You are on page 1of 11

Commissioning procedures

Phase A.1

20th LHCCWG
February 14th 2007

M. Gruwé
and
R. Alemany, V. Kain, L. Ponce, S. Redaelli, W. Venturini
Layout
• General comments (valid for all phases)
– Purpose of the procedures
– What are they based on?
– Input required from LHCCWG
• Phase A.1
– Some comments
– Web page describing procedures
– Remaining questions

February 14th 2007 20th LHCCWG 2


General comments
• Trial of presentation in LHCCWG:
– One phase presented per meeting (or every 2nd meeting)
– Will go through
• layout of the procedures web pages
• main steps of the procedure
• remaining questions
– But: will not go into details (too long to go through in such a wide
group)

• Work in progress
(and will remain so till actual commissioning...)

February 14th 2007 20th LHCCWG 3


Purpose
• Our understanding of the purpose of these procedures:
– Make sure everything required for the various beam
commissioning phases is available/ready/thought of
(applications, instrumentation, equipment, etc...)
– Make sure responsible people are informed of the requirements
– Point out possible problems, missing functionalities,
misunderstandings, etc...
– Ordered list of tasks to perform and results to achieve

• Not meant to be a complete “how to do” manual of each


step or measurement for anyone to use:
Experts will obviously be there and perform specific tasks

February 14th 2007 20th LHCCWG 4


Based on...
• The procedures are based on
– Presentations in the LHCCWG
– Some Chamonix presentations
– Mike’s web pages
http://lhc-commissioning.web.cern.ch/lhc-commissioning
– Discussions with experts, individuals
– Our current understanding...

February 14th 2007 20th LHCCWG 5


Input required
• Please read and check the proposed
procedures:
– Entry conditions
– Procedures
– Exit conditions
– Listed problems
– Remaining questions
• Give feedback

February 14th 2007 20th LHCCWG 6


Questions to LHCCWG
• Procedures:
– Do they make sense?
– Is there anything missing?
• Entry conditions (= prerequisites):
– Do we have all the tools/equipment necessary for each step of
the procedures?
• Exit conditions (=outcome):
– Do we reach these by following the procedures?
– Do we want to achieve more than these exit conditions?
• Questions:
– Remaining questions need to be discussed and solutions found
– Other points to be sorted out?

February 14th 2007 20th LHCCWG 7


Phase A.1: reminder
• First turn
• 450 GeV
• Pilot intensity
• Goal:
– Commissioning of the injections
– Threading around the ring
– Commissioning of beam instrumentation.
– Ring 1 and ring 2.

February 14th 2007 20th LHCCWG 8


Web page
• The procedures for phase A.1 can be found in:
http://lhccwg.web.cern.ch/lhccwg/Procedures/stageA/phaseA1/index.htm

• Comments:
– As one of the entry conditions: link to LHC machine checkout
web page (Mike’s web page)
– To be added: a table listing all steps of the procedures versus all
required applications and instrumentation
– Procedures for phase A.1 should/will be discussed in the
Injection working group (Brennan)
– No time estimate included at this stage. Should be added later to
facilitate the beam commissioning planning.

February 14th 2007 20th LHCCWG 9


Remaining questions (I)
• Recycling required ever? If energy mismatch detected and MBs
adjusted, recycling? If yes, how often?

• Will we have an additional event indexed database like SDA?

• Which magnets have to be fully commissioned for this stage?

• When shall we check interleaved ring 1/ring 2 injections? Already in


this phase?

• Display of the spare channels of BLM cards should be available in


the CCC (this is currently not foreseen: we need a soft to see all
spare channels in the CCC)...NEEDED FOR MOBILE BLMs

February 14th 2007 20th LHCCWG 10


Remaining questions (II)
• Probably difficult to quench a magnet at this stage...but: are BLM
thresholds remotely changeable or not??

• While threading: coarse calibration of the BPMs. How often do we


send someone to fix problems? Do we continue if one BPM is
missing? How many faulty BPMs do we allow?

• Which LHC mode are we in? BTVs should all be IN, but they can
only be IN if in the "inject and dump mode". How do we do the
transition from "First turn" to "Circulating beam" (for the BTVs'
functioning)?

February 14th 2007 20th LHCCWG 11