Consultant- MEP
1 2 3
UPLOAD INITIATE REVIEW FINAL REVIEWER
(MEP CONSULTANT) (ITC PACKAGE MANAGER) (ITC PACKAGE MANAGER)
4
REUPLOAD CORRECTED
FILES
(MEP CONSULTANT)
Review Workflow Steps (MEP Consultant):
Step 1 : MEP Consultant will Upload the Files in the respective SHARED folders and inform the ITC Package Managers through
transmittals.
Step 2 : ITC Package Managers will have preliminary check of the files, if found OK a Review can be initiated by selecting
appropriate Approval Workflow.
Step 3 : Once the Approval Workflow has been initiated, the Final Reviewer (i.e. ITC Package Manager) will get notified about
the approval workflow.
Step 4 : He will review the files and Add Comments and Markups, Save it and Ultimately APPROVE, REJECT and APPROVE
WITH COMMENTS. And Click END REVIEW
Step 5 : Now ITC Package Manager will click the Reviews tab and go to that specific review, open the files which were
reviewed and click the 3 dots on the top right corner. And from there he will share the link with MEP Consultant and mention
which documents has been APPROVED or REJECTED or APPROVED WITH COMMENTS (In case of Multiple documents).
Step 6 : MEP Consultant will receive a mail with the link. Link will divert him to the reviewed documents with all the
Comments and Markups in it. He has to incorporate all the changes for the Rejected document and Reupload the document
in the respective folder.
Guide/Reference for Consultant-MEP
4
Guidelines for Consultant (Uploading Files)
• You have to upload the files in the respective SHARED folder. And Under Shared you to respective stage of the project. (Here we
have shown Construction stage as an example).
Go to Consultants
MEP Consultants
Shared Folder
Guide/Reference for Consultant (Creating Transmittals)
• You Select the files that you uploaded. Go to the 3 dots and select Create Transmittals.
Numbers of Number of
File Name Approval Status
Markups Comments
Guide/Reference for Contractor (To Open Reviewed file)
• Here you will see all the Markups and Comments.
• Incorporate the Changes (if any) as suggested by the Reviewer. And Reupload in the respective Folders.
List of all
Markups
List of Comments
Provided
Position of
Markup
BIM 360 – WORK-FLOWS – CONTRACTOR/VENDOR
1 2 3 4
UPLOAD INITIATE REVIEW FIRST REVIEWER FINAL REVIEWER
(CONTRACTOR/VENDOR) (ITC PACKAGE MANAGER) (CONSULTANT) (ITC PACKAGE MANAGER)
5
REUPLOAD CORRECTED
FILES
(CONTRACTOR/VENDOR) 10
Review Workflow Steps (Contractor/Vendor):
Step 1 : Contractor/Vendor will Upload the Files in the respective SHARED folders and inform the ITC Package Managers through transmittals.
Step 2 : ITC Package Managers will have preliminary check of the files, if found OK a Review can be initiated by selecting appropriate Approval
Workflow.
Step 3 : Once the Approval Workflow has been initiated, the Initial Reviewer (i.e. Consultant) will get notified about the approval workflow.
Step 4 : Initial Reviewer will open the Review and click START REVIEW. In case multiple documents he will be doing it one at a time. During
the review he can Add Comments and Markups in the files.
Step 5 : Once Initial Reviewer is done with the reviewing part he can click the SUBMIT REVIEW so that final reviewer will get notified. A box
will appear where Initial Reviewer can Add NOTES about the APPROVAL AND REJECTION of Specific files. He can also Add any other Project
Member’s name if he wish to notify them as well. (Note : At this stage documents has not been formally Accepted or Rejected, it is to
intimate the final reviewer about the document).
Step 6 : ITC Project Manager will get notified about the Final Review (since he is the Final Reviewer). He will open the Review and Click Start
Review.
Step 7 : He will review the comments and markups provided by Initial Reviewer and will provide his Comments and Markups, Save it and
Ultimately APPROVE, REJECT and APPROVE WITH COMMENTS. And Click END REVIEW. (Note : This is the stage where documents are
formally Approved, Rejected, Approved with comments).
Step 8 : Now ITC Manager will click the Reviews tab and go to that specific review, open the files which were reviewed and click the 3 dots on
the top right corner. And from there he will share the link to the Contractor/Vendor and mention which documents has been APPROVED or
REJECTED or APPROVED WITH COMMENTS (In case of Multiple documents).
Step 9 : The Contractor/Vendor will receive a mail with the link. Link will divert him to the reviewed documents with all the Comments and
Markups in it. He has to incorporate all the changes for the Rejected document and Reupload the document in the respective folder.
11
Guide/Reference for Consultant-MEP
12
Guide/Reference for Consultant (Initial Reviewer)
• Once ITC Package Manager will initiate the review you will get notified via an email.
• You can go to the review tab or can directly click the link attached with the mail and you will see all the reviews which has
been initiated.
Review Tab
Start Review
Guide/Reference for Consultant (Initial Reviewer)
• You click the document you want to review (in case of multiple documents).
Click here to
Different Markup
switch to
Options
markups
Write your Comments
and Click Add
Guide/Reference for Consultant (Initial Reviewer)
• As you click the Markup options, screen will appear with a list of previous markups (if provided). You add your markup and
click Save Markup. And close the file.
Release task
Guide/Reference for Consultant (Initial Reviewer)
• You will be able to see the number of Markups and Comments which has been provided in the file.
You will
You will see the see theof
number number of
comments
comments
You will see the number of
Markups
Guide/Reference for Consultant (Initial Reviewer)
• Once you are done Click the Submit Review tab
Submit Review
Guide/Reference for Consultant (Initial Reviewer)
• After you click Submit Review, a pop-up will appear here you provide the notes regarding which document has been
approved and which had been rejected from your end. And Click Submit
Guide/Reference for Consultant (Initial Reviewer)
• You can further Notify any other Project Member and you can also write any message if you wish. After that click Send.
• ITC Package Manager will get notified once you send it from your end.