Professional Documents
Culture Documents
Procurement Presentation 092022
Procurement Presentation 092022
Technical
Budget Office
Working Group
WHAT IS PROCUREMENT PLANNING?
Process in determining the following:
Advance Deliveries
Suki System
Unwarranted resort to alternative methods of procurement
Fit for purpose
It must be done within
Value for money budgetary context.
PROCUREMENT PLANNING AND BUDGET
LINKAGE
Section 7.1 of IRR
All procurement shall be within the approved budget of the
Procuring Entity (PE) and should be meticulously and
judiciously planned by the PE.
Each end-user unit shall prepare the PPMP during the budget preparation to support the cost estimates
in the budget proposal.
The end-user or implementing units shall be responsible for the preparation of all documents
necessary for the procurement activity, including but shall not be limited to, the technical specifications,
scope of work, or terms of reference.
PREPARATION OF PPMP –
TIPS AND BEST PRACTICES
PREPARATION OF PPMP
Procurement Milestones
The PPMP, like any plan, is not complete without including therein
the schedule of significant activities.
PPMP NON-CSE SAMPLE FORMAT
PPMP CSE SAMPLE FORMAT
PPMP CSE SAMPLE FORMAT
EARLY PROCUREMENT
ACTIVITIES
EARLY PROCUREMENT ACTIVITIES
GPPB Resolution No. 14-2019
What is “EPA”?
What is “EPA”?
Effectively
managed
procurement
projects
FRAMEWORK
AGREEMENT
FRAMEWORK AGREEMENT
GPPB Resolution No. 12-2017 dated 10 April 2017
Definition
General Conditions
General Conditions
Valid only for the period stated in the Bidding Documents which, in no
case, shall exceed three (3) years from the time the Framework
Agreement is executed
FRAMEWORK AGREEMENT
GPPB Resolution No. 12-2017 dated 10 April 2017
General Conditions
Call-Offs
Repeat Order
However, a mere act of dividing a contract into smaller quantities or phases does
not automatically constitute splitting of contract.
Direct Contracting
Repeat Order
Shopping
Negotiated Procurement
Direct
Contracting
Conditions Threshold
Shopping B Latest Update:
Shopping B
[Section 52.1(b)] [Section 52.1(b)]
Procurement of
ordinary or regular CSE Items not available in
office supplies and DBM-PS may be procured
equipment not PhP1,000,000.00 from other sources without the
available in PS-DBM; need of securing of Certificate
and For NGA’s, GOCCs, of Non-Availability of Stocks
GFIs, SUCs & (CNAS), subject to conditions
Amount does not Autonomous Regional set forth in GPPB-Resolution
exceed the threshold Government No. 17-2020
Shopping
Procedures
Shopping B
[Section 52.1(b)]
Applicability Conditions
In case of imminent danger to life or property
during a state of calamity
Goods
Reminders:
PE should consider appropriate timing or the proximity of the time
between the actual procurement activity to be conducted and the
emergency sought to be addressed.
When the reason or cause for the emergency has already been abated,
adoption of competitive bidding shall be considered.
Procedural Guidelines
The End-user
The End-user shall secure a The HoPE shall
shall justify to certificate from The BAC shall enter into a MOA
the BAC the the relevant issue a with the
report to A-to-A officer of the Resolution Servicing
is more efficient Servicing Recommending Agency upon
and economical Agency that the the use of A-to- approval of the
to the latter complies A to the HoPE BAC
government with the recommendation
conditions
Small Value
Negotiated Procurement Procurement
Conditions
Background
The End-user shall submit a justification based on a cost- There is no threshold for
the use of this modality
benefit analysis and/or market study indicating that so long as it covers lease
Procurement covering leasing privately owned real property or venue is more of privately-owned real
lease of property or efficient and economical to the government property or venue.
venue for official use
The ABC shall be set using the mid- point
of the range obtained from the results of the
market analysis on the prevailing lease
rates.
Applicability
Rental rates should also be within the
prevailing market rates
Goods
Technical Specifications shall be prepared taking into
considerations the Rating Factors under Appendix B
Lease of Real Property &
Negotiated Procurement Venue
BAC shall invite at least It is preferred that government Prior to the extension of the lease of
three (3) prospective agencies lease publicly owned real contract, the end-user must conduct a
lessors/venues within the property or venue from other cost-benefit analysis to assess the
vicinity of the selected government agencies quality of service under the lease of
location to submit sealed contract
price quotations for real
property and open
quotations for venue
If there is an available publicly
If the result of the CB continue to
owned real property or venue that
result to favor the existing lessor, then
complies with the requirements of
the PE may simply renew its lease
the procuring entity it may enter
contract. If it does not, then the PE
Receipt of one (1) price into a contract of lease with the
should procure a new lease of
quotation is sufficient to government agency owner
contract
proceed with the evaluation
IMPORTANT TIMELINES
Particulars Date of Submission Where to Submit
Indicative Annual Procurement Plan for Non- September 30, 2022 Posted in the Agency’s
CSE based on NEP Transparency Seal Webpage
Annual Procurement Plan - Commonly Used September 30, 2022 Submission through PhilGEPS
Supplies and Equipment (APP-CSE) Virtual Store; Manual Submission
will not be accepted
Maintain/update PhilGEPS posting of all Updated on or before Updated in the PhilGEPS Website
Invitation to Bids and awarded Contracts from January 31, 2023
January 01 to December 31, 2022, including
EPA of FY 2022 Non-CSE items
(https://open/philgeps.gov.ph/pbb)
Conduct of Early Procurement Activities (50% December 31, 2022 GPP-Technical Support Office
of the Indicative APP) (actual conduct);
Submission of
Certification (one
month from approval
of the GAA or January
31 of the following
year)