Calculation of ES,EF,LS,LF & SLACK(FLOAT)

Find the Latest allowable time for the events and


prepare a time schedule and calculate float for
each activity and show the critical path for the
given network diagram. Use the figure below.
Cont’d…
Finally…
Additional Example
Draw the logic network and perform the CPM
calculations for the schedule shown next.
Activity IPA Duration

A - 5

B A 8

C A 6

D B 9

E B,C 6

F C 3

G D,E,F 1
Draw the Model
Critical path
Calculations

If ES = LS and EF = LF then TF = FF = 0

Which indicate the criticalities of the activity or

the resources.
FF TF LF LS EF ES Duration Activity

0 0 5 0 5 0 5 A

0 0 13 5 13 5 8 B

0 5 16 10 11 5 6 C

0 0 22 13 22 13 9 D

3 3 22 16 19 13 6 E

8 8 22 19 14 11 3 F

0 0 23 22 23 22 1 G

The end activity’s ES Or EF is computed from the critical path


ES,EF
Diagrammatically
Activity
LS.LF