Professional Documents
Culture Documents
1. Fixed Capital
- Indirect Cost
- Direct Cost
2. Working Capital
Material
allowances Subcontract
labour Overhead
Material Cost
Labour cost
Subcontractor cost
General contractor pay the subcontractor to do a package
of work in the project.
Fee/profit and contingencies
The amount of profit and contingencies depend on:
Project size
Site condition
Project complexity
Information from owner which can been seen in tender
document
Allowances
Cost for unplanned works
Chapter 4 - Project Cost System
Components of Project Cost 13
Variable Overhead
It should represent all operating expense generated by
the field personnel. These are costs that would not occur
if no field personnel were employed. Variable cost will
fluctuate directly with the amount of people a company
employees as part of it production labor force
Site engineer, project manager, project supervisor
Water, electricity, telephone, office stationary
Furniture
Marketing cost, official trip cost
Permanent workers’ salary, etc.
Fair-cost
Detailed estimates
estimates
Contractor’s
Bid estimates
Definite
estimates
Detailed estimates
These normally require a careful tabulation of all the
quantities for a project or portion of a project, this is
called a quantity takeoff
These quantities are then multiplied by selected or
developed unit costs, and the resulting sum represents the
estimated direct cost of the facility
Definitive estimates
Table 4.1 Example of Cost Index List from Various Technical Press
Example 4.1
solution 4.1
= RM 3,000,000 x 435
392
= RM 3,329,082
Q2 x
C2 = C1
Q1
Example 4.2
Solution 4.2
Q2 x
C2 = C1
Q1
75,000 0.6
= 4,000,000
50,000
= 5,101,698
Equipment Factor
Blender 2.0
Blowers and fans (including motor) 2.5
Centrifuges (process) 2.0
Compressors
Centrifugals, motor-driven (less motor) 2.0
Steam turbine (including turbine) 2.0
Reciprocating, steam and gas 2.3
Motor-driven (less motor) 2.3
Ejectors (vacuum units) 2.5
Furnaces (package units) 2.0
Heat exchangers 4.8
Instruments 4.1
Motor, electric 8.5
Equipment Factor
Pumps
Centrifugal, motor-driven (less motor) 7.0
Steam turbine (including turbine) 6.5
Positive displacement (less motor) 5.0
Refrigeration (package unit) 2.5
Tanks
Process 4.1
Storage 3.5
Fabricated and field erected (50,000+gal) 2.0
Towers (columns) 4.0
Table 4.4 Example of Parameter Cost in Table 4.4 Example of Parameter Cost in
Medical Office – R. S. Means Warehouse – R. S. Means
Example 4.4
Solution 4.4
Benefit
1
Cost
Conventional B/C
Modified B/C
i% F
0 1 2 3 4 5 n
F = P (1+i)n, P = F (1+i)-n,
F = P (F/P,i,n) P = F (P/F,i,n)
i% F
0 1 2 3 4 5 n
A / year
1 i n 1 i
F A A F
1 i 1
n
i
F A (F/A,i,n) A F (A/F,i,n)
P i%
0 1 2 3 4 5 n
A / year
i 1 i n 1 i n 1
A P P A n
1 i n
1 i 1 i
A P (A/P,i, n) P A (P/A,i,n)
Example 6.1
Solution 6.1
General
300-60 240
100 40 140
1.7 acceptable
Example 6.2
An individual investment opportunity is deemed to be
worthwhile if its B/C ratio is greater than or equal to 1.
Consider the project of installing a new inventory control
system with the following data:
Solution 6.2
Conventional method
B ratio PW[B]
C PW[CR (O M)]
10000
20000(A/P,15%,5) 4000(A/F,15%,5) 4400
10000
20000(0.2983) 4000(0.1483) 4400
1.02 1,acceptable
Conventional method
i 1 i n i
A P A F
1 i 1
n n
1 i 1
A P (A/P,i, n) A F (A/F,i,n)
Solution 6.2
Modified method
1.04 1,acceptable
Example 6.3
Even a company investment opportunity is deemed to be
worthwhile if its B/C ratio is greater than or equal to 1.
Consider the project of constructing a new houses with the
following data:
Example 6.3
80,000
a)
80,000 200
-
i = 6%
0 1 2 3 4
+
15,000
50,000
Chapter 4 - Project Cost System
Benefit-Cost Ratio Analysis 50
Example 6.4
b)
200,000 100
-
i = 6%
0 1 2 3 4
+
10,000
100,000
Chapter 4 - Project Cost System