Professional Documents
Culture Documents
1
Production planning
Meaning:-
Production planning involves management decisions on the
resources that the firm will require for its manufacturing
operations and the selection of these resources to produce the
desired goods at the appropriate time and at the least possible
cost.
22
Production control
Meaning:-
Production control guides and directs flow of production so
that products are manufactured in a best way and conform to
a planned schedule and are of the right quality. Control
facilitates the task of manufacturing and see that every theme
goes as per the plan.
Meaning:-
Production Planning and Control is concerned with
directing production along the lines set by the planning
department.
Definition:-
"Production Planning and Control is the co-ordination of series
of functions according to a plan which will economically
utilize the plant facilities and regulate the orderly movement
of goods through the entire manufacturing cycle from the
procurement of all materials to the shipping of finished
goods at a predetermined rate."
44
The PPC Cycle
5. Facility location
7. Capacity planning
8. Line planning
8
• Job or Scheduling: Preparation of time and action
calendar
Taskfor each order from order receiving to shipment
(T&A). The job schedule contains list of tasks to be processed
for the styles. Against each tasks planner mentions when to start
a task and what is dead line for that task. Name of responsible
person (department) for the job is being listed. For example,
scheduling planned cut date (PCD), line loading date etc.
9
• Process Selection & Planning: Processes needed to complete an
order, vary style to style. According to the order (customer)
requirement PPC department select processes for the orders.
Sometime extra processes are eliminated to reduce cost of
production.
10
10
• Capacity Planning: PPC department plays a major role during
order booking. They decide (suggest) how much order they should
accept according to their production capacity. Allocating of total
capacity or deciding how much capacity to be used for an order
out of total factory capacity. Regularly updating factories current
capacity (production capacity).
11
Garments Analysis for Production Planning
12
12
Garments Analysis for Production
Planning
During garments analysis we should check the following points
very carefully:
❑Garments observations,
❑Key seam quality areas by operation, stitch & seam construction and
SPI,
❑Point out how many operations are involved in the particular item,
❑ Accordingly make a diagram of machine lay out,
❑Point out the critical operation where we can expect the “bottle neck”
during production,
❑Considering bottle neck allow extra machines for that operation to
keep production flow as you expect (Line Balancing),
❑ Find out the input operation and out put operation 1
13
also. 3
Production Planning:
14
Load = Order or Contract Size x Work Content
For Example:
• Operators = 24
• Working minutes = 8 hrs
• Efficiency = 69.78%
• Absenteeism = 5%
• SMV = 20.1
• Contract Size = 5000 pcs
15
Q. Calculate load and capacity of that order.
• Solution:
Load = Contract Size X Work Content (Total SMV of the Garment)
= 5000x20.1
= 100500.00 (ans.)
Capacity = Actual Minutes
= no. of m/c operators X working minutes x efficiency x presents %
= 24 x (8x60)x0.6978 x .95
= 7636.7232 (ans.)
16
Q. Kmart placed an order of 40000pcs polo shirts to Viyellatex
ltd. Calculate the load and capacity assuming following data.
✔Operators = 52
✔Working = 8 hrs
minutes = 71%
✔Efficiency = 4%
✔Absenteeism = 26.2
✔SMV
17
Production planning – Scheduling:
19
• A) Average weekly load
= 19,20,000 SMV/13
= 147692 SMV
• B) weekly capacity
= 80 x (40X60) X .85
x .96
= 156672 smv
⮚ C) yes .
20
The Line Scheduling
Rule:
During making the schedule for line following
points are considered:
21
There are two types of scheduling :
1. Reverse Scheduling
Schedule starts from the “Due Date (del. Date) & schedule back
ward. External due date considerations will directly influence
activity scheduling in certain structures. Schedule of this type
are usually depicted on the Gantt Charts.
2. Forward Scheduling
Same as earlier but schedule forward from a given start time.
22
Some important formula
23
Some important formula
25
CM calculation???
• CM per pcs= (Factory total expense per month x no of m/c required for making the garment)
(total m/c x total working hrs per month x target production)
26
CM calculation
27
CM calculation
28
CM calculation (solution)
Garment CM Calculation:
(𝐹𝑎𝑐𝑡𝑜𝑟𝑦 𝑡𝑜𝑡𝑎𝑙 𝑒𝑥𝑝𝑒𝑛𝑠𝑒 𝑝𝑒𝑟 𝑚𝑜𝑛𝑡ℎ 𝑥 𝑛𝑜 𝑜𝑓 𝑚/𝑐 𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑑 𝑓𝑜𝑟 𝑚𝑎𝑘𝑖𝑛𝑔 𝑡ℎ𝑒 𝑔𝑎𝑟𝑚𝑒𝑛𝑡 )
=
(𝑡𝑜𝑡𝑎𝑙 𝑚/𝑐 𝑥 𝑡𝑜𝑡𝑎𝑙 𝑤𝑜𝑟𝑘𝑖𝑛𝑔 ℎ𝑟𝑠 𝑝𝑒𝑟 𝑚𝑜𝑛𝑡ℎ 𝑥 𝑡𝑎𝑟𝑔𝑒𝑡 𝑝𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑜𝑛 )
(50,00,000 𝑥 25)
= BD
(100 𝑥 26 x 8 𝑥 200)
T
= 30.048 X 12 [per
BDT dozen]
= 360.58 / [1$= 81
81 $ BDT]
= $4.45 /
dozen Ans: CM of this garment is $4.45 2
29
per dozen. 9