Activities A B C D E F G H I J K
Predecessor(s) -- -- -- C B B A F D,E G H,J
Duration (days) 5 5 3 7 17 11 9 9 11 27 7
1
A J 8
K 9
G
2 7
Cont’d…
• NO! Since activity “J” lies on the critical path,
any delay on J will cause delay on the project.
• YES! Since activity “F” does not lies on the
critical path, it can be delayed to some extent
without causing any delay in the project.
• YES! Since the desired completion time (30
days) is less than the latest completion time.
i.e. critical paths time = 48.