Professional Documents
Culture Documents
Track Transition
Track Transition
1
1
Different Track Types
• For different bed type, specific track types are
proposed at different location
• Ballasted Track:
• The least Capex and easiest to maintain for
areas prone to ground settlement.
• Mostly adopted in tracks outer side of City
where space is available.
• Plinth Track / Slab Track:
• Used on Elevated / Underground Structures
• Reduced self weight and ease of
maintenance.
• Embedded Track:
• Used in congested areas, at grade track
• Interface with vehicular traffic / road
intersections or at grade stations.
2
Need for Track Transition
• There is location where two different track types meet. At such location track transition is needed to be provided.
• For operation of trains on location where two different track types meet, it is utmost important to control
variation in rail deflection, and track transition fulfils the same purpose
• The limit of such variation is 0.5mm per unit length L, where L is defined by higher of the followings:
• 0.5 x V in m (where V is speed in m/s)
• Length of Wagon or Locomotive
• Deflection Control:
• Transition zone is provided to avoid sudden
variation in deflection.
• In case the total deflection (d) is more than
0.5mm, the length of transition zone shall be
calculated as (L * d /0.5)
3
Conventional Solution to Transition Zone
• Globally various railways are using specially selected and
compacted back fill material behind abutment
• This ascertains gradual change in stiffness of track.
• Figures here show global practice
• However, these solutions are mostly aimed at operation of
conventional railway
• For light rail:
Track Transition of Italian Railway
• Some typical details available in TCRP, but these are area
and system specific
• Need for Global unified method for transition zone is there
• The procedure described here follows analytical approach
based on the concept by EN code.
• This principle, can also be adopted for any other railway system
suitably modifying with respect to the input data. Track Transition of German Railway
4
Indian Railway Provision
5
Design Philosophy
6
Input of Standard Data
Parameters Value Units
• The above are project specific and do not change G 80 769,23 N/mm2
based on corridors or suppliers
7
Vendor Specific Data
Parameters Value Units
• Selected fastening system Plinth Track Fastening Stiffness, Static 22,5 kN/mm
properties
• Sleeper dimension,
Static to Dynamic Stiffness ratio 1,25
• Fastener / Sleeper Spacing
• Such data has a huge role to play in Toe Load Max per fastener 13 kN
overall deflection of rail.
8
Analytical Computation
• This Eisenmann’s
method, is “standard”
for track sections.
• This is followed in EN
16432 and DB RIL
820.2020 standard Summary of Computation by Analytical
practices also Method for Deflection
9
Sample Computation
• Dynamic Impact Assessment:
• Different Methods are adopted for computing the dynamic impact factor, some common
practices are provided in the table, based on:
• Speed 80kmph 1 AREA (American Railroad
• Wheel dia 880mm Engineering Association)
Formula 1.47
• 19m viaduct span 2 Eisenmann's Formula 1.23
3 ORE (Office of Research
• Dynamic Load is considered as Wheel Load * Dynamic Factor and Experiments of the
International Union of
• Deflection under Load: Railways) Formula 1.31
4 Indian Railway Formula,
• The Railpad Modulus and System Modulus is computed from standard practices (MM Aggarwal) 1.37
• Deflection of rail under wheel load is computed from Analytical Method, example shown 5 German Formula
6 Bridge Rule, RDSO
1.21
1.47
in next slide.
• Alternatively FEM Modelling can be done for this stage. Summary of Impact Factor
• Relative Displacement:
• The relative deflection is computed for both types of track at the junction
• Difference between the above is the relative displacement, and this governs the
transition zone design
10
Sample Computation : Deflection Check
Single Wheel Case Plinth Track Single Wheel Case Ballasted Track
11
Dimensioning and Provision of Transition
Zone
• Intermediate Zone Requirement:
• The Change in rail deflection is 0.859mm (2.173-1.314 mm,
from previous slide)
• Number of intermediate zones required will be 1, considering
maximum deflection change allowed is 0.5mm.,
• In case the change in rail deflection exceeded 1mm, but less
than 1.5mm, 2 such intermediate zones would have been
provided.
• Length of Intermediate Zone:
• The length of such transition slab, with respect to 80kmph
speed will be (80/3.6)*0.5m = 11.11m or say 12m.
• Total Provision:
• Total length = 1*12m = 12m in this case.
• Width of the transition slab shall be equal to the spread of
ballast bed at minimum.
12
Different types of Transition
• Target:
• The objective is to provide smooth change of deflection in rail over transition
zone.
• This can be achieved by varying the stiffness in the transition zone which
impacts the rail deflection.
• Different approaches can be used in order to achieve the same
• Concrete Slab:
• include a Reinforced concrete slab / PCC Slab under the ballast bed to control
the stiffness
• This becomes fixed asset which needs minimal maintenance in its service life.
• Alternate Option:
• Using different stiffness of elastic pad to achieve the stages in rail deflection
• Using glued ballast or using additional rail to add to rigidity of sleeper to
achieve required deflection range.
13
Concrete Slab Transition System
14
Concrete Slab Transition –Sample
Calculation
•Project Data:
• Young’s Modulus for concrete is computed as under • Thickness of Plinth Track : 185mm
For Plinth, = 29580 • Grade of Concrete for Plinth: M35
For Transition, = 22360 • Grade of Concrete for Transition Slab: M20
• Equivalent thickness of bound base (considering same System Modulus • System Modulus for Plinth Track: 42.9MPa
for both systems) under the ballasted track at junction of Rigid Track will
be computed from the following equation: • System Modulus for Ballasted Track: 21.9 MPa
= 0.9*185*1.098 = 183mm
• The Thickness thus found is factored with the ratio of System Modulus
of Rigid Track and Flexible Track to get the Actual Thickness
= 358 mm
Hence, the proposed thickness is 358mm, which can be rounded as
350mm (generally rounded to multiplier of 25mm is proposed for
transition slab thickness)
15
Alignment Recommendation in Transition Area
• Horizontal Alignment:
• There is no such specific bounding rules for the track,
• However, the stretch needs to be checked for adequacy in stability.
• Vertical Profile:
• The transition zone is needed to specifically take care of proper drainage
• Minimum 0.3% gradient is needed to be provided in the transition zone.
• Point to Remember:
• Drainage has to be properly planned in the transition zone.
• Check for prevention of Mud Pumping Phenomena needs to be ascertained.
16
Derailment Risk Mitigation in Transition
Area
• Derailment Risk:
• The transition zone is often at the approach of Elevated / Bridge /
Tunnel Section or near the critical area where embedded track is
provided.
• In such area, the effect of derailment should always be
minimized.
• Mitigation Measure:
• In such area, it is recommended to use either Guard Rail or Crash
Barrier in order to minimize the impact of such derailment.
• Ballastless track area mitigation:
• The sections on Elevated corridor inevitably has the provision for
derailment guard which minimizes impact of derailment.
• In case of Embedded Track the section is provided with grooved
rail, which in turn helps in preventing derailment
17
Design of Transition Slab