Professional Documents
Culture Documents
Case Study. Gonzales
Case Study. Gonzales
N
The climate of Sydney, the
capital of New South Wales, lying
on the southeast coast of Australia,
is subtropical oceanic, with mild
winters and warm summers.
The wind blows frequently,
especially from October to April,
that is, in the warm season (being
that it's in the Southern
Sun RiseHemisphere, the seasons in Sydney
are reversed in comparison to
Europe or North America).
In the warm half-year, from
Sunset October to March, heatwaves may
occur, with the wind blowing from
the desert, which can raise the
temperature above 35 °C (95 °F),
South-west Moonsoon though for short periods
(sometimes, only one day); in
addition, the wind can bring sand
and dust from the desert.
CONSTRUCTION AND
z
MATERIAL USED
The Sydney Opera House started in 1959.
It was built on Bennelong Point adjacent to Jon
Bradfiled's Sydney Harbour Bridge where it would
be visible from all sides.
At the centre of Utzon’s distinctive design was a
set of interlocking vaulted shells that became one
of the most challenging engineering projects ever
attempted. Each of the shells is made of pre-cast
concrete rib segments rising to a ridge beam, held
together by 350 km of tensioned steel cable.
Geometrically, each half of each shell is a segment
of a sphere; however, the 'sails' were originally
designed as parabolas, for which an engineering Although described as reinforced-
solution could not be found. concrete shells, they are in fact a series of
concrete ribs that support a total of 2,194
precast-concrete roof panels which are in turn
clad with over 1 million tiles. The tile surface
is highly detailed and uses two types of tile -
one glossy white, one matte cream - with
clearly expressed joints.
z
In submitting the winning design, the architect, Jørn
Utzon, conceived the scheme of the roof without any
engineering consultation or advice. When head engineer Ove
Arup and his team began their preliminary design of the roof,
they quickly realised that the thin shell Utzon had envisaged
would not be possible. This was because the shape of the roof
introduced large bending moments, regardless of any
conceivable structural system.
While the base of the building was constructed, Arup
and his team spent six years working with Utzon, refining the
design of the roof to arrive at a solution that was
architecturally pleasing, structurally sufficient and relatively
cost effective. Arup canvassed at least 12 iterations for the While the base of the building was
geometry of the shells, ranging from parabolas to arcs to constructed, Arup and his team spent six years
ellipsoids. The final solution involved forming each shell working with Utzon, refining the design of the roof
with segmented post-tensioned, precast concrete ribs, all to arrive at a solution that was architecturally
having their external surfaces described by the same sphere. pleasing, structurally sufficient and relatively cost
By fabricating similar elements forming part of a spherical effective. Arup canvassed at least 12 iterations for
geometry, it was possible to maximise the use of repetitive the geometry of the shells, ranging from parabolas
elements in the construction of the shells. to arcs to ellipsoids. The final solution involved
forming each shell with segmented post-tensioned,
precast concrete ribs, all having their external
surfaces described by the same sphere. By
fabricating similar elements forming part of a
spherical geometry, it was possible to maximise the
use of repetitive elements in the construction of the
shells.
DESIGN
STRATEGIES
z CONCLUSION
The Opera House's Although the Sydney Opera House is a
architect, Jørn Utzon, masterpiece worth reckoning, there were
incorporated sustainable design numerous risks and problems that were associated
elements such as a seawater- to it. For starters, the building even began being
cooling system into the building constructed before its design was fully complete
which opened in 1973. The and this brought about the risk of confusion and
Environmental Sustainability possible bringing down to rectify the plan.
Plan 2020-2023 builds on that
legacy. The alteration of the design added to extra
The Opera House has been
awarded a 5 star Green Star performance expenses being spent and additional time required
rating from the Green Building Council a thing that could have been avoided if proper
of Australia (GBCA), becoming one of designing had been done initially. Though the
the first World Heritage-listed buildings original architect of the design left way before the
globally to achieve the certification. A completion of the building together with his
number of successes including the Opera drawings, the completion of the project was
House’s recent Carbon Neutral finished and opened as a performing art centre.
certification, implementation of a new
waste management program, efficiencies
in water use and a more than 9%
reduction in energy use have enabled the
Opera
After first announcing the project Houseatoseries
in 2017, achieve the certification.
of modular artificial
reefs have now been installed alongside the Opera House sea wall. The
pioneering project, led by UTS Professor of Marine Ecology David Booth and
funded through a NSW Government Environmental Trust Restoration &
Rehabilitation grant, aims to explore new ways to increase marine biodiversity
and support native species in Sydney Harbour.
REFERENCE :
Sydney Opera House - 2209 Words | Essay Example. (2020, January 22). Free
Essays. https://ivypanda.com/essays/sydney-opera-house/
Sydney Opera House. Sydney Opera House | Climate Active. (n.d.). Retrieved
December 9, 2021, from https://www.climateactive.org.au/be-climate-active/climate-
active-stories/sydney-opera-house.
Sydney Opera house- inspired by nature. (n.d.). Retrieved December 9, 2021, from
https://technologystudent.com/prddes_2/nature1.html.