Professional Documents
Culture Documents
Programme Management and Project Evaluation
Programme Management and Project Evaluation
Project Evaluation
To Be Covered
• Programme Management
• Creating Program
• Resource Allocation
• Project Evaluation
• Risk Evaluation
2.7 Programme Management
• One definition:
4
Strategic Programmes
• Several projects together can implement a single
strategy.
• Portfolio???
– ICT infrastructure,
10
Programme managers versus project
managers
11
2.8 Allocation of Resource
• What is a project?
• Planned Activity
• What is Resource?
• support that may be drawn upon when needed
• Each project needs Resources to achieve there objective.
• Resources may be:
– Programmers
– Skilled resources
– Infrastructure (PC, Network, Server, Work stations etc)
– Mangers
12
Managing the allocation of resources
within programmes
• In company there are many project running concurrently at same time
the organization.
– Expertise
– Software Developer
– Database designer
13
Projects sharing resources
14
• These experts may be needed in number of
projects running in company.
• So it is the responsibility of program manager to
use these resources in optimum way.
• And if program manager have personal
relationship with these skilled resources. i.e.
he/she has the knowledge about these resources
15
• One resource may be needed by different
project
• So we need to identify the priority of the
project
• We can delay the start of activity of a project
with least priority.
16
2.10 Creating Programme
• Based on OGC approach
– OGC is a UK govt. Agency responsible for introduction programme
management
17
• A programme director is appointed for the
program to take leadership
• Programme director is responsible for success
of the programme
18
Next stages/documents
– Vision Statement
– Benefits
– Risks and Issues
– Estimation cost, timescale and effort
19
The vision statement
• The vision statement – explains the new capability
that the organization will have
– Provides information to sponsoring that it is worth
moving to more detailed definitions.
– Next Step is team forming
• A small team is formed with a programme manager
• This team will now take the outline vision and prepare a
detailed vision
20
The blueprint
• The blueprint – explains the changes to be made to obtain the
new capability
• It contains:
– Business model outline
21
2.4 Project Evaluation
• identify,
• optimise and
26
2.5 Cost-Benefit Evaluation Techniques
• Net Profit
• Payback Period
• Return on Investment(ROI)
• Net Present Value
Net profit
28
Net profit
29
Pay back period
• It is time taken to break even or pay back the initial
investment.
• Project with shortest payback period will be chosen on the
basis that an organization will wish
32
ROI
• For project1
• Net Profit = 50000
• Time Duration= 5 years
• Average annual profit is =50000/5=10000
10000 X 100
ROI =
100000
ROI = 10%
Return on investment (ROI)
In the previous example
Calculate ROI and decide which project is most
worthwhile:
P1: 10%
P2: 20%
P3:10%
P4:15%
Net Present Value = Sum of the discounted cash flows for all the
years - investment
35
t=1
r = 10% = 0.1 Discount Cash Flow = 10000 * 0.9091 = 9091
PV = 1 / (1 + 0.1)1
Year Cash-flow Discount Discounted cash
factor/Present flow
value @10%
0 -100,000 -100,000
1 10,000 0.9091 9,091
2 10,000 0.8264 8,264
3 10,000 0.7513 7,513
4 20,000 0.6830 13,660
5 100,000 0.6209 62,090
Net
Profit
50,000 NPV 618
38
Risk Evaluation
1. Risk Identification and Ranking
– One technique is, to draw risk matrix.
• Classify risk into two categories :
– Important (impact)
– Likelihood (probabilty)
• Matrix may be used for project evaluation
39
Example of a project risk matrix
40
• 2. NPV and Risk
– For riskier projects, could use higher discount
rates.
– We can increase Discount rate for risky projects
by 5 to10%.
41
• 3. Cost-benefit Analysis:
– In this approach we consider each possible
outcome and estimate the probability of their
occurrence.
– So instead of single cash flow we will have set of
cash flows and their occurrence.
42
Risk Evaluation(Cont.)
Sales Annual Sales Probability Expected value
Income
High 8,00,000 0.1 80,000
Medium 6,50,000 0.6 390,000
Low 100,000 0.3 30,000
Expected Income 5,00,000
43
4. Risk Profile Analysis
• Construction of risk profiles using sensitivity analysis
– We can analyze the risk with project by varying the
parameters of project that affects the cost or benefits of
the project.
– First we do the estimation then we vary it and check it’s
sensitivity.
• For example we are varying the original estimation by
+ or – 5% and then recalculate the cost and benefits.
If the project cost and benefits changes drastically
then that parameter becomes sensitive to project
44
5. Decision trees:
• Example:
– Some company is providing payroll service to
their customers.
– Their system is old and number of customers are
increasing. There is a probability that market will
expand more.
– They have two option
• Expand the existing system
• Replace the old with new
45
Decision trees
46