Professional Documents
Culture Documents
Project Appraisal
y Overview and vocabulary y Methods y Payback, discounted payback y NPV y IRR y Sensitivity Analysis y Breakeven Analysis
Initial outlay
...
two reasons:
accrual concept. y Second, for computing profit, expenditures are arbitrarily divided into revenue and capital expenditures.
Change in accounts receivable y Change in inventory y Change in accounts payable y Change in Capital Expenditure y Free Cash Flows
y
Salvage value of the new asset Salvage value of the existing asset now Salvage value of the existing asset at the end of its normal Tax effect of salvage value
10
1 g
kg
N n 1 ! kg
11
12
Case Study
y Warehouse Case
FREE LUNCH
Cost of Capital
y The project s cost of capital is the minimum
required rate of return on funds committed to the project, which depends on the riskiness of its cash flows. y The firm s cost of capital will be the overall, or average, required rate of return on the aggregate of investment projects.
15
. . . .
Government bonds isk-free security
.
Preference shares
Equity shares
orporate bonds
isk
16
firm s WACC: y Calculate the cost of specific sources of funds y Multiply the cost of each source by its proportion in the capital structure. y Add the weighted component costs to get the WACC.
WACC is in fact the weighted marginal cost of capital (WMCC); that is, the weighted average cost of new capital given the firm s target capital structure.
Growth Model
Cost of Debt
y Tax adjustment
WACC
y Cost of capital (WACC)=
(Cost of Equity x Proportion of equity from capital)+ (Cost of debt x Proportion of debt from capital)+
2.4
3 80 50
60 100 -30 0
= 2.375 years
1.6 2
3 20 40
70 100 50 -30 0 20
Strengths of Payback: 1. Provides an indication of a projects risk and liquidity. 2. Easy to calculate and understand. Weaknesses of Payback: 1. Ignores the VM. 2. Ignores CFs occurring after the payback period.
CFt . NPV ! t 1 t! r
Cost often is CF0 and is negative.
CFt NPV ! CF0 . t 1 t !1 r
n
NPVS = $19.98.
accept S because NPVs > NPVL . y If S & L are independent, accept both; NPV > 0.
IRR is the discount rate that forces PV inflows = cost. This is the same as forcing NPV = 0.
1 10
2 60
3 80
Enter CFs in CFLO, then press IRR: IRRL = 18.13%. IRRS = 23.56%.
Individual Assignment
y Complete All the questions