Professional Documents
Culture Documents
Hydraulicstructure Seepage
Hydraulicstructure Seepage
Chapter: Theories of
Seepage Flow/Subsurface
Flow
Introduction
Soil – A system
Soil – A system
In order that the floor to be safe against this uplift, its weight
must be at least equal to the uplift. If the specific gravity of
the material of the floor is G and its thickness t, the weight
per unit area will be γGt. This then yields for safety against
uplift
2.3 Undermining
Undermining starts if the seepage water emerging at the exit
retains enough force to dislodge sediment particles at that
location.
This then continues upstream and creates a cavity below the
structure which can result in the collapse of the structure.
See Fig.5.
Soil – A system
to provide safety against piping failure, the seepage force at the exit end
must be less than the submerged weight of the soil particles.
At the critical condition, the two forces will just balance each other.
Soil – A system
Soil – A system
Soil – A system
Soil – A system
Soil – A system
Soil – A system
Soil – A system
Soil – A system
Soil – A system
If the side of the last square at the exit is le, the exit hydraulic
gradient is:
Soil – A system
Soil – A system
Soil – A system
Soil – A system
Soil – A system
Uplift Pressure
The uplift pressure at any point P at a distance l from point A can
be determined from the relation
Where u is the uplift pressure in KN/m2, w is the specific weight of
water in KN/m3 and h is the residual head in m at that point. It may
be noted that the head his measured above the top surface of the
floor.
The residual head h at the point P can be determined by
either of the following methods.
Soil – A system
Design Criteria
For safety of hydraulic structure on pervious foundation, the
following two criteria should be satisfied.
The subsoil hydraulic gradient should be less than the
permissible value to prevent piping failure.
The floor should be sufficiently thick to prevent rupture due
to uplift pressure.
Piping failure
Soil – A system
Soil – A system
Soil – A system
Soil – A system
Soil – A system
Soil – A system
Upstream floor:
It may be mentioned that the floor thickness determined by
the above equation is applicable only for the portion of floor
on the downstream of the barrier.
On the upstream of the barrier, there is weight of water on
the floor which exerts a downward force equal to wH, which
is more than to counterbalance the upward force, U due to
uplift.
Theoretically, the thickness of U/S floor required is zero, but
as this is not feasible some nominal thickness is provided so
that the floor can act as an impervious floor
Soil – A system
and can resist wear, impact etc. The nominal thickness for
different hydraulic structures is different.
For the U/S floor of diversion weirs a thickness of 0.5 to
0.8m may be provided.
It is important and economical to provide as much length of
the creep length as possible on the u/s of the barrier.
Moreover, the provision of a greater length on the u/s side
also reduces the uplift pressure on the d/s floor because of a
large loss of head would occur up to the barrier and the
residual head and hence the thickness on the d/s floor would
be reduced (See Fig 15 a).
Soil – A system
Soil – A system
Soil – A system
Soil – A system
Soil – A system
i. The outer faces of end sheet piles were much more effective
than the inner faces and the horizontal length of the floor.
ii. Intermediated piles of smaller length than the outer piles are
ineffective except for some local redistribution of pressure.
iii. Undermining/piping of floor started from tail end when the
hydraulic gradient at the exit is greater than the critical gradient
for that particular soil. The soil particles move with the flow of
water, thus causing progressive degradation of the subsoil and
resulting in cavities below the floor and ultimate failure.
iv. It is absolutely essential to have a reasonably deep vertical cut
off/pile at the downstream end of the floor to prevent
undermining/or piping.
Soil – A system
Soil – A system
Soil – A system
Soil – A system
Soil – A system
Soil – A system
Soil – A system
Soil – A system
Soil – A system
Soil – A system
Soil – A system
Soil – A system
Soil – A system
Soil – A system
Soil – A system
Soil – A system
Soil – A system
Soil – A system
Soil – A system
Soil – A system
Soil – A system
Soil – A system
Soil – A system
Soil – A system
Soil – A system
Soil – A system
Soil – A system
Soil – A system
Cont…