WEAKNESS - OPPORTUNITIES WO BRIEF DESCRIPTION POSSIBLE ACTION

W3 No SOP for WWTP operation; manpower WWTP operation and personnel training can Create procedure for WWTP operation and
are not trained be standardized and documented train personnel assigned in WWTP operation
on DENR wastewater regulations and policy
O2 Standardized and documented HSE updates
Procedures

WEAKNESS - THREAT WT BRIEF DESCRIPTION POSSIBLE ACTION


W4 Missing as-built plans, drawings Red tape on issuance of as built plans, drawing Create an agreement stating the provision of
of the project necessary documents such as as-built plans of
T4 Red tape and bureaucracy the project and other documents that need to
be applied to the government that includes
timeline