Hook-up Sequence for SS pipe

Hook-up sequence will be performed as below step:


1. Fit-Up area 1 - then continuously welding from area 1
1. Blowing the line pipe before welding up-to area 7
2. Pipe to pipe fit-up & installation sponge dam
3. Welding activity 2. Move crane, Fit-Up area 11 then continuously welding
4. Radiography test for welding joint from area 11 up-to area 9
5. Remove sponge dam
6. Blowing 3.TGX welding activity, will execute on area 8 (loop)
7. Boroscope
8. Continue activity no.1 to next module *if only have 1 team for execute the activity for hook-up at
BF area the sequence will be continuously welding from area
1 up-to area 11

DH 11 10 9 7 6 5 4 3 2
1
8
DH