Time Line for Ash Handling System

Design Change Approval


by Contractor
Design Change
Approved by PLN
MOM
Joint Inspection of Ash
Valley shows that Center Rework of Retaining
chute of Existing Plant to VO Discussion Wall . Contractor will be
Suralaya #8 was 91m. submitted their new
Design of Ash Valley on
25/01/2011.

12/03/2007 ????? 19/08/2009 15/02/2010 21/09/2010 ????? 18/01/2011 20/01/2011 21/01/2011

Joint Inspection for Design


Kontrak No. MOM MOM Joint Inspection Calculation of Stone
Masonry
048.PJ/041/DIR/2
007
4.5.20.2 Furnace Design revision on PT Indonesia Power Ash Valley Design was
Bottom Ash Removal Approved Drawing of proposed adding “Bak built on …….
System BC-4 by Contractor Kontrol & Flowmeter”
to Ash Valley Design
“…the ash shall be Letter from Indonesia
dumped into ash Power (IP) to PLN
disposal area by using subject to Distance
mobile truck." between Discharge
Chute of Conveyor