
Legal Reference : IRR Section 17
Purpose of Bidding Documents
(BDs)
To provide prospective bidders the basic
information that they need to prepare
responsive bids for the contract (IRR Section 5
f)).
PURPOSE OF PBDs
89
2016 IRR AMENDMENTS
90
AVAILABILITY OF BIDDING
DOCUMENTS
91
WHEN AVAILABLE?
RATIONALE:
92
2016 IRR AMENDMENTS
93
REMINDERS
PBDs to be used by all NGAs, GFIs, SUCs, GOCCs and LGUs for
fully domestically-funded projects.
94
PREPARATION OF
BIDDING DOCUMENTS
Content of Contract-Specific BDs
oSection I. Invitation to Bid (IB)
oSection II. Instructions to Bidders (ITB)
oSection III. Bid Data Sheet (BDS)
oSection IV. General Conditions of Contract (GCC)
oSection V. Special Conditions of Contract (SCC)
oSection VI. Schedule of Requirements
oSection VII. Technical Specifications of Goods and
Services
oSection VIII. Bidding Forms (BFs)
REMINDERS
96
SPECIFIC
CONTENTS OF
BIDDING
DOCUMENTS
INVITATION TO BID (IB)
Section I
Purpose
Notice to interested suppliers and to the general
public of the proposed procurement for a specific
contract. It shall also provide basic information
that will enable prospective bidders to decide
whether or not to participate in the procurement
at hand.
ESSENTIAL CONTENTS
1. Name of the contract to be bid and a brief description;
99
ESSENTIAL CONTENTS
100
ESSENTIAL CONTENTS
4. Period of availability of the Bid Docs, place where the Bid Docs may be
secured, website where the Bid Docs may be downloaded and, where
applicable, price of the Bid Documents “acquired” by virtue of
GPPB Resolution Nos.
04 and 25-2012
101
ESSENTIAL CONTENTS
5. Date, time, place of the deadline for the submission and receipt of bid
requirements, conduct of pre-bid conference, if any, submission and
receipt of bids and the opening of bids;
6. The deadline for the submission and receipt of bids from the last day of
posting of the Invitation to Bid
102
ESSENTIAL CONTENTS
7. Reservation Clause
103
INVITATION TO BID (IB)
Section I
GPPB Resolution No. 23-2017
“Amendments to the Philippine Bidding Documents for the Procurement of Goods”
Original Amended
Notes on the Invitation To Bid Notes on the Invitation To Bid
Apart from the essential items listed in the Apart from the essential items listed in the
Bidding Documents, the Invitation To Bid Bidding Documents, the Invitation To Bid
should also indicate the following: should also indicate the following:
--------- ---------
(c) The deadline for the submission and (c) The deadline for the submission and
receipt of bids from the last day of posting receipt of bids; and
of the Invitation To Bid; and
You intercepted this coded
message sent by an enemy
operative:
YYURYYUBICURYY4ME
ANSWER:
Purpose
oProvides information necessary for bidders to
prepare responsive bids for the contract to be
procured, in accordance with the
requirements of the Procuring Entity. Also
provides information on Bid submission,
opening, and evaluation, post-qualification,
and award.
NOTE: Section II contains provisions that are to
be used unchanged
ESSENTIAL CONTENTS
108
ESSENTIAL CONTENTS
CONFLICT OF INTEREST
The presence of a conflict of interest is a ground for
Bidders’ disqualification.
109
ESSENTIAL CONTENTS
CONFLICT OF INTEREST
111
ESSENTIAL CONTENTS
Disclosure of Relations (Sec. 47, IRR of R.A. 9184) shall apply to
the following persons:
112
ESSENTIAL CONTENTS
113
ESSENTIAL CONTENTS
Sample Omnibus Sworn Statement
• AFFIDAVIT
• I, [Name of Affiant], of legal age, [Civil Status], [Nationality], and residing at [Address of Affiant], after having been duly sworn in accordance with law,
do hereby depose and state that:
• 1. Select one, delete the other:
• If a sole proprietorship: I am the sole proprietor or authorized representative of [Name of Bidder] with office address at [address of Bidder];
• If a partnership, corporation, cooperative, or joint venture: I am the duly authorized and designated representative of [Name of Bidder] with office
address at [address of Bidder];
• 2. Select one, delete the other:
• If a sole proprietorship: As the owner and sole proprietor, or authorized representative of [Name of Bidder], I have full power and authority to do,
execute and perform any and all acts necessary to participate, submit the bid, and to sign and execute the ensuing contract for [Name of the Project] of
the [Name of the Procuring Entity], as shown in the attached duly notarized Special Power of Attorney;
• If a partnership, corporation, cooperative, or joint venture: I am granted full power and authority to do, execute and perform any and all acts necessary
to participate, submit the bid, and to sign and execute the ensuing contract for [Name of the Project] of the [Name of the Procuring Entity], as shown in
the attached [state title of attached document showing proof of authorization (e.g., duly notarized Secretary’s Certificate, Board/Partnership Resolution,
or Special Power of Attorney, whichever is applicable;)];
• 3. [Name of Bidder] is not “blacklisted” or barred from bidding by the Government of the Philippines or any of its agencies, offices, corporations, or
Local Government Units, foreign government/foreign or international financing institution whose blacklisting rules have been recognized by the
Government Procurement Policy Board;
• 4. Each of the documents submitted in satisfaction of the bidding requirements is an authentic copy of the original, complete, and all statements and
information provided therein are true and correct;
114
ESSENTIAL CONTENTS
Sample Omnibus Sworn Statement
• Omnibus Sworn Statement
• REPUBLIC OF THE PHILIPPINES )
• CITY/MUNICIPALITY OF ______ ) S.S.
• AFFIDAVIT
• 5. [Name of Bidder] is authorizing the Head of the Procuring Entity or its duly authorized representative(s) to verify all the documents submitted;
• 6. Select one, delete the rest:
• If a sole proprietorship: The owner or sole proprietor is not related to the Head of the Procuring Entity, members of the Bids and Awards
Committee (BAC), the Technical Working Group, and the BAC Secretariat, the head of the Project Management Office or the end-user unit, and
the project consultants by consanguinity or affinity up to the third civil degree;
• If a partnership or cooperative: None of the officers and members of [Name of Bidder] is related to the Head of the Procuring Entity, members of
the Bids and Awards Committee (BAC), the Technical Working Group, and the BAC Secretariat, the head of the Project Management Office or the
end-user unit, and the project consultants by consanguinity or affinity up to the third civil degree;
• If a corporation or joint venture: None of the officers, directors, and controlling stockholders of [Name of Bidder] is related to the Head of the
Procuring Entity, members of the Bids and Awards Committee (BAC), the Technical Working Group, and the BAC Secretariat, the head of the
Project Management Office or the end-user unit, and the project consultants by consanguinity or affinity up to the third civil degree;
• 7. [Name of Bidder] complies with existing labor laws and standards; and
• 8. [Name of Bidder] is aware of and has undertaken the following responsibilities as a Bidder:
• a) Carefully examine all of the Bidding Documents;
• b) Acknowledge all conditions, local or otherwise, affecting the implementation of the Contract;
• c) Made an estimate of the facilities available and needed for the contract to be bid, if any; and
• d) Inquire or secure Supplemental/Bid Bulletin(s) issued for the [Name of the Project].
• 9. [Name of Bidder] did not give or pay directly or indirectly, any commission, amount, fee, or any form of consideration, pecuniary or otherwise,
to any person or official, personnel or representative of the government in relation to any procurement project or activity
115
ESSENTIAL CONTENTS
Sample Omnibus Sworn Statement
• Omnibus Sworn Statement
• REPUBLIC OF THE PHILIPPINES )
• CITY/MUNICIPALITY OF ______ ) S.S.
• AFFIDAVIT
• IN WITNESS WHEREOF, I have hereunto set my hand this __ day of ___, 20__ at ____________, Philippines.
• _____________________________________
• Bidder’s Representative/Authorized Signatory
• SUBSCRIBED AND SWORN to before me this ___ day of [month] [year] at [place of execution], Philippines. Affiant/s is/are personally known to me and was/were
identified by me through competent evidence of identity as defined in the 2004 Rules on Notarial Practice (A.M. No. 02-8-13-SC). Affiant/s exhibited to me his/her
[insert type of government identification card used], with his/her photograph and signature appearing thereon, with no. ________ and his/her Community Tax
Certificate No. _______ issued on ____ at ______.
116
ESSENTIAL CONTENTS
117
ESSENTIAL CONTENTS
BID VALIDITY
119
ESSENTIAL CONTENTS
BID SECURITY
NOTE:
121
ESSENTIAL CONTENTS
BID SECURING DECLARATION
122
ESSENTIAL CONTENTS
2016 IRR
Clause 19.4 Each and every page of the Bid Form, including the Schedule
of Prices, under Section VIII hereof, shall be signed by the duly authorized
representative/s of the Bidder. Failure to do so shall be a ground for the
rejection of the bid.
123
ESSENTIAL CONTENTS
124
ESSENTIAL CONTENTS
NOTE:
125
ESSENTIAL CONTENTS
NOTE:
• The ORIGINAL Technical/Financial Envelope and the COPY
Envelopes shall be CONTAINED in ONE ENVELOPE.
• All envelopes shall have the required data.
• Procuring Entity not be responsible for misplaced bid docs
and premature opening.
126
ESSENTIAL CONTENTS
127
ESSENTIAL CONTENTS
128
ESSENTIAL CONTENTS
129
INSTRUCTIONS TO BIDDERS (ITB)
Section II
GPPB Resolution No. 36-2017
AMMENDMENT TO THE
5th EDITION OF THE PHILIPPINE BIDDING DOCUMENTS FOR THE PROCUREMENT OF GOODS
ORIGINAL AMENDED
Instruction to Bidders Clause 12.1(a)(i) Instruction to Bidders Clause 12.1(a)(i)
PhilGEPS Certificate of Registration and membership in accordance with PhilGEPS Certificate of Registration and membership in accordance with
Section 8.5.2 of the IRR, except for foreign bidders participating in the Section 8.5.2 of the IRR, except for foreign bidders participating in the
procurement by a Philippine Foreign Service Office or Post, which shall procurement by a Philippine Foreign Service Office or Post, which shall
submit their eligibility documents under Section 23.1 of this IRR: Provided, submit their eligibility documents under Section 23.1 of this IRR: Provided,
That the winning bidder shall register with the PhilGEPS in accordance That the winning bidder shall register with the PhilGEPS in accordance with
with Section 37.1.4 of this IRR. Section 37.1.4 of this IRR. For procurement to be performed overseas, it
shall be subject to the Guidelines to be issued by the GPPB.
136
STATEMENT OF SINGLE LARGEST COMPLETED
CONTRACT (GOODS)
SLCC shall indicate, for each contract, the following:
(1) name of the contract;
(2) date of the contract;
(3) Contract duration;
(4) owner’s name and address;
(5) kinds of Goods;
(6) amount of completed contracts, adjusted by the Bidder to current
prices using PSA’s consumer price index, if necessary for the
purpose of meeting the SLCC requirement
(7) date of delivery; and
(8) end user’s acceptance or official receipt(s) or sales invoice* issued
for the contract, if completed, which shall be attached to the
statements.
137
2016 IRR AMENDMENTS
Amendment in the PBDs to conform with the 2016 IRR.
The first envelope shall contain the following eligibility and technical
documents:
(a) Eligibility Documents –
Class “A” Documents:
(i) PhilGEPS Certificate of Registration and Membership in
accordance with Section 8.5.2 of the IRR of RA 9184, except for
foreign bidders participating in the procurement by a Philippine
Foreign Service Office or Post, which shall submit their eligibility
documents under Section 23.1 of the IRR of RA 9184, provided,
that the winning bidder shall register with the PhilGEPS in
accordance with Section 37.1.4 of the IRR of RA 9184.
138
2016 IRR AMENDMENTS
Submission and Receipt of Bids
NOTE:
• Bids must be received at the address and on or before the date and
time indicated in the BDS.
• Bids submitted after deadline shall be declared “LATE” and shall not
be accepted by the BAC.
• The BAC Secretariat shall notify in writing all bidders whose bids it
has received through its PhilGEPS-registered physical address or
official e-mail address. The notice shall be issued within seven (7)
cd from the date of the bid opening
140
ESSENTIAL CONTENTS
MODIFICATION OF BIDS
141
ESSENTIAL CONTENTS
WITHDRAWAL OF BIDS
142
INSTRUCTIONS TO BIDDERS (ITB)
Section II
GPPB Resolution No. 23-2017
“Amendments to the Philippine Bidding Documents for the Procurement of Goods”
Original Amended
13. Documents Comprising the Bid: 13. Documents Comprising the Bid:
Financial Component Financial Component
13.1 Unless otherwise stated in the BDS, 13.1 The financial component of the bid
the financial component of the bid shall shall contain the following:
contain the following:
BID DATA SHEET (BDS)
Section III
Purpose
NOTE:
145
BID DATA SHEET (BDS)
Section III
GPPB Resolution No. 23-2017
“Amendments to the Philippine Bidding Documents for the Procurement of Goods”
Original Amended
13.1 List any additional requirements or state 13.1 List any additional requirements or state
“No additional requirements.” “No additional requirements.”
15.4(b) Maintain the ITB Clause and state here 15.4(b)(i) Maintain the ITB Clause and state
“Not applicable”, “The price of the Goods shall here “Not applicable”, “The price of the Goods
be quoted DPP [state place of destination]”, or shall be quoted DPP [state place of
the applicable INCOTERMS for this Project. destination]”, or the applicable INCOTERMS for
this Project.
List here the incidental services that are 15.4(b)(ii) List here the incidental services that
required as part of the Bidder’s bid cross are required as part of the Bidder’s bid cross
referencing to the technical specifications and referencing to the technical specifications and
SCC as appropriate. SCC as appropriate.
If none, state “No incidental services are If none, state “No incidental services are
required.” required.”
GENERAL CONDITIONS OF
CONTRACT(GCC)
Section IV
Purpose
oProvide the standard terms and provisions of the
Contract applicable to all contracts in general,
without detailed information and data specific to the
contract at hand.
oThe GCC defines the contractual requirements and
obligations of both the Procuring Entity and the
merchant for the contract at hand.
23.3 23.5
GENERAL CONDITIONS OF
CONTRACT(GCC)
Section IV (5th Edition of PBD)
Original Amendment
GCC Clause 19. Liquidated Damages GPPB Reso No. 07-2019 dtd.
March 08, 2019
Subject to GCC Clause 18 and 22, if the Supplier Subject to GCC Clause 18 and 22, if the Supplier
fails to satisfactorily deliver any or all of the fails to satisfactorily deliver any or all of the Goods
Goods and/or perform the Services within the and/or perform the Services within the period(s)
period(s) specified in this Contract, inclusive of specified in this Contract, inclusive of duly granted
duly granted time extensions if any, the time extensions if any, the Procuring Entity shall,
Procuring Entity shall, without prejudice to its without prejudice to its other remedies under this
other remedies under this Contract and under Contract and under applicable law, deduct from
applicable law, deduct from the Contract Price, the Contract Price, as liquidated damages, the
as liquidated damages, the applicable rate of applicable rate of one tenth (1/10) of 1% of the
one tenth (1/10) of 1% of the cost of the cost of the unperformed portion for every day of
unperformed portion for every day of delay until delay until actual delivery or performance. The
actual delivery or performance. The maximum maximum deduction shall be 10% of the amount
deduction shall be 10% of the amount of of contract. Once the maximum is reached,
contract. Once the maximum is reached, the amount of liquidated damages reaches
Procuring Entity may rescind or terminate the 10%, the Procuring Entity may rescind or
Contract pursuant to GCC Clause 23, without terminate the Contract pursuant to GCC Clause
prejudice to other course of action and 23, without prejudice to other course of action
remedies open to it. and remedies open to it.
ANNEX “I” OF THE 2016 R-IRR OF RA
9184 OR GUIDELINES ON
TERMINATION OF CONTRACT
CONDITIONS Original OF CONTRACT(GCC) Amendment
Section IV (5th for
Item III(A). Termination
Edition
Default
ofGPPB
PBD)
Reso No. 07-2019 dtd.
March 08, 2019
In contracts for Goods In contracts for Goods
The Procuring Entity shall terminate a The following are grounds for
contract for default when any of the termination of contract for default:
following conditions attend its
implementation: a) Pursuant to Sec. 68 of the 2016 R-
IRR, the Procuring Entity may
a) Outside force majeure, the Supplier terminate the contract when outside
fails to deliver or perform any or all of force majeure, the Supplier fails to deliver
or perform any or all of the Goods within
the Goods within the period(s) specified
the period(s) specified in the contract, or
in the contract, or within any extension
within any extension thereof granted by
thereof granted by the Procuring Entity the Procuring Entity pursuant to a request
pursuant to a request made by the made by the Supplier prior to the delay,
Supplier prior to the delay, and such and such failure amounts to at least 10%
failure amounts to at least 10% of the of the contract price;
contract price;
GENERAL CONDITIONS OF
CONTRACT(GCC)
Section IV (5th Edition of PBD) (NEW)
Original Amendment
Item III(A). Termination of GPPB Reso No. 07-2019 dtd.
Contract March 08, 2019
b) As a result of force majeure, the b) Pursuant to Sec. 68 of the
Supplier is unable to deliver or 2016 R-IRR, the Procuring
perform any or all of the Goods, Entity may terminate the
amounting to at least 10% of the contract when, as a result of force
contract price, for a period of not majeure, the Supplier is unable to
less than sixty (60) calendar days deliver or perform any or all of the
after receipt of the Notice from the Goods amounting to at least 10% of
Procuring Entity stating that the the contract price, for a period of not
circumstance of force majeure is less than sixty (60) calendar days
deemed to have ceased: or after receipt of the Notice from the
Procuring Entity stating that the
circumstance of force majeure is
deemed to have ceased ;
GENERAL CONDITIONS OF
CONTRACT(GCC)
Section IV (5th Edition of PBD) (NEW)
Original Amendment
Item III(A). Termination for GPPB Reso No. 07-2019 dtd.
Default March 08, 2019
c) The Supplier fails to perform c) The Procuring Entity shall
ant other obligation under the terminate the contract when,
Contract. the Supplier fails to perform any
other obligations under the
Contract.
SPECIAL CONDITIONS OF
CONTRACT (SCC)
Section V
Purpose:
Content of SCC:
oIntended completion date
oStart date
oTerms and conditions of delivery
oInspection and Tests
158
GCC and SCC
PRICES
All bid prices are considered fixed prices, and therefore not
subject to price escalation during contract implementation,
except under extraordinary circumstances and upon prior
approval of the GPPB in accordance with Section 61 of R.A.
9184 and its IRR or except as provided in this Clause.
159
GCC and SCC
160
GCC and SCC
161
GCC and SCC
162
GCC and SCC
FORCE MAJEURE
Winning Bidder is not liable for delay in performance or other
failure to perform obligations under the Contract if such is
caused by force majeure.
“Force majeure” and “fortuitous event” interpreted to mean an
event which the Winning Bidder could not have foreseen, or
which though foreseen, was inevitable.
Does not include conditions the effects of which could have
been avoided with the exercise of reasonable by the Winning
Bidder.
Winning Bidder to promptly notify the PE if a force majeure
situation arises.
163
SCHEDULE OF REQUIREMENTS
Section VI
Purpose:
Purpose:
o Provide prospective bidders a clear, accurate and full
description of the Procuring Entity’s needs to enable
them to propose a solution to meet these needs.
Includes the standards that need to be met by the
supplier of the goods to be manufactured and services
to be rendered as set by the End User Unit in terms of
the physical, functional, performance, environmental
interface and design requirements.
o Also includes the testing parameters for goods, when
such testing is required in the contract.
TECHNICAL SPECIFICATIONS
Section VII
Purpose:
xxx xxx
We agree to abide by this Bid for the We agree to abide by this Bid for the
Bid Validity Period specified in the Bid Validity Period specified in the
BDS provision for ITB Clause 18.2 BDS provision for ITB Clause 17.1
and it shall remain binding upon us and it shall remain binding upon us
and may be accepted at any time and may be accepted at any time
before the expiration of that period. before the expiration of that period.
STANDARD RATES OF PBDs
173
COMPETITIVE BIDDING
NPM 80-2014
174
COMPETITIVE BIDDING
PROCESS (GOODS)
Advertisement/
Pre-Procurement Conference Pre-Bid Conference
Posting
178
REFERENCE TO BRAND NAMES
NPM 22-2013
179
ADVERTISEMENT/POSTING
OF INVITATION TO BID
Importance:
PhilGEPS website
PE’s Website, if available
Conspicuous Place
Website prescribed by the foreign
government/foreign or international funding
institution, in case of foreign funded
procurement
183
ADVERTISEMENT/POSTING
OF INVITATION TO BID
Charging of Fees
Reference: NPM-68-2013
Decision in charging fees for bidding documents, whether for the first bidding or any
subsequent re-bidding, depends upon the procuring entity, taking into account the need to
recover the cost of its preparation and development vis-à-vis the effects in competition and
participation of bidders.
However, fees must conform with the standard rates for the sale of bidding documents under GPPB
Res. No. 04-2012, which took effect on 4 September 2012.
189
PRE-BID CONFERENCE
NPM 49-2013
190
CLARIFICATION OF BIDDING
DOCUMENTS
Supplemental/Bid Bulletins– issued by BAC to answer
requests for clarification (query submitted 10 cd before
deadline) or interpretation, and upon BAC’s initiative to
clarify or modify any provision of Bidding Docs. (at least
7 cd before deadline for bids).
NPM 24-2013
192
PRE-BID CONFERENCE
(PBC)
Reference: NPM 48-2013
Sec. 22.1 of the IRR of RA 9184 provides that at least one
(1) pre-bid conference should be conducted by the
procuring entity for projects costing at least Php 1 Million,
in order to afford prospective bidders the opportunity to
inquire on or clarify any of the requirements, terms,
conditions, and specifications stipulated in the Bidding
Documents.
Supplemental Bulletin
BAC may issue a Supplemental
Bulletin to amend BDs at least
7 cd before the deadline for
receipt of bids (IRR Sec.
22.5.1).
SUPPLEMENTAL/BID
BULLETINS
Bid Bulletin
BAC may also issue a Bid Bulletin to clarify any
provision of the BDs in response to a request
from prospective bidders at least 10 cd before
the deadline for the receipt of bids (IRR Section
22.5.1).
BAC may, at its own initiative, also issue a Bid
Bulletin to clarify any provision of the BDs.
Submitted to the BAC on the date, time, and place specified in the Invitation
to Bid. Bids submitted after the deadline should not be accepted.
Date of submission should not be later than the following period from the
last day of posting of the Invitation to Bid (Sec. 25.4) (Sec. 25.5, 2016 IRR of
RA 9184)
201
SUBMISSION AND
RECEIPT OF BIDS
Bidders are no longer required to submit a written
LOI together with their application for eligibility as
previously required in IRR Part A of RA 9184.
NPM 101-2013
Bidders only have to submit their bids not later than the
deadline for the submission and receipt of bids, which can
be extended or rescheduled together with the opening of
bids as provided in Section 29 of the IRR of RA 9184.
NPM 55-2013
202
OPENING AND EVALUATION OF
1ST ENVELOPE
CONTENTS:
1. Eligibility requirements (Legal, financial and technical)
2. Bid Security
3. Technical specifications (Goods) / Project requirements
(Infra)
4. Omnibus sworn statement (New Form, Sec. 25.3, 2016 IRR)
Non-inclusion in blacklist Responsibilities of bidders
Authenticity of documents Labor laws and standards
Verification authority Non-payment (directly or
indirectly) any commission,
Signatory’s authority amount, fee, or any form of
Disclosure of relations consideration in relation to
any procurement project or
activity
203
OPENING AND EVALUATION OF
1ST ENVELOPE
Section 30 requires that the preliminary examination of
bids be conducted by merely checking for the presence
or absence of documentary requirements using a non-
discretionary “pass/fail” criterion.
NPM 54-2013
204
OPENING AND EVALUATION OF
1ST ENVELOPE
NPM 69-2013
205
OPENING AND EVALUATION OF
1ST ENVELOPE
206
OPENING AND EVALUATION OF
1ST ENVELOPE
3. Tax clearance per Executive Order 398, series of 2005, as finally reviewed
and approved by the BIR.
208
ELIGIBILITY REQUIREMENTS
GOODS
TECHNICAL:
1. Statement of all ongoing contracts.
2. Statement of SLCC
FINANCIAL:
1. Audited financial statement
2. NFCC computation
Class B Document
JVA or notarized statement from the partners that they will enter into joint
venture if awarded the contract.
209
ELIGIBILITY REQUIREMENTS
Section 8.5.2, 2016 IRR of RA 9184 - All bidders shall upload and
maintain in PhilGEPS a current and updated file of the following
Class “A” eligibility documents under Sections 23.1(a) and 24.1(a):
a) Registration Certificate;
b) Mayor’s/Business Permit or its Equivalent Document;
c) Tax Clearance;
d) Philippine Contractors Accreditation Board (PCAB) license and
registration; and
e) Audited Financial Statements.
210
ELIGIBILITY REQUIREMENTS
211
ELIGIBILITY REQUIREMENTS
212
ELIGIBILITY REQUIREMENTS
GPPB Circular 07-2017, dated 31 July 2017
1. All procurement projects advertised and/or posted after
the effectivity of the Circular, bidders may still submit their
Class “A” Eligibility Documents required to be uploaded and
maintained current and updated in the PhilGEPS pursuant
to Section 8.5.2 of the 2016 Revised IRR, or if already
registered in the PhilGEPS under Platinum Category, their
Certificate of Registration and Membership in lieu of their
uploaded file of Class “A” Documents, or a combination
thereof. In case the bidder opted to submit their Class “A”
Documents, the Certificate of PhilGEPS Registration
(Platinum Membership) shall remain as a post-qualification
requirement to be submitted in accordance with Section
34.2 of the 2016 Revised IRR of RA 9184.
213
ELIGIBILITY REQUIREMENTS
GPPB Circular 07-2017, dated 31 July 2017
2. For all procurement projects advertised and/or posted
starting May 01, 2017 until the effectivity of the Circular
(01 September 2017), procuring entities and bidders are
bound to observe the mandatory submission of their
PhilGEPS Certificate of Regitration under Platinum Category
in lieu of the Class “A” Documents required to be uploaded
and maintained current in the PhilGEPS, and
3. In cases where the advertisements or invitations for bids
were issued prior to May 01, 2017, Procuring Entities may
still allow bidders to submit either their Class “A”
Documents or the PhilGEPS Certificate of Registration under
the Platinum Category, or a combination thereof.
214
A man wanted to work, but he could not
log in to his computer terminal successfully.
He tried twice, but still his password did
not work. He suddenly remembered that
the passwords are reset every month for
security purposes. So, he called his boss
and said, “Hey boss, my password is out of
date.”
His boss replied, “Yes, that’s right. The
password is different. Listen carefully. I am
sure, you can figure out the new one. The
new one has the same amount of letters as
your old password, but only four of the
letters are the same.””Thanks boss.”With
that, the man could correctly log into his
station. What are both the new and old
passwords?
215
Answer:
The old one was “out
of date.” The new one
is “different.” Both
passwords contain
the letters d, f, e, and
t.
216
ELIGIBILITY REQUIREMENTS
2017-12-29
NPM No. 147-2017 Requesting Entity: MUNICIPALITY OF SAN ISIDRO
Issues Concern: GPPB Circular No. 07-2017
Details: Clarification on Section 4.1.1 of GPPB Circular No. 07-2017 specially its last sentence
which states:
In case the bidder opted to submit their Class “A” Documents, the Certificate of Registration
(Platinum Membership) shall remain as a post-qualification requirement to be submitted in
accordance with Sections 34.2 of the 2016 revised Implementing Rules and Regulations (IRR)
of Republic Act (RA) No. 9184.
[F]or all procurement projects advertised and/or posted on 2 September 2017 onwards, a bidder may submit
their Class “A” Eligibility Documents in lieu of the PhilGEPS Certificate of Registration and Membership, if it
has not yet obtained a Platinum Membership; or if already registered under Platinum category, their PhilGEPS
Certificate of Registration and Membership in lieu of the uploaded file of Class “A” Documents, or a
combination thereof, in the event that some Class “A” documents earlier submitted with PhilGEPS already
expired, but a renewal thereof had already been secured. In case the bidder submits only its Class “A”
Documents, the PhilGEPS Certificate of Registration and Membership (Platinum Membership) shall still be
submitted as part of the post-qualification documents required under Section 34.2 of the 2016 IRR of RA
9184.
In view of the foregoing, we wish to clarify that the last sentence of Section 4.1.1 of the GPPB Circular allows
the bidder, for purposes of bid submission, to submit only its Class “A” Documents without requiring its
PhilGEPS Certificate of Registration and Membership (Platinum Membership). We wish to stress, however,
that the requirement of the PhilGEPS Certificate of Registration is not completely dispensed with as the same
shall still be required to be submitted by the bidder during the post-qualification period.
217
ELIGIBILITY REQUIREMENTS
TECHNICAL:
1. Statement of all ongoing contracts.
2. Statement of SLCC
FINANCIAL:
1. NFCC computation or committed Line of Credit
219
ELIGIBILITY REQUIREMENTS
GOODS
Class B Document
JVA or notarized statement from the partners that they will enter into
joint venture if awarded the contract.
220
MAYOR’S PERMIT
221
TAX CLEARANCE
NPM 02-2013
222
TAX CLEARANCE
NPM 02-2016
223
TAX CLEARANCE
224
TAX DELINQUENCY VERIFICATION
CERTIFICATE
NPM 39-2014
225
COMMITTED LINE OF CREDIT
226
NET FINANCIAL CONTRACTING
CAPACITY (NFCC)
230
ELIGIBILITY REQUIREMENTS FOR
FOREIGN BIDDERS
TAX CLEARANCE FOR FOREIGN BIDDERS
NPM 02-2013
231
ELIGIBILITY REQUIREMENTS FOR
JOINT VENTURES
GOODS
WITH AN EXISTING JOINT VENTURE: submission of a valid joint
venture agreement
232
ELIGIBILITY REQUIREMENTS FOR
JOINT VENTURES
233
LEGAL ELIGIBILITY CRITERIA
GOODS
• General rule: 60% Filipino
• Foreign bidder allowed if:
1) Stated in treaty or international or executive agreement;
2) National of a country offering reciprocity rights to Filipinos;
3) Goods not available from local suppliers; or
4) To prevent situations that defeat competition or restrain trade
234
A man is headed to a mountain along with a lion, a goat,
and a basket of vegetables. On the way, he needs to cross
a river and the boat can only carry two things at a time. If
he takes the vegetables, the lion will eat the goat. If he
takes the lion, the goat will eat the vegetables. How does
he cross the river?
235
Trip 1: He takes the goat with him, leaving the lion and the vegetables
behind. On reaching the other riverbank, he drops off the goat.
Trip 2: He then comes back for the lion, leaving the vegetables behind.
On reaching the bank this time, he drops the lion, and again takes the
goat along.
Trip 3: He drops off the goat again and takes the vegetables with him
to the other shore.
Trip 4: Lastly, he comes back alone for the goat.
236
TECHNICAL ELIGIBILITY CRITERIA
Previous contract
Similar to the contract to be bid out (as defined by the
Bidding Documents)
Completed within a period as defined by the Bidding
Documents
25% of the ABC (expendable supplies)
50% of the ABC (non-expendable supplies)
- Based on the value of the previous completed
contract, as adjusted to current prices using the NSO
PSA consumer price index.
237
TECHNICAL ELIGIBILITY CRITERIA
238
TECHNICAL ELIGIBILITY CRITERIA
GOODS – SINGLE LARGEST COMPLETED CONTRACT
(Illustration)
Expendable Goods Non-expendable Goods
ABC = P1,000,000.00 ABC = P1,000,000.00
THUS: Previous contract should be at least THUS: Previous contract should be at least
239
FINANCIAL ELIGIBILITY CRITERIA
240
NFCC COMPUTATION
NPM 76-2013
242
BID SECURITY
Only 1 form of Bid Security is required to be submitted
244
BID SECURITY
Amount
Form of Bid Security Bid Security
(% = ABC)
a) Cash or cashier’s/manager’s check
245
BID SECURING DECLARATION
246
BID SECURING DECLARATION
Conditions:
The Bid Securing Declaration shall be enforced when the
bidder commits any act resulting to the forfeiture of bid
security under:
248
DISCLOSURE OF RELATIONS
249
OPENING AND EVALUATION OF
2ND ENVELOPE
CONTENTS:
250
DETAILED EVALUATION
OF BIDS
Purpose is to determine the Lowest Calculated Bid
(LCB), by:
1. Establishing correct calculated prices of bids; and
2. Ranking calculated total bid prices from lowest to
highest
251
DETAILED EVALUATION
OF BIDS
In case of Discrepancies:
252
DETAILED EVALUATION
OF BIDS
No Contact Rule - prohibition on communication w/ bidders
from bid evaluation until award of contract.
The “no contact” rule applies only to those whose bids are
being evaluated by the BAC after passing the preliminary
examination until the issuance of Notice of Award.
254
DETAILED EVALUATION OF
BIDS
NPM 111-2014 Lowest Bid “as read” as the LCB
265
POST-QUALIFICATION
266
POST-QUALIFICATION
If the BAC verifies any of these deficiencies to be due to the bidder's fault or
negligence, the BAC shall disqualify the bidder from the award, for the
procurement of Goods. (Sec. 34.3(b), 2016 IRR of RA 9184)
268
POST-QUALIFICATION
NPM 27-2013
269
POST-QUALIFICATION
NPM 25-2013
270
RECOMMENDATION OF AWARD
271
RECOMMENDATION OF AWARD
272
FAILURE OF BIDDING
GROUNDS:
1) No bids received
2) Bids received but no one was eligible
3) All bids failed to post qualify
4) Someone post qualified but refused w/o justifiable
cause to accept the award.
273
FAILURE OF BIDDING
EFFECTS:
274
RESERVATION CLAUSE
HOPE reserves the right to:
◦ Reject any and all bids;
◦ Declare a failure of bidding; or
◦ Not award the contract.
(Sec. 41, IRR of RA 9184)
GROUNDS:
1. Prima facie evidence of collusion;
2. BAC is found to have failed in following the prescribed bidding
procedures;
3. For justifiable reasons, the award of contract will not redound to the
benefit of the Government:
Physical and economic conditions have significantly changed;
Project is no longer necessary
Source of funds for the project has been withdrawn/reduced.
275
AWARD OF CONTRACT
The BAC Sec shall post the NOA in the PhilGEPS, PE’s
websites and in any conspicuous place within 3 cd
from its issuance.
276
AWARD OF CONTRACT
277
PERFORMANCE SECURITY
278
POST-QUALIFICATION OF
BIDDER W/ LCB
Failure to enter contract and post performance security:
Lowest Calculated and Responsive Bidder fails, refuses or is unable to
submit documents (in the post-qualification process), or enters into
contract, or post performance security – bid security forfeited and
appropriate sanctions imposed except where such failure, refusal or
inability not thru fault of the bidder
Amount
Form of Performance Security Performance Security
(% equal to the Contract Price)
a) Cash or cashier’s/manager’s check
5%
b) Bank guarantee/draft or
Irrevocable LC
c) Surety bond callable upon
demand 30%
280
CONTRACT SIGNING
281
PERIOD TO COMPLETE
PROCUREMENT PROCESS
PROCUREMENT PROCESS
From Opening of Bids to Award of Contract shall
NOT EXCEED 3 MONTHS
282
NOTICE TO PROCEED
The BAC Sec shall post the NTP and the approved
contract in the PhilGEPS and PE’s websites within 15 cd
from the issuance of the NTP.
283
WARRANTY SECURITY
Section 62
Minimum period of 3 months for Expendable
Minimum period of 1 year for Non-Expendable
GPPB Resolution No. 30-2017
In the form of: dated July 31, 2017
1. Retention money is 10% at least 1% but not to exceed five
percent (5%) of every progress payment or
2. A Special Bank Guarantee at least 1% but not to exceed five
percent (5%) of the total contract price
Released after the Warranty Period provided that the delivered
goods are free from patent and latent defects and all imposed
conditions have been fully met
284
LIQUIDATED DAMAGES
285
LIQUIDATED DAMAGES
286
CONTRACT DELIVERY EXTENSION
2010-03-09
NPM No. 009-2010 Requesting Entity: Office of the ACoFAS for Logistics
Issues Concern: Contract Delivery Extension
Details: Clarification on the following:
1. May the procuring entity grant several extensions in the delivery of goods
upon determination that the grounds cited by the supplier are meritorious?
Yes, the procuring entity may grant several extensions in the delivery
period as long as these extensions are based on meritorious grounds.
2. If yes, what is the maximum period for every extension?
Based on the relevant provisions of the Generic Procurement Manual,
each extension should not exceed the initial delivery period as stated
in the original contract (Volume 2, p. 108). It bears stressing,
however that in every grant of extensions, the procuring entity must
validate the reasons cited by the supplier and determine that
extension is based on meritorious grounds.
287
RECOMMENDED EARLIEST TIME AND MAXIMUM
PERIOD ALLOWED FOR PROCUREMENT OF GOODS
Section Procurement Min. CD for Earliest Possible Maximum CD Maximum Conditions/
Activity Activity Time Allowed Period Remarks
289
OUTLINE
I. Procurement Standards
II. Alternative Methods
1. Limited Source Bidding*
2. Direct Contracting
3. Repeat Order
4. Shopping
5. Negotiated Procurement
290
OUTLINE
5. Negotiated Procurement:
a. Two Failed Biddings h. Defense Cooperation Agreement*
b. Take Over Contracts i. Small Value Procurement
c. Emergency Cases j. Lease of Real Property and Venue
d. Adjacent or Contiguous k. NGO Participation*
e. Agency-to-Agency l. Community Participation*
f. Scientific, Scholarly or Artistic Work, m. UN Agencies, International
Exclusive Technology and Media Organizations or International
Services Financing Institutions*
g. Highly Technical Consultants
291
PROCUREMENT STANDARD
292
PROCUREMENT STANDARD
EXCEPTION
Alternative methods shall be resorted ONLY:
For any change in the
1. In highly exceptional case
2. To promote economy and efficiency method of procurement, the
3. Justified by conditions specified in IRR APP shall be updated first
4. prioramended)
GPPB approval as required under EO 423, S. 2005 (as to the conduct of the
procurement activity.
293
Update!
Executive Order 34
Signed 17 July 2017
295
1. LIMITED SOURCE BIDDING
APPLICABILITY:
CONDITIONS:
Highly specialized types where only a few bidders are known
to be available, or
Major plant components beneficial to limit bidding to known
qualified bidders to maintain uniform quality and
performance of the plant
296
1. LIMITED SOURCE BIDDING
297
1. LIMITED SOURCE BIDDING
PRE-SELECTION PROCEDURE : IF PE is a RELEVANT
GOVERNMENT AUTHORITY
GPPB Resolution 06-2012
PE posts GPPB-TSO
procurement acknowledges receipt
opportunity and and posts the list in
conducts LSB the website
298
1. LIMITED SOURCE BIDDING
Relevant
Request for a
Government
List from RGA
Authority?
Competitive
Bidding
299
2. DIRECT CONTRACTING
300
2. DIRECT CONTRACTING
APPLICABILITY:
301
2. DIRECT CONTRACTING
CONDITIONS: (Continuation)
302
DIRECT CONTRACTING
Procedure:
The BAC shall prepare the RFQ or pro-forma invoice together with the
terms and conditions of sale, and shall send the same to the
identified direct supplier.
The BAC shall recommend to the HOPE the award of contract in favor
of the supplier. Award of contract shall be made in accordance with
Section IV(L) of this Guidelines.
3. REPEAT ORDER
304
3. REPEAT ORDER
APPLICABILITY:
CONDITIONS:
1. Same or lower unit prices than those in the original contract,
provided that such prices are still the most advantageous to the
GOP after price verification;
2. No splitting of contracts, requisitions and Purchase Orders;
305
3. REPEAT ORDER
CONDITIONS: (Continuation)
3. Availed of within 6 months from the date of the NTP arising from
the original contract, provided that there has been a partial delivery,
inspection and acceptance of the goods within the same period;
4. Not to exceed 25% of the quantity of each item in the original
contract;
5. Original contract awarded through competitive bidding; and
6. The goods under the original contract must be quantifiable, divisible
and consisting of at least four (4) units per item
306
REPEAT ORDER
Procedure:
i. Upon determination of the need to replenish the goods earlier procured through
competitive bidding, the End-User unit shall prepare the necessary Purchase
Request for the procurement of additional goods, after a careful study and
confirmation of the prevailing market price of the goods to be re-ordered and
comparing this with the price of the goods in the original contract, accompanied
by the appropriate justification why the re-ordering is being pursued.
ii. When all the conditions are present, the BAC shall recommend to the HOPE the
award of contract through Repeat Order. Award of contract shall be made in
accordance with Section IV(L) of this Guidelines.
1. TO WAIT
2. THE VALUE
3. VAIN TEA
4. SICK RATE
5. LONG QUOTE
6. LITURGY
7. SURVEY TEST
308
4. SHOPPING
309
4. SHOPPING
The phrase “ordinary or regular office supplies” are those supplies,
commodities, or materials which are necessary in the transaction
of official business, and consumed in the day-to-day operations.
This will not include services such as repair and maintenance of
equipment and furniture, as well as trucking, hauling and related
analogous services.
310
4. SHOPPING
311
4. SHOPPING
The BAC shall send the RFQs to at least three (3) suppliers of known
qualifications, and at least three (3) price quotations must be
obtained.
The deadline for submission may be extended thrice, if none or less than the
required number of quotations are received.
In case no supplier responded after the third extension, the BAC shall conduct
a mandatory review in accordance with Section IV(K) of Annex H.
312
4. SHOPPING
313
4. SHOPPING
314
4. SHOPPING
315
4. SHOPPING
NPM 019-2014
316
4. SHOPPING
• NPM 127-2014
• Requesting Entity: Ms. Edcel Nacion
• Issues Concern: Shopping and Request for Quotation
• Details
• In Shopping, whether the requirement for three (3) quotations
is met when only one supplier offered a price while the other
two suppliers indicated "NONE" in compliance with the
Request for Quotation (RFQ) and the Guidelines for Shopping
and Small Value Procurement (Guidelines).
317
4. SHOPPING
318
5.a NEGOTIATED PROCUREMENT -
SMALL VALUE PROCUREMENT
APPLICABILITY:
The BAC shall prepare and send the RFQs/RFPs to at least three (3)
suppliers, contractors or consultants of known qualifications.
Receipt of at least one (1) quotation/proposal is sufficient to
proceed with the evaluation thereof.
319
5.a NEGOTIATED PROCUREMENT -
SMALL VALUE PROCUREMENT
•
5.a NEGOTIATED PROCUREMENT -
SMALL VALUE PROCUREMENT
THRESHOLD:
NGAs, GOCCs, GFIs, SUCs and Autonomous Regional Government–
PhP1,000,000
LGUs:
Maximum Amount (in Philippine Pesos)
Classification
Province City Municipality
1st Class 1,000,000 1,000,000 200,000
2nd Class 1,000,000 1,000,000 200,000
3rd Class 1,000,000 800,000 200,000
4th Class 800,000 600,000 100,000
5th Class 600,000 400,000 100,000
6th Class 400,000 200,000 100,000
In the case of Barangays, the maximum amount is PhP50,000
321
The PE should be able to
SHOPPING AND SMALL VALUE produce supporting
documents that it has
PROCUREMENT invited at least 3
suppliers.
PROCEDURAL GUIDELINES:
Post in PhilGEPS, PE’s Send RFQ/RFP to at
website and conspicuous least 3 suppliers
Prepare place for 3 cd *May be 1 in case of 52.1(a)
RFQ/RFP *Except 52.1(a) and ABC 50k and *Receipt of 3 RFQs for 52.1(b)
below is mandatory
*Extend deadline if no quotation is Receipt of 1 RFQ in SVP will
received suffice
322
SHOPPING and SMALL VALUE
PROCUREMENT
323
A man lives in the penthouse of an apartment
building. Every morning he takes the elevator
down to the lobby and leaves the building.
Upon his return, however, he can only travel
halfway up in the lift and has to walk the rest
of the way unless it's raining. What is the
explanation for this?
324
THE MAN IS A HOBBIT
326
5.b NEGOTIATED PROCUREMENT -
TWO FAILED BIDDINGS
PROCEDURAL GUIDELINES
- Disqualified bidders
in previous biddings
for the project shall
also be invited 2 Failed Mandatory Preparation of
- Even if only one (1) Competitive Review RFQ/Bid docs
bidder should Bidding/LSB
respond, the BAC
shall proceed with the
negotiation
Invite at least
three (3) Submission and
Negotiation opening of best Awarding of
suppliers/
and final offer contract
contractors/
consultants Requirements, guidelines,
documents, clarifications, or other
information relative to the
negotiations shall be communicated
on an equal basis.
327
5.b NEGOTIATED PROCUREMENT -
TWO FAILED BIDDINGS
328
5.b NEGOTIATED PROCUREMENT -
TWO FAILED BIDDINGS
329
5.b NEGOTIATED PROCUREMENT -
TWO FAILED BIDDINGS
GPPB RESOLUTION NO. 30-2016 AND CIRCULAR 05-2016 BOTH
DATED DECEMBER 20, 2016
(Period for the conduct of Re-bidding and Negotiated Procurement
under Two Failed Biddings Modality)
a) The BAC shall endeavor to conduct the re-bidding of a procurement project
immediately, but it should not exceed fifteen (15) days after the declaration of the
first failure of bidding under Section 35 of RA and 2016 R-IRR. The period may be
extended up to 30 days upon approval of the HoPE;
b) The same period shall be observed for the conduct of Negotiated Procurement
under Two Failed Biddings modality reckoned from the declaration of the 2 nd failure
of bidding; and
c) If the procurement cannot be undertaken within such periods, the BAC shall make
a report to the HoPE so that the latter can make the appropriate decision to facilitate
the procurement or take other proper action.
330
5.c NEGOTIATED PROCUREMENT -
EMERGENCY CASES
APPLICABILITY:
331
5.c NEGOTIATED PROCUREMENT -
EMERGENCY CASES
CONDITIONS:
332
5.c NEGOTIATED PROCUREMENT -
EMERGENCY CASES
In all instances, the HoPE shall confirm in writing the existence and
veracity of the ground/s relied upon before approving the contract.
Considering that the underlying reason of this modality relates to “time
element”, the PE should consider appropriate timing or the proximity of
time between the actual procurement activity to be conducted and the
emergency sought to be addressed.
When the reason or cause for the emergency has already been abated,
adoption of competitive bidding shall be considered.
When the ground is based on imminent danger to life during a state of
calamity, there must be a declaration by a competent authority of a state
of calamity before any procurement activity may be undertaken.
333
5.d NEGOTIATED PROCUREMENT -
TAKE-OVER OF CONTRACTS
APPLICABILITY:
334
5.d NEGOTIATED PROCUREMENT -
TAKE-OVER OF CONTRACTS
CONDITIONS:
335
5.d NEGOTIATED PROCUREMENT -
TAKE-OVER OF CONTRACTS
The BAC shall post-qualify and negotiate starting with the 2nd LCB or
HRB at the said bidder’s original bid price, then on to the next if
Authority to negotiate
negotiation fails. contracts for projects under
this modality shall be subject
to prior approval by the
If negotiation fails, the BAC may either: HoPE.
1. Invite a short list of at least three (3) suppliers, contractors or
consultants to submit bids and negotiate starting with the LCB or
HRB; or
2. Resort to any other appropriate alternative method of procurement.
336
8. LAUGH IS
9. TEA BALL
10. LOVING A NAME
11. STD
12. SHE FEEL YOU
13. SHE KISS
14. THE RICH ZOO
15. BIRDIE
341
5.f NEGOTIATED PROCUREMENT -
AGENCY-TO-AGENCY
342
5.f NEGOTIATED PROCUREMENT -
AGENCY-TO-AGENCY
APPLICABILITY:
All procurement to be undertaken by the Servicing Agency, including
those required for the project, shall be governed by the provisions of RA
9184.
All projects undertaken under A-to-A shall be subject to pertinent
budgeting, accounting, and auditing rules and regulations.
343
5.f NEGOTIATED PROCUREMENT -
AGENCY-TO-AGENCY
CONDITIONS:
1. The PE shall justify that entering into an A-to-A with the Servicing
Agency is more efficient and economical to the government;
2. The Servicing Agency has the mandate to deliver the goods and
services required to be procured or to undertake the infrastructure
project or consultancy required by the Procuring Agency;
3. Servicing Agency has the absorptive capacity to undertake the
project;
4. Servicing Agency owns or has access to the necessary tools and
equipment required for the project;
344
5.f NEGOTIATED PROCUREMENT -
AGENCY-TO-AGENCY
CONDITIONS:
345
5.f NEGOTIATED PROCUREMENT -
AGENCY-TO-AGENCY
PROCEDURAL GUIDELINES:
The End-User
The HoPE shall
The End-User shall secure a
enter into a MOA
shall justify to the certificate from The BAC shall
with the
BAC that the the relevant issue a
Servicing
resort to A-to-A officer of the Resolution
Agency upon
is more efficient Servicing recommending
approval of the
and economical Agency that the the use of A-to-A
BAC
to the latter complies to the HoPE.
recommendation
government. with the
.
conditions.
346
5.g NEGOTIATED PROCUREMENT
SCIENTIFIC, SCHOLARLY OR ARTISTIC WORK,
EXCLUSIVE TECHNOLOGY AND MEDIA SERVICES
347
5.g NEGOTIATED PROCUREMENT
SCIENTIFIC, SCHOLARLY OR ARTISTIC WORK,
EXCLUSIVE TECHNOLOGY AND MEDIA SERVICES
APPLICABILITY:
All types of Procurement involving:
348
5.g NEGOTIATED PROCUREMENT
SCIENTIFIC, SCHOLARLY OR ARTISTIC WORK,
EXCLUSIVE TECHNOLOGY AND MEDIA SERVICES
APPLICABILITY: (Continuation)
349
5.g NEGOTIATED PROCUREMENT
SCIENTIFIC, SCHOLARLY OR ARTISTIC WORK,
EXCLUSIVE TECHNOLOGY AND MEDIA SERVICES
CONDITIONS:
1. End-User shall conduct a market study and determine the
probable sources to justify the need to procure through this
negotiated modality;
2. The study should confirm that the supplier, contractor or
consultant could undertake the project at more advantageous
terms; and
3. The market study must be conducted prior to the commencement
of the procurement process.
350
5.i NEGOTIATED PROCUREMENT
DEFENSE COOPERATION AGREEMENT
APPLICABILITY:
Goods and Consulting Services to be used by AFP
major defense equipment or materiel
CONDITIONS:
1. Prior approval of the President;
2. Expertise or capability required is not available locally;
3. DND Secretary has determined that the interests of the country shall be
protected by negotiating directly with an agency or instrumentality of
another country with existing defense cooperation agreement or
diplomatic relations with the Philippines; and
4. Performance security under §39 of IRR of RA 9184 shall be required to
supplier
357
5.j NEGOTIATED PROCUREMENT
LEASE OF REAL PROPERTY AND VENUE
358
5.j NEGOTIATED PROCUREMENT
LEASE OF REAL PROPERTY AND VENUE
APPLICABILITY:
Goods (Real Property and Venue)
359
5.j NEGOTIATED PROCUREMENT
LEASE OF REAL PROPERTY AND VENUE
CONDITIONS:
360
5.j NEGOTIATED PROCUREMENT
LEASE OF REAL PROPERTY AND VENUE
The BAC shall invite at least three (3) prospective lessors/venues
within the vicinity of the selected location to submit sealed price
The RFQ is not required to
quotations. be posted in the PhilGEPS
be posted in the PhilGEPS
website
Receipt of at least one (1) quotation is sufficient to proceed with the
evaluation.
361
5.k NEGOTIATED PROCUREMENT -
NGO PARTICIPATION
APPLICABILITY:
CONDITION:
Appropriation law or ordinance earmarks an amount to be
contracted to NGOs
PE may opt to:
1. Conduct public bidding; or
2. Enter into a MOA with an NGO, subject to the guidelines issued
by the GPPB for the purpose
362
5.l NEGOTIATED PROCUREMENT -
COMMUNITY PARTICIPATION
APPLICABILITY:
Delivery of goods, including non-consulting services and simple
infrastructure projects
CONDITION:
In the interest of project sustainability or to achieve certain
specific social objectives
PROCEDURE:
Subject to Community Participation Procurement Manual
(CPPM), approved for adoption on 23 May 2014 (GPPB
Resolution No. 09-2014
363
5.l NEGOTIATED PROCUREMENT -
COMMUNITY PARTICIPATION
THRESHOLDS:
MAXIMUM AMOUNT
PROCURING ENTITY (In Philippine Peso)
Goods Infrastructure Projects
364
5.m NEGOTIATED PROCUREMENT -
UN AGENCIES, INTERNATIONAL ORGANIZATIONS OR
INTERNATIONAL FINANCING INSTITUTIONS
APPLICABILITY:
CONDITIONS:
Procurement from UN Agencies, IOs or IFIs, of any of the following:
a. Small quantities of off-the-shelf goods, primarily in the fields of education and
health;
b. Specialized products where the number of suppliers is limited; or
c. Goods, Infrastructure Projects and Consulting Services, involving advanced
technologies, techniques and innovations not locally available as certified by the
HoPE,.
365
DOCUMENTARY REQUIREMENTS
Alternative Modality Mayor’s/ Professional PhilGEPS PCAB NFCC Income/ Omnibus
Business License /CV Reg. License (Infra.) Business Sworn
Permit (Consulting Number (Infra.) Tax Statement
Services) Return
Direct Contracting
[Section 50] For ABCs
above
P500K
Shopping [Sec 52.1(b)]
Emergency Cases
(Section 53.2)] For For ABCs For ABCs
ABCs above above P500K
GPPB Res.
above P500K
21-2017
P500K dated May 30,
2017
366
DOCUMENTARY REQUIREMENTS
Alternative Modality Mayor’s/ Professional PhilGEPS PCAB NFCC Income/ Omnibus
Business License /CV Reg. License (Infra.) Business Sworn
Permit (Consulting Number (Infra.) Tax Statement
Services) Return
Take-Over of Contracts
(Section 53.3.2; for
new bidders)
Adjacent/ Contiguous
(Section 53.4)
Scientific, Scholarly or
Artistic Work, For ABCs
Exclusive Technology above
and Media Services P500K
(Section 53.6)
367
DOCUMENTARY REQUIREMENTS
Alternative Modality Mayor’s/ Professional PhilGEPS PCAB NFCC Income/ Omnibus
Sworn
Business License /CV Reg. License (Infra.) Business
Statement
Permit (Consulting Number (Infra.) Tax
Services) Return
Highly Technical Consultant
(Section 53.7)
Small Value Procurement
(Section 53.9) For ABCs For ABCs
above above P50K
P500K GPPB Res.
GPPB Res. 21-2017
21-2017 dated May 30,
dated May 2017
30, 2017
*For individuals engaged under Sec. 53.6, 53.7 and 53.9 of the IRR
of RA 9184, only the BIR Certificate of Registration shall be
submitted in lieu of Mayor’s Permit.
**Requirements under Section 53.6 of the IRR of RA 9184 will not
apply to artists such as singer, performer, poet, writer, painter and
sculptor who are not engaged in business.
***For methods of procurement requiring Mayor’s Permit and
PhilGEPS Registration Number, Certificate of Platinum Membership
may be submitted in lieu of the said documents.
369
POSTING REQUIREMENTS
370
PHILGEPS REGISTRATION
371
PHILGEPS REGISTRATION
Continuation:
For Sec. 53.1 - Two Failed Biddings, the BAC shall require the
submission of a Certificate of PhilGEPS Registration in
accordance with Sec. 8.5.2 of the IRR of RA 9184
372
INVITATION OF OBSERVERS
373
REFERENCE TO BRAND NAMES
374
DELEGATION OF AUTHORITY
1. Shopping
2. Negotiated Procurement under Emergency Cases
3. Small Value Procurement
4. Lease of Real Property and Venue
375
PERFORMANCE and
WARRANTY SECURITIES
Alternative Method of Performance Warranty Security
Procurement Security (PS) (WS)
Limited Source Bidding
Direct Contracting x
Repeat Order x
Two-Failed Biddings
In no case shall WS
be required in the
procurement of
Consulting Services.
376
PERFORMANCE and
WARRANTY SECURITIES
Alternative Method of Performance Warranty Security
Procurement Security
(PS)
Emergency Cases Procuring Entity may Procuring Entity may
require PS depending require WS depending on
on the nature of the the nature of the
procurement project. procurement project.
However, for In no case shall WS be
Infrastructure Projects, required in the
PS is required. procurement of Consulting
Services.
Take-over of Contracts
Adjacent/Contiguous For Infrastructure Projects,
WS is required.
377
PERFORMANCE and
WARRANTY SECURITIES
Alternative Method of Performance Warranty Security
Procurement Security
(PS)
Small Value Procurement Procuring Entity may Procuring Entity may
require PS depending require WS depending on
on the nature of the the nature of the
procurement project. procurement project.
However, for In no case shall WS be
Infrastructure Projects, required in the
PS is required. procurement of Consulting
Services.
378
OTHER TERMS AND CONDITIONS
379
ISSUANCES TO CONDSIDER:
380
WHY DO WE
HAVE OUR EYES
IN FRONT OF
OUR FACE?
382
“OUR EYES ARE
IN FRONT OF
OUR FACE
BECAUSE IT IS
BETTER TO LOOK
AHEAD THAN TO
LOOK BACK.”
383
WHY DO WE CLOSE OUR
EYES WHEN WE PRAY,
CRY, KISS OR DREAM?
384
“WHY DO WE CLOSE
OUR EYES WHEN WE
PRAY, CRY, KISS OR
DREAM? BECAUSE THE
MOST BEAUTIFUL
THINGS IN LIFE ARE
NOT SEEN BUT FELT BY
THE HEART.”
385
THANK YOU and
GOD BLESS!
ROBERTO P. TING, JR.
SAO, Goods and Services Division
Procurement Service
3043530/09328484241/09054403615