Trabajo Grupal 01 PPS - 2009 - 2
Trabajo Grupal 01 PPS - 2009 - 2
Mantenimiento 2009-II
Integrantes:
Ing. Carlos Tasaico
VACIO DE AMONIADO DE LA LINEA DEL COMPRESOR 1 0.00 7.83 0.00 7.83 0.00
DESMONTAJE DEL COMPRESOR 2 7.83 12.83 7.83 12.83 0.00
DESMONTAJE DEL MOTOR 3 7.83 9.33 9.18 10.68 1.35
DESARME DEL MOTOR 4 9.33 11.83 10.68 13.18 1.35
BARNIZADO,ESTUFADO DEL MOTOR 5 11.83 35.83 13.18 37.18 1.35
DESARME DEL COMPRESOR TOTAL 6 12.83 19.83 12.83 19.83 0.00
CAMBIO DEL COJINETE PRINCIPAL
7
CAMBIO DEL COJINETE LATERAL 19.83 24.03 27.31 31.51 7.48
CAMBIO DEL PISTON DE BALANCE
CAMBIO DEL RODAMIENTO DE EMPUJE 8
CAMBIO DE CAMISA DE PISTON DE BALANCE 19.83 25.13 27.05 32.35 7.22
CAMBIO DEL SELLO DE ACEITE
CAMBIO DE RODAMIENTO CILINDRO CAM
9
CAMBIO DEL SELLO DEL PISTON DE DESCARGA
O-RING DE TEFLON CILINDRO CAM 19.83 24.83 32.26 37.26 12.43
CAMBIO JUEGO SELLO MECANICO N200VMD
CAMBIO O-RING N200VMD
CAMBIO FILTRO DESCARGA PAPEL EPC200 10
CAMBIO ELEMENTO COALESCENTE STD
CAMBIO FILTRO DESCARGA DE LA BOMBA 19.83 22.03 36.48 38.68 16.65
DESMONTAJE DE LA BOMBA 11 19.83 22.25 19.83 22.25 0.00
CAMBIO JUEGO DE BOCINAS PARA BOMBA M50P
CAMBIO JUEGO O-RING PARA BOMBA M50P 12
CAMBIO JUEGO DE EMPAQUES PARA BOMBA M50P 22.25 24.35 22.25 24.35 0.00
DESARME DEL MOTOR DE LA BOMBA 13 24.35 25.76 24.35 25.76 0.00
BARNIZADO,ESTUFADO DEL MOTOR 14 25.76 37.76 25.76 37.76 0.00
MONTAJAE DE BOMBA 15 37.76 40.76 37.76 40.76 0.00
MONTAJE DE SELLOS Y FILTROS 16 22.03 24.11 38.68 40.76 16.65
MONTAJE DE EMPAQUE 17 24.83 28.33 37.26 40.76 12.43
MONTAJE DE PISTON Y CAMISA 18 25.13 30.46 32.35 37.68 7.22
MONTAJE DE CIGÜEÑAL Y RODAMIENTO 19 24.03 30.20 31.51 37.68 7.48
BALANCEL DE COMPRESOR 20 30.46 32.63 37.68 39.85 7.22
MONTAJE DE PEIZAS FIJAS Y COMPRESOR 21 40.76 42.68 40.76 42.68 0.00
MONTAJE DE PEIZAS MOVILES Y COMPRESOR 22 32.63 35.46 39.85 42.68 7.22
ENSAMBLE MOTOR 23 35.83 44.50 37.18 45.85 1.35
ENSAMBLE COMPRESOR 24 42.68 45.85 42.68 45.85 0.00
ALINEAMIENTO GENERAL 25 45.85 48.01 45.85 48.01 0.00
REVISION DE PARAMETROS Y PUESTA EN MARCHA 26 48.01 51.01 48.01 51.01 0.00
PINTADO GENERAL DEL EQUIPO 27 51.01 62.35 51.01 62.35 0.00
Calculo de finalización de proyecto:
proyecto
La ruta critica de acuerdo a nuestro diagrama de red es como
sigue a continuación: