Excavation Soil

© PT. TOKYU CONSTRUCTION INDONESIA


Excavation Soil and Shoring

400

IWF 100x50x5x7

-  Partial excavation from Grid Line 12 and Shoring Installation


- Shoring is partial with IWF 100 x 50 and wooden 30 x 200
- One section/span for partial excavation and shoring = 12000 mm and continue
for RC wall work (rebar, formwork and concrete)
- Spare soil from wall existing (bak aerasi) to Edge shoring

© PT. TOKYU CONSTRUCTION INDONESIA


Shoring Method

2000

IWF (100 x 50 x 5 x 7)

-  Partial Shoring Installation with IWF (100 x 50 x 5 x 7) and wooden 30 x 200


- IWF Installation for shoring method use existing excavator PC 130
- One section/span for partial excavation and shoring = 12000 mm and continue
for RC wall work (rebar, formwork and concrete)
- Spare soil from wall existing (bak aerasi) to Edge shoring
- Shoring method just for construction RC wall beside (bak aerasi)

© PT. TOKYU CONSTRUCTION INDONESIA


RC wall construction

- Fix elevation for bottom soil RC wall


- Preparation soil with sand and lean concrete bottom RC wall
- Marking position
- Installation rebar and formwork
- 2 step for casting concrete
- 1st : Casting concrete foot/slab RC wall
- 2nd : Casting concrete until top wall

© PT. TOKYU CONSTRUCTION INDONESIA


RC wall Concreting

- For Casting Concrete we make a crane 30 ton


- Preparation with scaffolding for access

© PT. TOKYU CONSTRUCTION INDONESIA