• We must employ scheduling approaches in a project to coordinate all of its
parts so that they work in tandem. A timetable should be proportionate to the project's time frame, and all of the project's resources should be utilized to their full potential. • A schedule is a list of all the actions that must be completed throughout the implementation and execution of a project within the allotted time frame. A project schedule assists in prioritizing work and completing a project in a timely manner. • Since Government of Gujarat (GoG) through Roads and Buildings Department (R&BD) constructs roads across the state. The scope of our project revolved around highways hence CPM i.e., Critical Path Method was used in this. CPM manages predictable activities whereas PERT manages unpredictable activities. Therefore, for the project CPM was used as it is widely used in highway projects because the range of activities like alignment, land acquisition, excavation, backfilling, concreting, curing etc have a defined time of completion. WBS: Work Breakdown Structure