Vendor Perspective
Submitted by Group 3
Chirag Gupta (34BM15)
Deepak Kumar Sood (34BM17)
Madhur Ranjan (34BM20)
Introduction
• How vendor firms make choice about agile methodologies in software projects and their fit.
• A development methodology has a direct relationship with managing project complexity
• Vendors choose the methodology based on
• usability
• Maintainability
• Reliability
• Portability
Agile methodologies in whole
Different authors
• Strong training mechanism)
• project management process (strong requirement
management)
have summarized • configuration management(communication management
processes)
key dimensions of
• team environment (team location, self-organized teams)
• customer involvement (strong relationship with customers,
customer having full authority)
agile • innovation
• rapid response to change
methodologies • initiative
• Learning
• project size
• highly competent personnel
• criticality
• Reliability
• safety issues
Research Methodology
Follow a deductive case study approach (analyzing qualitative data)
3 companies Chosen
S. No Company Name Total Emp Turn Over (Rs) Business Focus No. of
Projects
1 ABC Limited 100000+ 40 Million IT, Consulting, 3
BPO
2 DEF Tech Limited 100000+ 600 Billion IT, Consulting 1
3 GHI Technologies 100 IT, Consulting 1
All Diverse projects viz. 2 projects (SCRUM with pair programming, 2 project (SCRUM) and
1 project with XP.
Respondents must fulfill 3 criteria
10 years experience minimum in SDLC projects
Minimum 5 agile project experience
Experience in methodological decision of project management
Data Analysis Framework
• Two frameworks used to analyze data
Framework 1 Framework 2
• Agility degree was determined by the • Agility degree was determined on variables from project
variables from project scope, features, management support, SDLC, availability of concrete
agile values and development process guidance for application, adaptability in actual use.
Each methodologies and frameworks has its own pros and cons
Determinants of agile methodology for development
Determinants P1 P2 P3 P4 P5
Agile Method Scrum + PP Scrum Scrum + PP XP Scrum
Project Size Medium Large Large Medium Small
Development style Iterative, DA Accpt testing driven Test driven dev, DA Fixed price model, Iterative, DA
dev Test driven dev
Requirements uncertainty High Medium Medium Low High
Cost and time estimation accuracy Low Medium Medium High Medium
Perspectives P1 P2 P3 P4 P5
Project management support Iteration Manager Scrum Master Scrum Master, Scrum of Project Manager Sprint Planning & daily Scrum
Scrum Master meeting
Software development life cycle Life cycle for Architecture and design – No requirement Customer validation, 2 sprints of design and
requirements, Iteration-1 phase. finalisation. acceptance testing and planning. At the end of each
design and system Development- Test cases Dry run on initial iteration release of usable sprint build and demo is
testing. phase. Unit testing and product. The project done and moved to
Implementation weekly integration testing followed all principles. acceptance. At the end of 4th
phase doesn’t in same sprint and sprint release planning done
follow any functional testing of and moved for production.
particular life cycle previous sprint in
subsequent sprint
Availability of concrete guidance Implementation Subjectively driven with Best practices used for Derived from practical Emphasis on Abstract
for application phase of design, no concrete guidance requirement gathering settings and concrete principles over concrete
coding and unit and integration testing guidance guidance for flexibility in
test relied on phase. Rest life cycle was development
abstract principles free flow
Adaptability in actual use Adaptability in High Adaptability wears Flexibility is required for XP followed rules but Situation based adaptability,
actual use but not the team soon due to adaptability Principles and process no pre-described practices
in adaptation rules unexpected changes were changed
Analysis of agile methodology for development
Final Variables P1 P2 P3 P4 P5
Reasoning High Requirement High Requirement High Requirement The project was High Requirement volatility +
volatility + Low to volatility + Low to volatility + Low to repetitive , Low to medium cost and
medium cost and medium cost and time medium cost and time requirements were time estimation accuracy
time estimation estimation accuracy estimation accuracy stable and estimations
accuracy were near accurate
Conclusion
The purpose of this study was to develop understanding about the choice of agile development
methodologies in software development projects.
The findings show that the fit was poor for P4 and the decision was made by the client
predominantly based on their prior experience. Other projects considered in the study had a
medium fit with the methodologies chosen however, the decision was again influenced by the
client.
The motivation for the choice of the chosen methodology, the actual choice was guided by more
subjective considerations. These subjective reasons are not fully known as we did not have access
to the client firms due to confidentiality requirements of the vendors involved in the study.
Way forward
This study provides a theoretical basis to conduct future research that could be more
generalizable by following quantitative approach.
The variables identified in this study for understanding choice of agile methodology and their
proposed relationships with the choice could be tested using statistical techniques. Such findings
will provide substantial and valuable guidelines for project management related to software
development.