Muhammad Iqbal Prasojo - PPT Sidang
Muhammad Iqbal Prasojo - PPT Sidang
civil-eng.binus.ac.id civengbinus
Preliminaries
• Background
• Problem Identification
• Scope of Research
Background
Enshassi, et al., (2012), stated that disharmony in the
construction implementation team actually resulted
Problem from disputes between contractors and
Identification subcontractors.
Construction implementers must have Different in reality; it does not always run Resulting an unstable progress that
a good relationship smoothly on field costs the whole project
Previous Research
No Previous Research Year
1 Major Causes of Problems Between Contractors and Subcontractors in the Gaza Strip 2012
2 The General Contractor – Subcontractor Relationship: The General Contractor’s View 2008
4 Improving the Main Contractor – Subcontractor Relationship Through Partnering on Construction Projects 2015
Relationship Between Main Contractors and Subcontractors and Their Impacts on Main Contractor Competitiveness: An
5 2017
Empirical Study in Hong Kong
Analisis Faktor – faktor yang Mempengaruhi Kontraktor Utama dalam Pemilihan Sub-kontraktor pada Pelaksanaan Proyek
6 2015
Konstruksi
Analisis Faktor – Faktor Pengaruh yang Mempengaruhi Kontraktor Utama dalam Pemilihan Subkontraktor pada Pelaksanaan
7 2018
Proyek Konstruksi
Kajian Terhadap Resiko Kualitas Hubungan Kontraktual Antara Kontraktor Dan Subkontraktor Berkaitan Dengan Pekerjaan
8 2013
Spesialis Pada Proyek Konstruksi
9 Analisis Pengaruh Konflik Dalam Pelaksanaan Konstruksi Terhadap Kesuksesan Proyek 2012
Construction implementers must have Different in reality; it does not always run Resulting an unstable progress that
a good relationship smoothly on field costs the whole project
Supriyadi (2014) explained that a harmonious
cooperation relationship is something that is
Research Objectives dreamed of by all construction parties because it
brings big success
To find problem factors & dominant To find the comparison of factors in domestic Resulting a much stable progress
factors that often occur and mostly found and foreign countries’ construction project & that brings big success
Preventive Measures
Benefits
As a source of information
As an input and suggestion As a reference
for companies to use
Scope of Research
• Used data that are taken from 50 trusted
international and national journals, scientific
articles, dissertations and media
• Data Analysis
• Preventive Measure
• Data Validation
Desk Study
Data Collecting
Deskripsi Data
Desk Study
Judul
Construction Duration in Nigeria
1 Oetomo, 2015 ü ü
Indra Saputra,
2
dkk, 2017 ü
Lendra & Andi,
3
2006 ü ü ü
Tanuwijaya &
4
Sekarsari, 2018 ü
5 Hassan, 2016 ü
Januardi &
6
Pribadi, 2020 ü ü
Listanto &
7 Hardjomuljadi, ü ü ü
2018
8 Susoko, 2019 ü ü
Mudzvokorwa,
Mwiya &
9
Mwanaumo, ü ü
2020
Enshassi, Arain
10
& Tayeh, 2009 ü ü
11 Jin, dkk, 2013 ü
Kale & Arditi,
12
2010 ü
Enshassi &
13
Medoukh, 2008 ü
Abdull Rahman,
14
dkk., 2013 ü ü ü ü
Manu, dkk.,
15
2015 ü
Abdull Rahman,
16
dkk., 2013 ü ü
Data Analysis – Combined Data (Domestic &
Foreign Countries’ Construction Project)
Faktor Internal Faktor Eksternal
19 3.5
20
3
3
18
2.5
16
14 2
2
14
11 1.5
12
1
10
1
8
7
8
0.5
6 6 6
5 5 5 5 5
6
0
4 4
4
14
10
12
10
10
8
8
6
6
6
4 4 4 4
4 4 4
3 3
4
3 3 3 3 3
4
2 2 2 2 2
1 1 1 1 1
2
1 1 1
2
0 0 0 0 0
0
0
a. Komunikasi k. Kualitas Kerja
b. Finansial l. Lack of Trust
c. Koordinasi m. Lack of Experience
d. Procurement n. Pengalihan Pekerjaan
e. Prolonged Dispute o. Penjadwalan
f. Ketidakpatuhan pada Jadwal Konstruksi p. Praktik Kecurangan
g. Revisi q. Tenaga Kerja
h. Multilayer Subcontracting r. Profesionalitas Pekerja
i. Pengelolaan dan Supervisi s. Masalah Kontrak Kerja
j. Perencanaan
Data Analysis – External Factor
2.5
0.8
2
2
0.6
1.5
0.4
1
0.2 0.5
0 0 0
0 0
Ahli 2
Hari/Tanggal Kamis, 14 Januari 2021
Waktu 20.45 WIB
Media Aplikasi WhatsApp
Nama Narasumber Bapak Sugiarto
Jabatan Deputy General Superintendent
Preventive Measure