Hidase Elementary School

Dinning Hall Constriction


Project Progress Report

date 25/05/2013 Ec
Client Bole Sub city Construction
Office
Contractor Anbes Ayisa G.C
Consultant Sarzna Engineering
Consulting Plc.
Site location Bole Sub City Worda 14
Contract time and amount
Contract time 2 months Normal
contract
Site hand over october 03/2013 E.c
Contract Amount 1.75milion
Current situation of the project
All construction activities are completed
Except:
1. Electrical
2. Sanitary
3. Fitting glass
Total percent completed = 98% of the
contract
Interior part
Interior part
ceiling
Front view
External view
Ramp and site work
Problems faced
Additional and supplementary work
not included in the contract
1. forciline floor finish
2. fascia board
3. Ridge cover
4 . External ceiling /purling/
5. Ceiling painting
Total Estimated 28% of the contract
Contract agreement condition
Even if the contractor construct the
above additional work items,
Supplementary agreement is still not
signed.
This impacts the contract completion
time
Decision is required by the client