Professional Documents
Culture Documents
C H A P T E R FOUR
Project Control
2
Monitor and Control
Cost
Schedule
Scope
Stakeholder satisfaction
Changes
To the progress measurement baseline
To the description of the product of the project.
5
Baseline Development
7
Benefits of Project Controls
9
Project control cycles
10
Three Types of Controls
11
Three Types of Controls process
12
1. Cybernetic control
13
2. Go/No-go Controls
18
Control Systems
20
Project Controlling Tools
21
Controlling Tools for Individual Work Packages
Work packages 1.1, 1.2, 2.1.1 and 2.2.2 are complete, 2.1.2 and
2.2.1 started but not yet complete, and 2.1.3, 3.1 and 3.2 not yet
started. 23
Project control tool: Network diagram
24
Project control tool: Gantt chart
If we want to know our project status in terms of schedule we use the Gantt chart.
A blue bar for each work package indicates its planned time and a red bar below it
its actual time.
For example, work package 1.1 was started on time, but it took one week longer
to complete it; work package 1.2 was started one week later and finished one
week later, etc. So, as of twelve weeks into our project, it seems to be one week
behind schedule. 25
5. Earned Value Analysis (EVA) or Earned Value
Management
26
….cont’d
To calculate Cost Performance Index (CPI) and Schedule Performance Index (SPI)
with the following formulas:
In our example, we obtain CPI = 0.609 and SPI = 0.778 indicating
that we are over budget and behind schedule. Earlier presentations
refer to
Cost Variance CV = BCWP – ACWP = EV – AC
Schedule Variance SV = BCWP – BCWS = EV – PV
27
Use of Logframe for project control
29
By:Mohammed G (Msc,
Assistant professor), Jimma
30
University
PUT THIS KNOWLEDGE TO WORK!