Professional Documents
Culture Documents
Session 13 PERT
Session 13 PERT
Recap- Session - 12
• Resource loading
• Resource levelling
• Time-constraint projects
• Resource-constraint projects
• Ways of levelling
• Use slacks
• Alter the network relationships
• Split the task
• Change the scope
• Assign more efficient resources
The PERT Technique
(Program Evaluation & Review
Technique)
PERT:
Program
Evaluation
and Review
Technique
Example: assume a = 3, m = 6, b = 15
Then = 2
PERT Technique (Cont’d)
These formulas are based on assumption that
each activity duration conforms to Beta
distribution (not Normal distribution)
Beta Distribution:
Not necessarily symmetrical
Definite cut-off points
A single peak
a m b
Consider the following project information and answer the
following,
Activity a m b
1-2 17 29 47
2-3 6 12 24
2-4 16 19 28
3-5 13 16 19
4-5 2 5 14
5-6 2 5 8
Activity a m b te Ve
1-2 17 29 47 30 25
2-3 6 12 24 13 9
2-4 16 19 28 20 4
3-5 13 16 19 16 1
4-5 2 5 14 6 4
5-6 2 5 8 5 1
Summary: The Role of PERT
PERT does not reduce project duration
However, it does the following:
1. Given a network with estimates a, m, and b as well as a
value for project duration, it provides a probability figure
for finishing on time
2. Alternatively, given a network with estimates a, m, and b
as well as a desired level of confidence (probability figure,
say 99%), it can calculate a project duration that
corresponds with the level of confidence
3. It provides insight in the effect of variability of activity
duration on the critical path
PERT only considers the critical path
There are often “near critical” paths
The optimistic (a), most likely (m), and pessimistic (b) time estimates, are
shown in following Table.
2. The project has begun on August 1. What is the probability that this project
can be completed by October 7?
DAYS
ACTIVITY a m b
AB 5 6 7
BC 3 6 9
CD 6 8 10
CE 5 6 7
DF 3 5 7
FG 4 6 10
FH 5 6 7
FI 4 5 8
FJ 6 8 10
JK 11 12 13
KL 5 7 9
KM 8 9 10
MN 5 6 11
LO 6 8 10
OP 6 7 8
PQ 3 4 5