Professional Documents
Culture Documents
Project Management: by DR Aatma Maharajh
Project Management: by DR Aatma Maharajh
Management
By Dr Aatma Maharajh
Learning Objectives
Project Phases
Mass Production
Volume
Batch
Production
Project
Solution
Project Phases Prototype Design
Development
Milestones
Lessons Learnt Commissioning
Source: PMBOK 6 Ed (2017, p 20)
th Review
“… the application of
knowledge, skills, tools and
techniques to project activities to
meet the project requirements.”
What Is Project
Management? - PMBOK Guide - 6th Ed (2017)
Class exercise:
Effective Project
Management
Optimise Optimise the use of organisational resources
Identify,
recover, or Identify, recover, or terminate failing projects
terminate
Uncontrolled expansion of the Loss of reputation for the Unsatisfied Stakeholders Failure in achieve the
project organisation objectives for which the
project was undertaken
Source:
https://www.teamgantt.com/free-gantt-chart-excel-template,
Controlling
• Constant monitoring of project
Source: https://www.wrike.com/project-management-guide/faq/what-is-a-
network-diagram-in-project-management/, cited: 02/02/21
Types of Network Diagrams
• Activity-on-Node (AON): A network diagram in which nodes designate
activities.
A C E G
STAR
T
B D
Network Diagram (AOA)
C
2 4
A F
Dummy H
1 Activity E 6 7
B
G
D
3 5
Critical Path Analysis
Activity Description Time (Weeks)
A Build internal components 2
B Modify roof and floor 3
C Construct collection stack 2
D Pour concrete and install frame 4
E Build high-temperature burner 4
F Install pollution control system 3
G Install air pollution device 5
H Inspect and test 2
Total Time (Weeks) 25
Determining the Project Schedule
• This is done using critical path analysis
• Earliest start (ES) = earliest time at which an activity can start, assuming all
predecessors have been completed
• Earliest finish (EF) = earliest time at which an activity can be finished
• Latest start (LS) = latest time at which an activity can start to not delay the completion
time of the entire project
• Latest finish (LF) = latest time by which an activity must finish to not delay the
completion time of the entire project
Activity Name
or Symbol
Notation
Early Start Early Finish
A
ES EF
LS LF
2
Late Start Late Finish
Activity
Duration
Forward vs Backward Pass
• Forward Pass: A process that identifies all the early times.
• Backwards Pass: An activity that finds all the late start and late finish
times.
FORWARD PASS
• Calculated using the following:
• If an activity has only a single immediate predecessor, its ES equals the EF of
the predecessor.
• If an activity has multiple immediate predecessors, its ES is the maximum of all
EF values of its predecessors
Backward Pass
• Calculated using the following:
• If an activity is an immediate predecessor for just a single activity, its LF equals
the LS of the activity that immediately follows it.
• If an activity is an immediate predecessor to more than one activity, its LF is
the minimum of all LS values of all activities that immediately follow it.
Slack Times
• Free time for an activity. Also referred to as free float or free slack.
𝐶𝐶− 𝑁𝐶
𝐶𝑜𝑠𝑡𝑡𝑜 𝐶𝑟𝑎𝑠h =
𝑁𝑇 −𝐶𝑇
Minimizing Costs
• Minimum-Cost Schedule - A schedule determined by starting with the
normal time schedule and crashing activities along the critical path, in
such a way that the costs of crashing do not exceed the savings in
indirect and penalty costs.
Any Questions?
References
• Project Management Institute (2017) A Guide to the project management
knowledge: PMBOK Guide (6th Ed), Project Management Institute, IL:USA