Professional Documents
Culture Documents
for Implementation of
Renewable Energy Projects
Between
14 July, 2020
NWPGCL: Overview
28 August 2007 January 2009 December 2012 October 2016 July 2020
Registration Business Started Achieved ISO certificates Currently Generating:
and Incorporation Commencement Electricity Generation in Quality, Environment,
2435 MW
141 MW Health & Safety
Fastest
Fastest growing
growing Power
Power
Total
Total asset
asset at
at the
the end
end of
of FY
FY 2018-19
2018-19
Generation
Generation Utility
Utility of
of Bangladesh.
Bangladesh.
is
is 148,167.6
148,167.6 Million
Million BDT.
BDT.
Currently
Currently ownsowns Eight
Eight Power
Power Plants
Plants
Net
Net worth
worth 34,060.7
34,060.7 Million
Million BDT
BDT (FY
(FY
with
with total
total installed
installed capacity
capacity of
of 2,435
2,435
2018-19).
2018-19).
MW
MW including
including JVJV companies
companies (12%
(12%
of
of Nation’s
Nation’s capacity
capacity excl.
excl. captive
captive
Net
Net profit
profit after
after tax
tax for
for FY
FY 2018-19
2018-19
plants).
plants).
was
was 3,271.404
3,271.404 Million
Million BDT.
BDT.
NWPGCL
NWPGCL supplied
supplied 8,743.26
8,743.26 Million
Million
Net
Net profit
profit margin
margin of
of FY
FY 2018-19
2018-19 was
was
kWh
kWh toto national
national grid
grid in
in FY
FY 2019-20
2019-20
11%.
11%.
with
with >92%
>92% plant
plant Availability
Availability Factor.
Factor.
1st
1st Bangladeshi
Bangladeshi Company
Company toto achieve
achieve certificates
certificates on
on the
the
latest
latest version
version of
of ISO
ISO 9001:2015,
9001:2015, ISO
ISO 14001:2015
14001:2015 && ISO
ISO
45001:2018.
45001:2018.
NWPGCL: Overview
In 2018, NWPGCL received Award Sirajganj 225 MW CCPP (U-1) Three Power Projects of NWPGCL
from Honorable Prime Minister, received Best Power Plant Award received Best Project Award of
Sheikh Hasina for it’s contribution to consecutively in 2014 & 2015 from ADB in 2013 & 2015.
rapid growth of electricity generation. Power Division.
Sirajganj 225 MW CCPP (Unit-3) In Electricity Week-2014,one of the Project Director, Bheramara 360 MW
received “Power Deal of the Year, Project Directors received Power CCPP Project received the Award of
Bangladesh Award” in The Asset Triple Division 2014 Best Project The Best Project Director in National
A Asia Infrastructure Award-2017. Director Award. Power & Energy Week-2018.
NWPGCL: Plants in Operation
Sirajganj 225 MW CCPP (Unit 2)
Sirajganj 225 MW CCPP (Unit 1) 220 MW Natural Gas
214 MW Natural Gas / HSD Feb 2018
Dec 2012 (SC) & Jul 2014 (CC)
China National Machinery Import & Bangladesh-China Power Company (Pvt.) Registration on Oct,
01 50 %
Export Corporation (CMC) Limited (BCPCL) 2014
M/s Sembcorp Utilities Pte Ltd, Sembcorp North-West Power Company Registration on Jan,
02 Singapore (Sembcorp) Limited (SNWPCL) 29 % 2016.
Revised JDA is in
04 Siemens AG, Germany, CMC and Payra 3600 MW LNG-to-Power Project * 50% govt’s approval
Excelerate Energy
process.
* Proposed
Bangladesh-China Power Company (Pvt.) Limited
507.6
Future Projects On-going Projects Existing Capacity
12000 2358
10000
Gas
3488
8000 Liquid Fuel 335
6000
LNG
Coal
4000
Renewable
2000
3600
141
299 372 444 722 1074 2435
0
Financial Year
Total Capacity
Existing Power Plants On-going Projects Upcoming Projects
(Up to 2028)
Summary:
2,435 MW 6,413.6 MW 1,440 MW 10,288.6 MW
Overall Investment:
Overall Capacity:
Approx. USD 500 Million
500 MW (aprox.)
[Debt 80%+Equity 20%]
Pabna 60 MW Solar
Payra 50 MW Wind
Project Status: Pabna 60 MW Solar
Expected COD: June 2022. Sirajganj 100 MW Grid Connected Solar PVPP: Google Earth View
15
Project Status: Sirajganj 100 MW Solar
Met-Tower of Payra 50 MW
Wind Power Plant Project Payra 50 MW Wind Power Plant 17
Project Status: Jamuna 100 MW Solar
Land acquisition
process of 443.30
acres is ongoing.
Land utilization shall
be maximized by
keeping provision for
agricultural
cultivation under
elevated solar
panels.
Expected COD:
December 2022.
18
A Proven Friendship…