Professional Documents
Culture Documents
Project Cost Management - V3
Project Cost Management - V3
MANAGEMENT
1
“every project boils down to money “
DEFINITIONS
Cost
The value of money that has been used up to produce something
B ) Fixed Costs
C ) Direct Costs
D ) Sunk Costs
3
DEFINITIONS
Opportunity Cost
Opportunity cost
The other project that you will not to do
Project A Project B
Selected Project
Depreciation
Loses of project value over project time
Sunk Cost
A cost that has already been incurred and thus cannot be recovered .
4
DEPRECIATION METHODS
Loses of project value over project time
B ) Depreciation
D ) Lifecycle Costing
6
PROJECT COST
MANAGEMENT
Project cost management includes the processes involved in estimating, budgeting, and
controlling costs so that the project can be completed within the Approved Budget .
10
7.1 Plan Cost (Inputs)
Scope Baseline
Components of the scope; baseline include :
Project scope statement , WBS , WBS Dictionary
Project Schedule
The type and quantity of resources and the
amount of time which those resources are applied to
complete the work of the project are major factors in
determining the project cost.
Project Charter
The project charter is used to provide the high-
level project requirements and high-level product
description of the project. 11
7.1 Plan Costs (Inputs)
12
7.1 Plan Cost (Tools & Techniques)
• Expert judgment guided by historical information, provides
valuable insight about the environment and information from prior
similar projects. Expert judgment can also suggest whether to
combine methods and how to reconcile differences between them.
• Analytical Techniques
Choosing strategic options to fund the project such as: self-
funding, funding with equity, or funding with debt. The cost
management plan may also detail ways to finance project
resources such as making, purchasing, renting, or leasing. These
decisions, like other financial decisions affecting the project, may
affect project schedule and/or risks.
• Meetings
Project teams hold planning meetings to develop the cost
management plan.
The planning effort of the processes of the Cost Management Plan is a part of the
develop project management plan
( Cost management plan can establish the following )
}
Cost Estimating Cost Estimating
Cost Budgeting
Cost Budgeting
Single Process
( Short Period – Single Person ) Two separate Process
16
17
7.2 ESTIMATE
COSTS
Cost Accuracy
Project Progress
19
7.2 Estimate Costs (Inputs)
Scope Baseline
Components of the scope; baseline include :
Project scope statement , WBS , WBS Dictionary
Project Schedule
The type and quantity of resources and the
amount of time which those resources are applied to
complete the work of the project are major factors in
determining the project cost.
• Basis of Estimates
The amount and type of additional details
supporting the cost estimates vary by application
area
- How it was developed ( Cost Estimation )
- Assumptions / Constrains
- Range of possible estimates
- Inclusions / Exclusions.
Inputs
Inputs Tools
Tools&&Techniques
Techniques Outputs
Outputs
•• Enterprise
Enterprise •• Analogous •• Activity
ActivityCost
Cost
Environmental Analogousestimating
estimating
EnvironmentalFactors
Factors •• Expert
Expertjudgment
judgment
estimates
estimates
•• Organizational
OrganizationalProcess
Process •• Bottom-up •• Basis
Basisofofestimates
estimates
Assets Bottom-upestimating
estimating •• Project
Assets •• Parametric
Parametricestimating
estimating Projectdocument
document
•• Scope
Scopebaseline
baseline •• Project updates
updates
•• Project ProjectManagement
Management
Projectschedule
schedule Software
Software
•• Human
Humanresource
resourceplan
plan •• Vendor
•• Risk VendorBidBidAnalysis
Analysis
Riskregister.
register. •• Reserve
ReserveAnalysis
Analysis
•• Cost
CostofofQuality
Quality
•• Three-point
Three-pointestimate
estimate
25
7.2 Estimate Costs
26
7.3 Determine Budget
• Determine Budget is the process of Aggregating the estimated
costs of individual activities or work packages to establish an
authorized cost baseline.
27
7.3 Determine Budget
Activity Cost Estimates (Inputs)
7. Management reserves
6. Cost baseline
5. Contingency reserves
Budget At Completion
4. Project estimates
33
7.3 Determine Budget
Inputs
Inputs Tools
Tools&&Techniques
Techniques Outputs
Outputs
•• Activity •• Cost
CostAggregation
Aggregation •• Cost
Costperformance
performance
Activitycost
cost •• Reserve
estimates
estimates ReserveAnalysis
Analysis baseline
baseline
•• Basis •• Historical
Historicalrelationships
relationships •• Project
ProjectFunding
Funding
Basisofofestimates
estimates •• Expert
•• Scope
Scopebaseline
baseline Expertjudgment
judgment Requirements
Requirements
•• Project •• Funding
FundingLimit
Limit •• Project
Projectdocument
document
Projectschedule
schedule Reconciliation updates
•• Resource
Resourcecalendars
calendars Reconciliation updates
•• Contracts
Contracts
•• Organizational
Organizational
process
processassets
assets
34
7.3 Determine Budget
35
36
7.4 CONTROL COSTS
Behind schedule
Ahead of schedule
Over budget
Cost Control ( Status )
Under budget
37
7.4 CONTROL COSTS
•Ensuring that cost expenditures do not exceed the authorized funding, by period
38
and in total for the project,
• Forecasting (Tools)
40
1. Earned Value Management Analysis
41
MANAGEMENT
Cost
EAC
Data date
BAC
Actual Cost AC
PV
Planned Value CV= EV - AC
SV= EV - PV
EV
Time
42
Earned Value Management Analysis
SV = ( EV – PV ) Negative Recoverable
• Cost Variance (CV)
is a measure of cost performance on a project. 43
CV = ( EV – AC ) Negative Often Non-Recoverable
Earned Value Management Analysis
• Schedule performance index (SPI)
Is a measure of progress achieved compared to progress planned on a the
project.
SPI = ( EV / PV )
44
WHICH OF THE FOLLOWING REPRESENTS THE VALUE OF
WORK WE HAVE ACTUALLY COMPLETED?
A ) Earned value
B ) Planned value
C ) Actual cost
D ) Estimate to complete
45
Earned Value Management Analysis
Example
We are about to produce 20 tables in 20 days cost is $20 for each.
Estimate At Completion (EAC) actual costs incurred for work completed, plus an
estimate to complete (ETC) the remaining work.
EAC = ( AC + ETC )
EAC = AC + ( BAC – EV )
= 90 + ( 400 – 60 ) = $430
EAC forecast for work performed at the Percent CPI
49
A PROJECT TEAM BUDGETED US $3000 FOR THE WORK
PERFORMED AND HAS SPENT US $4000 , TO DATE. IF
THEY BUDGETED US $5,000 FOR THE WORK
SCHEDULED , WHAT IS THE COST VARIANCE ( CV )?
A ) ($1,000)
B ) $2,000
C ) $ 1,000
D ) ($2000)
50
IF EARNED VALUE (EV) IS U.S.$300000, ACTUAL COST (AC) IS
U.S.$350000, AND PLANNED VALUE (PV) IS U.S. $375000, WHAT
DOES THE SCHEDULE PERFORMANCE INDEX (SPI)
INDICATE?
51
THE FORMULA, EAC = BAC/CPI, ASSUMES THAT :
52
EXERCISE
.
53
EXAMPLE - WALL CONSTRUCTION
Wall Construction
Time = 1 week per wall
Cost = $ 1,000 per wall, materials and labor
Total Schedule = 4 weeks
Total Cost = $ 4,000
54
5 pm Wednesday, Week 2
55
5 pm Wednesday, Week 2
56
5 pm Wednesday, Week 2
57
5 PM WEDNESDAY, WEEK 2
Earned Value
PV $1,800
EV $1,600
AC $2,250
Schedule Variance = EV - PV
= $1,600 - $1,800
= ($200)
Cost Variance = EV - AC
= $1,600 - $2,250
= ($650)
58
5 PM WEDNESDAY, WEEK 2
Performance Index
PV $1,800
EV $1,600
AC $2,250
SPI = EV / PV
= $1,600 / $1,800
= .9
CPI = EV / AC
= $1,600 / $2,250
= .7
59
10- IF AC IS GREATER THAN YOUR EV ,
WHAT DOES THIS MEAN?
61
7.3 Control Costs
Inputs
Inputs Tools
Tools&&Techniques
Techniques Outputs
Outputs
•• Project •• •• Work
WorkPerformance
Performance
Projectmanagement
management Earned
Earnedvalue
valuemanagement
management Measurements
plan
plan •• Performance
Performancemeasurement
measurement Measurements
•• Project •• Budget
Budgetforecasts
forecasts
ProjectFunding
Funding Analysis
Analysis •• Change
Requirements
Requirements •• Forecasting
Forecasting Changerequests
requests
•• Work •• •• Recommended
RecommendedCorrective
Corrective
WorkPerformance
Performance To-complete
To-completeperformance
performance action
Information
Information index
index(TCPI)
(TCPI) action
•• Organizational •• •• Organizational
OrganizationalProcess
Process
Organizational Performance
PerformanceReviews
Reviews
process •• Assets
Assets(Updates)
(Updates)
processassets
assets Project
ProjectManagement
Management •• Project
Software
Software Projectmanagement
managementplan
plan
•• Variance (Updates)
(Updates)
Varianceanalysis
analysis •• Project
Projectdocument
document(Updates)
(Updates)
62
7.4 Control Costs
63
HALF WAY THROUGH THE EXECUTING PROCESSES OF
YOUR PROJECT, A TEAM MEMBER ALERTS YOU TO A
POTENTIAL COST OVERRUN FOR A SPECIFIC
DELIVERABLE. WHAT DO YOU DO FIRST?
64
YOU ARE HAVING DIFFICULTY ESTIMATING THE COST OF
YOUR PROJECT. WHICH OF THE FOLLOWING BEST
DESCRIBES THE MOST PROBABLE CAUSE OF YOUR
DIFFICULTY?
66