ETHIOPIAN ROADS AUTHORITY
Review of Project Progress up to End of March 2021 against Five Month Agreed
Action Plan (from Feb – June 2021)
2
Table Content
3
Summary of 2013 EFY Action Plan ( 5 months)
Plan for Total Tot date Plan for Total Time Slippage
2013 Prog. by Progress 5 prog +5 Elapse by against time
EFY end of Mar-21 months month June-21 by June-21
June -21
% % % % % % %
B C=A+B A F G D E=D-C
58.73% 59.66% 4.11% 31.98% 36.09% 61.56% 25.47%
4
Review of Project To date Progress
Plan Accom Five month Plan (%) Total To date Completi Remain
for p (Jan Plan Mar 21 on date ing
2013 21) (Feb contract
EFY -Jun) time
% Feb Mar Apr May Jun %
Plan 58.70 35.80% 5.50% 8.20% 8.70% 5.00 4.10% 31.50 17.81% 16-Jun-
% % % 22 15
Months
Actual 4.11% 0.71% 3.23% 8.05%
Actual 11.48% 12.91 39.39% 45.20%
/Plan %
MWP AAP April 1st 2nd
Total Time Elapsed (Mar 21) 51.59% 51.59% Plan 2.17 2.17
To date Plan (Mar 21) 47.57% 17.81% Actual 0.9
Actual Acc (Mar 21) 8.05% 8.05% 41.38
Plan -39.52% -9.76%
Slippage against
Time -43.54% -43.54% 5
To date Linear Progress of Major
Description Unit Plan Actual Slippage Remark
Survey, Investigation
and Design % 88.98% 67.15% -21.83%
Employer’s
Representative % 88.70% 51.27% -37.43%
Facilities
Detour & Traffic % 68.35% 6.84%
-61.51%
Management
Earthworks % 75.67% 12.98% -62.69%
Sub-base % 21.39% 0 -21.39%
Base-course % 25% 0 -25.00%
AC/DBST % 3.71% 0 -3.71%
Drainage & Major % 41.66% 0.69%
-40.98%
Structures
Road Furniture and % 5.79% 1.20%
Environmental Works -4.59%
6
To date Design and Contract Deliverables
Item Description of deliverables Status Remark / Delay due
1 Route selection Final submitted Approved
2 Topographic survey Final submitted Consented
3 Sub grade soil material investigation and Final submitted
pavement design report
Being reviewed as per the
4 Geotechnical design report Final submitted
comment on the revised
5 Geometric design report Final submitted project quantity
6 Hydrology/Hydraulic study report Final submitted
7 Structure and drainage report (Minor and Major Final submitted
structures)
8 Construction specification and special provisions Not Submitted
9 Environmental and social report & Quality control Final Submitted Commented
plan
10 Design of suspended bridge Not Submitted
Asphalt Plant 1 1 1 0 1
Crusher 1 1 1 1 1 1 1 0
Fuel Truck 2 2 2 2 2 2 1 1 ***
Delivery/Production
Description Unit Require Available Shortage Schedule
d
Quantity Date
Base-course M3 -
Agg. 93,025.80 93,025.80
12
Summary of Major Outstanding Issues
Item Description Status Promised date
on Feb 04
1 Construction of ER Finishing and site activities are on 15 days for site
Camp progress. Furniture and fixtures are not activities & 10 days
yet ready. for furnishing
Comment is forwarded to office
2 Laboratory Temporary laboratory established & for
equipments soil and concrete only. Compressive
strength machine mobilized.
13
Status of ER’s Camp
14
Summary of Mobilization of Crusher & Asphalt plant
Item Description Status Promised date
on Feb 04
1 Erecting the Mobilization and installation is One month to
Crusher and completed at the end of March 2021 complete erecting
Generator
15
16
Summary of Environmental and Quality Issues
Item Description Status Remark
1 Treatment of the Rock fill and embankment Temprary measures need
gully formed activities on progress from Km to be completed before
15+300 to km 16+000 the rainy season
18
Summary of Major Outstanding Issues
Description of Issues Issue pending with (Employer,
Engineer, Contractor
Outstanding ROW issues (removal of trees Employer & Engineer
electric poles)
2nd Advance payment cash portion & IPCs
Crusher Plant:- Production Contractor
20