Joint Venture Agreement (JVA) Signing

for Implementation of
Renewable Energy Projects
Between

North-West Power Generation Company Limited (NWPGCL)


&
China National Machinery Import & Export Corporation (CMC)

14 July, 2020
NWPGCL: Overview

28 August 2007 January 2009 December 2012 October 2016 July 2020
Registration Business Started Achieved ISO certificates Currently Generating:
and Incorporation Commencement Electricity Generation in Quality, Environment,
2435 MW
141 MW Health & Safety


 Fastest
Fastest growing
growing Power
Power

 Total
Total asset
asset at
at the
the end
end of
of FY
FY 2018-19
2018-19
Generation
Generation Utility
Utility of
of Bangladesh.
Bangladesh.
is
is 148,167.6
148,167.6 Million
Million BDT.
BDT.

 Currently
Currently ownsowns Eight
Eight Power
Power Plants
Plants

 Net
Net worth
worth 34,060.7
34,060.7 Million
Million BDT
BDT (FY
(FY
with
with total
total installed
installed capacity
capacity of
of 2,435
2,435
2018-19).
2018-19).
MW
MW including
including JVJV companies
companies (12%
(12%
of
of Nation’s
Nation’s capacity
capacity excl.
excl. captive
captive

 Net
Net profit
profit after
after tax
tax for
for FY
FY 2018-19
2018-19
plants).
plants).
was
was 3,271.404
3,271.404 Million
Million BDT.
BDT.

 NWPGCL
NWPGCL supplied
supplied 8,743.26
8,743.26 Million
Million

 Net
Net profit
profit margin
margin of
of FY
FY 2018-19
2018-19 was
was
kWh
kWh toto national
national grid
grid in
in FY
FY 2019-20
2019-20
11%.
11%.
with
with >92%
>92% plant
plant Availability
Availability Factor.
Factor.

 1st
1st Bangladeshi
Bangladeshi Company
Company toto achieve
achieve certificates
certificates on
on the
the
latest
latest version
version of
of ISO
ISO 9001:2015,
9001:2015, ISO
ISO 14001:2015
14001:2015 && ISO
ISO
45001:2018.
45001:2018.
NWPGCL: Overview

In 2018, NWPGCL received Award Sirajganj 225 MW CCPP (U-1) Three Power Projects of NWPGCL
from Honorable Prime Minister, received Best Power Plant Award received Best Project Award of
Sheikh Hasina for it’s contribution to consecutively in 2014 & 2015 from ADB in 2013 & 2015.
rapid growth of electricity generation. Power Division.

Sirajganj 225 MW CCPP (Unit-3) In Electricity Week-2014,one of the Project Director, Bheramara 360 MW
received “Power Deal of the Year, Project Directors received Power CCPP Project received the Award of
Bangladesh Award” in The Asset Triple Division 2014 Best Project The Best Project Director in National
A Asia Infrastructure Award-2017. Director Award. Power & Energy Week-2018.
NWPGCL: Plants in Operation
Sirajganj 225 MW CCPP (Unit 2)
Sirajganj 225 MW CCPP (Unit 1) 220 MW Natural Gas
214 MW Natural Gas / HSD Feb 2018
Dec 2012 (SC) & Jul 2014 (CC)

Sirajganj 225 MW CCPP (Unit 3)


Bheramara 410 MW CCPP 220 MW Natural Gas / HSD
410 MW Natural Gas / HSD Aug 2018 (SC) & Jan 2019 (CC)
May 2017 (SC) & Dec 2017 (CC)

Khulna 225 MW CCPP


Madhumati 100 MW HFO PP
230 MW Natural Gas / HSD
105 MW HFO
Sep 2013 (SC) & Jun 2016 (CC)
Apr 2019
Joint Venture Company (JVC)
To achieve technical synergies among the parties, ensure quick project financing and secure
foreign direct investment for the Power Projects; NWPGCL has already formed several Joint
Venture Companies (JVC):
Sl.
No. NWPGCL’s Partner Name of the JVC NWPGCL’s Share Remarks

China National Machinery Import & Bangladesh-China Power Company (Pvt.) Registration on Oct,
01 50 %
Export Corporation (CMC) Limited (BCPCL) 2014

M/s Sembcorp Utilities Pte Ltd, Sembcorp North-West Power Company Registration on Jan,
02 Singapore (Sembcorp) Limited (SNWPCL) 29 % 2016.

Bangladesh-China Power Company (Pvt.)


03 China National Machinery Import & Limited. Renewable 50 % JV signing on 14
Export Corporation (CMC) July, 2020
(BCPCL Renewable)

Revised JDA is in
04 Siemens AG, Germany, CMC and Payra 3600 MW LNG-to-Power Project * 50% govt’s approval
Excelerate Energy
process.

* Proposed
Bangladesh-China Power Company (Pvt.) Limited

Operational Unit: Unit-1 of Payra 1320


MW Thermal PPP (1st phase)
Capacity: 622 MW (net)
Fuel: Imported Coal
IOD: 15 May 2020
 Payra 1320 MW Thermal Power
Plant Project (1st phase)
Unit-1 of Phase-1 (660 MW) has became
the 1st USC Power Plant of Bangladesh.
The Expected COD of Unit-2 of this
phase is Dec 2020.
Existing Plant Projects Under Implementation
Unit -1, Payra 1320 MW Unit -2, Payra 1320 MW Payra 1320 MW  Payra 1320 MW Thermal Power
Thermal Power Plant Thermal Power Plant Thermal Power Plant Plant Project (2nd phase)
Project (1st Phase) Project (1st Phase) Project (2nd Phase) The Overall EPC progress is 12.42%
upto May, 2020.
622 MW 622 MW 1244 MW
Both Units of this phase is expected to be
Total Capacity: 2488 MW (By 2023) online by 2023.
Sembcorp North-West Power Company Limited

Operational Unit: : Sirajganj 414 MW


CCPP (Unit-4)
Capacity: 414 MW (CC)
Fuel: Natural Gas/HSD
COD: Oct 2018 (SC) & Apr 2019 (CC)

Contracted capacity: 413.792 MW

Configuration: CCGT in a 1x1x1


configuration using MHPS 701F4 GTG,
Hangzhou Boiler HRSG, and Dongfang
ST/STG Key Operational Data
1st successful PPP in the power sector Average PLF (as of Dec,19) 79.2%

Availability (as of Dec’19 91.3%


Ranked top in the dispatch merit order of
power plants in the country Reliability (as of Dec’19) 97.9%
Payra 3600 MW LNG-to-Power Project

Capacity: 3600 MW (3 x 1200 MW)


Fuel: Imported LNG
Expected COD: Dec 2024 (1st unit),
Dec 2026 (2nd unit),
Dec 2028 (3rd unit).
Siemens and NWPGCL signed JDA on 7
September, 2018. Restated JDA with additional
partners is under government approval
process.
Land Acquisition & Land Development are
Other Salient Features
completed.
Location : Kalapara, Patuakhali Feasibility Study of the Power Plant Package
Approx. USD 1.8 Billion is completed.
Project Cost :
(for 3.6 GW CCPP excl. LNG/Gas infrastructures) Concept Study for the LNG Terminal & Gas
400-500 gm CO2 offset per KWH compared to coal Infrastructure is done. Detailed study will begin
Environmental soon.
Benefits : fired power plant [About 12 million Ton CO2 offset
per year by a 3600 MW CCPP] ESIA study is in progress.
Future Generation Outlook
Year-wise Generation Projection of NWPGCL* Future Fuel Mix (2028)*
Generation Capacity

507.6
Future Projects On-going Projects Existing Capacity
12000 2358

10000
Gas
3488
8000 Liquid Fuel 335
6000
LNG
Coal
4000
Renewable
2000
3600
141
299 372 444 722 1074 2435
0

Financial Year

Total Capacity
Existing Power Plants On-going Projects Upcoming Projects
(Up to 2028)
Summary:
2,435 MW 6,413.6 MW 1,440 MW 10,288.6 MW

* Including JVC projects


Plan for Renewable Energy

 In order to decrease dependency on fossil


fuel and reduce pollution, Government of
Bangladesh has adopted “Renewable
Energy Policy-2008”

 At least 10% electricity generation from


renewable sources, by 2030.

 In line with this policy, NWPGCL signed an


Memorandum of Understanding (MoU) with
China National Machinery Import & Export
Corporation (CMC) on 27-Aug-2019.

 The total capacity of these Solar and/or


wind based power plants would be up to
500 MW approximately.
Proposed Renewable Energy Projects

Capacity Location Energy Source Expected COD

Pabna 60 MW Solar 60 MW Pabna Solar December 2021

Sirajganj 100 MW Solar 100 MW Sirajganj Solar June 2022

Payra 50 MW Wind 50 MW Payra Wind December 2023

Jamuna 100 MW Solar 100 MW Pabna Solar December 2022

Overall Investment:
Overall Capacity:
Approx. USD 500 Million
500 MW (aprox.)
[Debt 80%+Equity 20%]

*As of 5 July 2020


Site Locations of Renewable Energy Projects

Sirajganj 100 MW Solar

Pabna 60 MW Solar

Jamuna 100 MW Solar

Payra 50 MW Wind
Project Status: Pabna 60 MW Solar

Pabna 60 MW Grid Connected


Photo-voltaic Solar Power Plant
Project

 Land acquisition (205.69 Acres) is


completed.
 The consultant has already
submitted Feasibility Study Report.
 Fencing work around the project
area is ongoing.
 Grade beam and column
installation has been completed
up to 2.1 km.

Expected COD: December 2021.

Pabna 60 MW Grid Connected Solar PVPP 13


Project Status: Pabna 60 MW Solar

Few Glances from


Pabna 60 MW Grid Connected Solar PVPP site
14
Project Status: Sirajganj 100 MW Solar

Sirajganj 100 MW Grid


Connected Photo-voltaic Solar
Power Plant Project
 Land lease process (330
Acres) is going on.

Feasibility Study Report has


been completed.

Waterbody of the site shall


be kept undisturbed and land
utilization shall be maximized
by fish farming under the
panels.

Expected COD: June 2022. Sirajganj 100 MW Grid Connected Solar PVPP: Google Earth View
15
Project Status: Sirajganj 100 MW Solar

Birds eye view of Sirajganj 100 MW Grid Connected Solar PVPP 16


Project Status: Payra 50 MW Wind

Payra 50 MW Wind Power Plant Project


 Feasibility study is ongoing.
 Expected COD: December 2023.

Met-Tower of Payra 50 MW
Wind Power Plant Project Payra 50 MW Wind Power Plant 17
Project Status: Jamuna 100 MW Solar

Jamuna 100 MW Solar


Power Plant Project

 Land acquisition
process of 443.30
acres is ongoing.
 Land utilization shall
be maximized by
keeping provision for
agricultural
cultivation under
elevated solar
panels.

 Expected COD:
December 2022.

18
A Proven Friendship…

 CMC is a trusted partner of NWPGCL and


successfully implemented JVC company
together.

 The friendship between two countries and


previous success with CMC have added
vigor to this partnership for BCPCL
Renewable.

The Hon’ble Prime Minister of the Government of Bangladesh


and The Hon’ble Prime Minister of the People’s Republic of
China added vigor to the Bangladesh-China friendship.
Thank You!