Topics of Presentation

 Overview of Turbine

 Concept of Governing System

 Functioning of EHC Circuits

 Turbine Start Up Procedure

 TSI & TSC System

 Turbine Protection System


Turbine Block Diagram
Turbine Extractions
Ext. Source Of Extraction Destination Equipments
No

1 13th stage of HPT HPH-8

2 CRH HPH-7

3 3rd stage of IPT HPH-6 *

3 3rd stage of IPT TDBFP

4 6th stage of IPT DEAERATOR

5 8th stage of IPT LPH-4

6 11th stage of IPT LPH-3

7 2nd stage of LPT LPH-2

8 4th stage of LPT LPH-1


Turbine Components

 Turbine: HPT, IPT, LPT1 and LPT2


 Turbine Bearings: 08
 Generator / Exciter Bearings: 04
 Turbine Stop Valves: 04 (HPSV-1&2, IPSV-1&2)
 Turbine Control Valves: 08 (4 HPCV & 4 IPCV)
 CRH Check Valves: 02 ( With Bypass lines for warm up)
 Motor driven Shut Off valve in non-stabilized oil line to
Check Valve
 Motor driven warm up Shut Off valves for HPCV-3 & 4
 Governing Box
Overview of Governing Box
Governing Box Components

 Motor operated Control Gear to generate resetting / protection


oil & control oil for S.V./ Summators

 Two Manual trip devices

 Two Over Speed Governor Slide valves (110 % & 111 %)

 Two Remote Trip Solenoids

 Slide Valve for ATT with two solenoids


Governing System
 Combination of throttle & nozzle governing

 IP Turbine has throttle governing – all four control valves open


simultaneously

 HP Turbine has nozzle governing – all four control valves open


in preset sequence

 Resetting of Turbine is done by Control Gear operation

 Operation of Stop & Control Valves and CRH Check Valves are
done by spring type hydraulic servomotors

 Servomotors are closed by spring action during loss of oil


pressure
Governing System

 HPT control valves open only after achieving preset load


(12% of 660 MW)
 Opening time of control valve is 1.5 sec
 Closing time of Stop valve in case of operation of protection
is 0.3 sec
 Turbine maximum speed is restricted to 108% in case of
generator disconnected from grid
 Over speed protection system stops steam supply in HPC in
< 0.5s
 Speed Controller Droop is adjustable from 2.5% to 8% (with
dead band of 0.04%)
Resetting of Turbine
Resetting of Turbine
 Stabilized oil pressure of 50 Ksc is supplied to Control Gear

 The control gear (AE001) is moved from closed position (0


degree) to open position (90 deg)

 Oil is first supplied to reset the over speed governor slide


valves

 Subsequently Protection Oil is generated and supplied to


protection devices

 Finally, Control Oil for Stop Valves servomotors & Control


Oil for EHC-summators are generated
Operation of Stop Valve
Operation of Stop & Control Valves
 Control Oil pressure in S.V. servomotor moves up slide valve,
providing Header Pressure Oil under the piston for S.V. opening

 Header Pressure Oil is supplied to C.V. valve servomotors via


locking pilot valve & traction/bush arrangements. Opening of C.V. is
governed by Control Oil from EHC-Summator

 During loss of Header Pressure Oil, the servomotors are closed by


spring action

 During loss of Control Oil pressure, Bush & Traction of Pilot valve
travels up shutting off head pressure oil supply to C.V. servomotors,
resulting control valve closing

 During S.V. ATT, bush & Traction do not travel up due to slide valve
downward movement by ATT motor
Components of EHC

EHC comprises of following controllers:

1. Speed Controller

2. Pressure Controller

3. Load Controller

4. Position Controller
Interesting, right?
This is just a sneak preview of the full presentation. We hope you like it! To see the
rest of it, just click here to view it in full on PowerShow.com. Then, if you’d like, you
can also log in to PowerShow.com to download the entire presentation for free.

You might also like