Professional Documents
Culture Documents
Contract Management
Lesson -9-Cont’d
Contract Administration
Prof. Dr. Shahid Naveed
2022
Claims
Claims (Slide Repeated)
• Claims are the unfortunate result of change on conditions that the
contractor considers to be a materially changed condition, but the owner
does not agree.
• Often claims result from a disagreement on the meaning of the terms of
the contract. Claims often result from poor communication and a claim
will be compounded by poor communication.
• Contracts require that a contractor notify the owner of claims within a
specified number of days, and then proceed with the work. The contractor
cannot refuse to proceed with work that is within the original scope, but it
is sometime difficult to determine whether work is within the original
scope.
• Contractors must read the contract to determine what process must be
followed to file a claim.
• Successful settlement of a claim depends on adequate documentation. Con
tractors have learned to maintain high-quality daily records of the events
in the field. Good records include meeting minutes, records of telephone
conversations, project photographs taken regularly, and other records that
would re-create an accurate picture of the events that caused the claim.
Contractor’s claims (FIDIC)
• Clause 20.1 provides for and sets out procedure.
• Claims include:
• Delayed Drawings or Instruction – clause 1.9
• Late Access or Possession clause 2.1
• Setting out reference point errors – clause 4.7
• Adverse unforeseeable conditions – clause 4.12
• Extension of Time – clause 8.4
• Interference with tests – clause 10.3
• Variations – clause 13.3
• Change in law – clause 13.7
• Force Majeure – clause 19.4
Contractor’s claims [sub-clause 20.1]
• If Contractor considers it is entitled to EOT and / or additional
payment, under any Clause, it shall give notice to Engineer
detailing event or circumstance.
• Notice MUST be as soon as practicable but No later than 28
days after becoming aware, or should have become aware of
event of circumstance.
Failure Will Result In Loss Of Entitlements And No Claim!!
• Contemporary records must be kept. Within 42 days of
becoming aware, or should have become aware, of event (Not
date of notice) fully detailed claim to be submitted.
Managing claims
• Understanding
of the Contract
of the allocation of risks
of the obligations of the Parties.
• Recognize the notice periods and any other time
requirements
Presentation of claims
Claims – principles of presentation
• Cause
• Effect
• Justification
• Evaluation
• Substantiation
Presentation of claims
Vital contemporaneous supporting evidence might include :
Tender / Contract Information
• Works Records Sheets • Photographs (dating facility essential)
• Daily Record of labor and plant, • Agreed measurements of works
staff etc. • Delay Notices
• Materials received / issued records • Claim Notices
• Drawings Register • Material Orders / Invoice
• Correspondence and Meeting • Subcontract Accounts
Minutes • Cost Reports
• Site Diaries • Program Updates
• Site Instructions
• Variation Orders
• Day-work
Presentation of claims
A well presented claim should fall conveniently into sections, each
one with its own important part to play in the overall presentation
An example format could be:
1. Introduction
2. Executive Summary
3. Contractual Terms
4. Planned Sequence of Construction
5. Actual Sequence of Construction
6. Events and their Affects upon the Sequence of Construction
7. Program Affects
8. Evaluation
Liquidated Damages &
Substantial Completion
Liquidated Damages and Substantial
Completion
• Liquidated damages are paid by the contractor to the owner if the contractor
exceeds the allowed contract time period.
• A contract may require liquidated damages of a few hundred dollars per day
to many thousands of dollars per day. The amount is determined before the
contract is advertised, and it is based on an estimate of actual costs the
owner or the public would incur by the late completion of the work.
• To avoid the imposition of liquidated damages, contractors must actively
manage the project schedule. The project manager must have a realistic
schedule to complete the work. In addition, change order work must always
include additional time for the added work as part of the negotiation
process.
Liquidated Damages and
Substantial Completion
• Contractors must know the requirement of each contract and
the definition of substantial completion.
• The general rule (not a legal rule) is that the work must be
done. The facility must be ready for the owner to move into
and use. There can still be a "punch list" of items the con
tractor needs to correct to reach final completion. Punch list
items can be anything from touching up paint to completing
the landscaping. Punch list items cannot be substantial items
of work such as installing the windows and doors, or
completing the air-conditioning system.
• If main items of work are complete, the facility may be
"substantially complete."
Final Inspection
Final Inspection
• When project is substantially complete and the owner agrees
that the project is ready for acceptance, as defined in the
contract documents, the "final inspection" will be scheduled.
• Contractors should treat the final inspection as a formal
contract requirement. It is the owner's last formal opportunity
to walk through the facility to identify remaining work items
and to formally accept ownership of the facility. The final
inspection is used to generate the final punch list. The owner
and the contractor agree on the punch list items.
• When the punch list items are done, the contract requirements
are fulfilled.
• The contractor should be required to return to the site only for
possible corrective work covered in the warranty.
Defect Liability Period
Defects liability period