Professional Documents
Culture Documents
9-2
9-2
FIGURE 9.1 COMPANY COST OF CAPITAL
• A company’s cost of capital can be
compared to CAPM required return
Required SML
return
5.5
Company cost
of capital
0.2
0
0.5 Project beta
9-3
9-3
9-1 COMPANY AND PROJECT COSTS OF
CAPITAL
• Company Cost of Capital
9-4
9-4
9-1 COMPANY AND PROJECT COSTS OF
CAPITAL
• Weighted Average Cost of Capital
• Traditional measure of capital structure, risk and
return
WACC (1 Tc )r r
D
D V
E
E V
9-5
9-5
9-2 MEASURING THE COST OF EQUITY
• Capital Structure (CS)
• Mix of debt and equity within a company
• Expand CAPM to include CS
• r = rf + β(rm − rf)
• requity = rf + β(rm − rf)
9-6
9-6
9-2 MEASURING THE COST OF EQUITY
• Estimating Beta
• SML shows relationship between return and risk
• CAPM uses beta as proxy for risk
• Other methods can also determine slope of
SML and beta
• Regression analysis can be used to find beta
9-7
9-7
FIGURE 9.2A CITIGROUP RETURN
9-8
9-8
FIGURE 9.2B CITIGROUP RETURN
9-9
9-9
FIGURE 9.2C DISNEY RETURN
9-10
9-10
FIGURE 9.2D DISNEY RETURN
9-11
9-11
FIGURE 9.2E CAMPBELL’S RETURN
9-12
9-12
FIGURE 9.2F CAMPBELL’S RETURN, %
9-13
9-13
TABLE 9.1 ESTIMATES OF BETAS
9-14
9-14
9-2 MEASURING THE COST OF EQUITY
• Beta Stability
% IN SAME % WITHIN ONE
RISK CLASS CLASS
CLASS 5 YEARS LATER 5 YEARS LATER
10 (High betas) 35 69
9 18 54
8 16 45
7 13 41
6 14 39
5 14 42
4 13 40
3 16 45
2 21 61
1 (Low betas) 40 62
Source: Sharpe and Cooper (1972)
9-15
9-15
9-2 MEASURING THE COST OF EQUITY
• Company cost of capital (COC) is based on
the average beta of the assets
• The average beta of the assets is based on
the % of funds in each asset
• Assets = debt + equity
D E
β assets β debt β equity
V V
9-16
9-16
9-2 MEASURING THE COST OF EQUITY
• Expected Returns and Betas Prior to Refinancing
Expected 20
return (%)
Requity = 15
Rassets = 12.2
Rdebt = 8
0
0 0.2 0.8 1.2
Bdebt Bassets Bequity
9-17
9-17
9-2 MEASURING THE COST OF EQUITY
• Company cost of capital (COC) is based on
average beta of assets
• Average beta of assets is based on the % of
funds in each asset
• Example
• 1/3 new ventures β = 2.0
• 1/3 expand existing business β = 1.3
• 1/3 plant efficiency β = 0.6
• AVG β of assets = 1.3
9-18
9-18
9-2 MEASURING THE COST OF EQUITY
• Company Cost of Capital
9-19
9-19
9-3 ANALYZING PROJECT RISK
PV(fixed cost)
β revenue β fixed cost
PV(revenue)
PV(variable cost) PV(asset)
β variable cost β asset
PV(revenue) PV(revenue)
PV(fixed cost)
β revenue 1
PV(asset)
9-20
9-20
9-3 ANALYZING PROJECT RISK
• Allowing for Possible Bad Outcomes
• Example
• Project Z will produce one cash flow, forecasted at $1
million at year 1. It is regarded as average risk,
suitable for discounting at 10% company COC:
C1 1,000,000
PV $909,100
1 r 1.1
9-21
9-21
9-3 ANALYZING PROJECT RISK
• Allowing for Possible Bad Outcomes
• Example, continued
• Company’s engineers are behind schedule
developing technology for project. There is a small
chance that it will not work. Most likely outcome still
$1 million, but some chance that project Z will
generate zero cash flow next year:
9-22
9-22
9-3 ANALYZING PROJECT RISK
• Allowing for Possible Bad Outcomes
• Example, continued
• If technological uncertainty introduces a 10% chance of zero
cash flow, unbiased forecast could drop to $900,000:
900,000
PV $818,000
1.1
9-23
9-23
TABLE 9.2 CASH FLOW FORECASTS
9-24
9-24
9-4 CERTAINTY EQUIVALENTS—ANOTHER WAY
TO ADJUST FOR RISK
• Risk, Discounted Cash Flow (DCF), and
Certainty Equivalents (CEQ)
Ct CEQ t
PV t
t
(1 r ) (1 rf )
9-25
9-25
FIGURE 9.3 TWO WAYS TO CALCULATE
PRESENT VALUE
9-26
9-26
9-4 CERTAINTY EQUIVALENTS—ANOTHER WAY
TO ADJUST FOR RISK
• Example
• Project A expects CF = $100 mil for each of
three years. What is PV of project given 6%
risk-free rate, 8% market premium, and .75
beta?
r rf β(rm rf )
6 .75(8)
12%
9-27
9-27
9-4 CERTAINTY EQUIVALENTS—ANOTHER WAY
TO ADJUST FOR RISK
• Example, continued
• Project A expects CF = $100 mil for each of
three years. What is PV of project given 6%
risk-free rate, 8% market premium, and .75
beta?
Project A
Year Cash Flow PV @ 12%
1 100 89.3
2 100 79.7
3 100 71.2
Total PV 240.2
9-28
9-28
9-4 CERTAINTY EQUIVALENTS—ANOTHER WAY
TO ADJUST FOR RISK
• Example, continued
• Project A expects CF = $100 mil for each of three years.
What is PV of project given 6% risk-free rate, 8%
market premium, and .75 beta?
• Assume cash flows change, but are risk-free. What is new PV?
Project A Project B
Year Cash Flow PV @ 12% Year Cash Flow PV @ 6%
1 100 89.3 1 94.6 89.3
2 100 79.7 2 89.6 79.7
3 100 71.2 3 84.8 71.2
Total PV 240.2 Total PV 240.2
9-29
9-29
9-4 CERTAINTY EQUIVALENTS—ANOTHER WAY
TO ADJUST FOR RISK
• Example, continued
Project A Project B
Year Cash Flow PV @ 12% Year Cash Flow PV @ 6%
1 100 89.3 1 94.6 89.3
2 100 79.7 2 89.6 79.7
3 100 71.2 3 84.8 71.2
Total PV 240.2 Total PV 240.2
9-30
9-30
9-4 CERTAINTY EQUIVALENTS—ANOTHER WAY
TO ADJUST FOR RISK
• Example, continued
• Project A expects CF = $100 mil for each of three years.
What is PV of project given 6% risk-free rate, 8%
market premium, and .75 beta?
9-31
9-31
9-4 CERTAINTY EQUIVALENTS—ANOTHER WAY
TO ADJUST FOR RISK
• Example, continued
• Project A expects CF = $100 mil for each of three years.
What is PV of project given 6% risk-free rate, 8%
market premium, and .75 beta?
• Assume cash flows change, but are risk-free. What is
new PV?
• Difference between 100 and certainty equivalent
(94.6) is 5.4%
• This % can be considered annual premium on risky
cash flow
Risky cash flow
certainty equivalent cash flow
1.054
9-32
9-32
9-4 CERTAINTY EQUIVALENTS—ANOTHER WAY
TO ADJUST FOR RISK
• Example, continued
• Project A expects CF = $100 mil for each of three years.
What is PV of project given 6% risk-free rate, 8%
market premium, and .75 beta?
• Assume cash flows change, but are risk-free. What is
new PV?
100
Year 1 94.6
1.054
100
Year 2 2
89.6
1.054
100
Year 3 3
84.8
1.054
9-33
9-33