ACWP = Actual Cost of Work Performed EV = Earned Value
BCWS = Budgeted Cost of Work Scheduled PV = Planned Value
BCWP = Budgeted Cost of Work Performed BCTW = Budgeted Cost of Total Work ACC = Additional Cost of Completion Formulas - EVA • Cost Variance = BCWP – ACWP • Scheduled Variance = BCWP – BCWS • Cost Performance Index (CPI) = • Schedule Performance Index (SPI) = • Estimated Project Completion Cost = • Estimated Project Duration = • While solving problems – • BCWS = % of scheduled completion x Budgeted cost for that activity • BCWP = % of actual completion x Budgeted cost for that activity