Professional Documents
Culture Documents
Duration
• Critical Chain
C1=5
Schedule
C2=8 D1=4 Project
Buffer = 6
Different Variability
Protection Mentality
• Shift from protecting tasks to protecting project as a
whole
• Project Buffer allocated to tasks that need it, not
allocated to tasks that don’t need it
• 50/50 estimates eliminate student syndrome
• Less protection lost due to early finishes and Parkinson’s
law
• Different mentality when judging those responsible for
completing tasks
– Half of the tasks will be late with 50/50 estimates
– Tasks can be late and the project can still finish early
Impact of Resource Contention
C1=8 C2=14
• Critical Path length = 29 days (C1-C2-D1)
• What if tasks A2 and B3 are performed by the same
resource?
• Can the project be completed in 29 days?
Impact of Resource Contention