A - 5
B A 8
C A 6
D B 9
E B,C 6
F C 3
G D,E,F 1
Draw the Model
Critical path
Calculations
If ES = LS and EF = LF then TF = FF = 0
the resources.
FF TF LF LS EF ES Duration Activity
0 0 5 0 5 0 5 A
0 0 13 5 13 5 8 B
0 5 16 10 11 5 6 C
0 0 22 13 22 13 9 D
3 3 22 16 19 13 6 E
8 8 22 19 14 11 3 F
0 0 23 22 23 22 1 G