Outline:
1. Introduction
2. Appropriateness of RFQ
3. Threshold and Quotations
4. Form of request
5. Opening, Evaluation/Comparisons
and award
6. Purpose of Using the Proper
Formats
2
Introductory Messages to Procurement staff
3
1. Introduction
• Simple and rapid procurement method
• One of the least competitive procurement methods
• May be abused unless it is carried out
– in compliance with the legal agreements, and
– observing a minimum of formality in the process,
and
– with appropriate record keeping for verification and
audit.
• The Bank has discovered cases of abuse that have
concluded in declaration of mis-procurement.
4
2. Appropriateness of RFQ
• To procure small amounts of off-the-shelf goods or
standard specification commodities for which more
competitive methods are not justified on the basis of
cost or efficiency.
• In emergency projects or for urgent relief-type
operations including re-establishment of vital services
like utilities, communications, shelter, and vital supplies
which stem from disasters or conflict.
• Because of the risk of abuse in procurement under
shopping, the use of this method is restricted to cases
when the justification for it is beyond contention.
5
RFQ Key characteristics
Characteristics
Some or all of the following characteristics apply:
Examples
low to medium value (Bank Guidance thresholds) furniture
requirements are simple and easy to specify, or off-the-shelf laptops, computers
standard product or service catering services
there is a ready market with many suppliers office maintenance
transport services
procurement decision is based on technically conforming lowest
Small industrial
quotation materials
Hand tools
Small works contract
SLIDE 6
Appropriate….
• Executing Agencies (EAs) may not use RFQ/shopping
only as an expedient to by-pass more competitive
methods or fraction of large procurements into smaller
ones solely to allow the use of shopping.
• When the nature of the specifications is complex or the
type of procurement requires an elaborate, detailed
evaluation system that needs substantial
documentation, a formal bidding process instead of
shopping is used. Shopping is not appropriate in these
cases, because it is a method that should not require
complex documentation or all the formalities of a
bidding process.
7
3. Thresholds and Quotation
• Threshold for shopping is less than $100,000****
• Compare at least three quotations to establish
reasonableness of price
• Comparison of two quotations is justified only when there is
evidence satisfactory to the Bank that there are only two
reliable sources of supply (national or foreign as the case
may be)
• To minimize the risk of getting only one or two quotations,
EAs are advised to initially request more than three
quotations.
• EAs may also at the time of the request, verify whether those
being invited will make an offer or not. 8
4. Form of Requests
• The EA exercises due diligence to satisfy itself that the firms
invited to quote are reputable, well established, and are
suppliers of the goods or services being purchased as part of
their normal business.
• Mandatory to use the RFQ form Prepared for the Project
• In case the EAs receives unsolicited quotations, these may be
accepted after carrying out a similar due diligence exercise to
verify the nature and reputation of the firms.
• The EA requests quotations by letter, fax, telex, electronic
messaging, etc., (with proof of receipt and record keeping).
• Local advertisement to get quotations from the local
suppliers/labour contracts is also acceptable as far as the
requirement of minimum three quotations are compared 9
Form of Requests …
• The request includes:
the description of items, total quantity, unit of measurement,
etc. of the goods/works/NCs,
Validity period of the quotation
Quotation submission, closing and opening date, place and
time.
Required information/documentation to award the contract.
Specification/BoQ and Drawing
Suppliers qualification
delivery time and place, completion of works
Evaluation and contract award process & criteria (item by item
or lot basis)
Quotation with or w/out TAX, Any qualification criteria,
10
etc.
Form of Requests …
11
CLARITY OF RFQ
• RFQ documents should clearly and precisely indicate ;
– The work to be carried out / the goods to be supplied,
– Minimum performance/conformance requirement
– the place of delivery / installation /the location of work
– the schedule for delivery / completion, performance
– warranty / maintenance requirements, any pertinent terms
and conditions.
• specify any criteria and the relevant requirement - in addition to
price - that will be taken into consideration in the evaluation
process.
• Qualification Criteria: technical, Financial, Past Similar
experience, Staffing, Equipment, etc.
• All bidders shall be provided the same information, and assured
of equal opportunities to obtain additional information on a
timely basis.
12
STANDARDS & BRAND NAMES
• Standards and technical specifications quoted in the
RFQ shall promote the broadest possible competition.
• As far as possible indicate internationally accepted
standards such as those issued by the international
standards organisation/national standards.
• In indicating specifications, reference to brand names,
catalogue numbers or similar classifications shall be
avoided.
• If it is necessary to quote a brand name to clarify an
otherwise unclear specification, the words “or
equivalent” shall be added.
13
5. Bid Opening, Evaluation/Comparison of Bids
Bid opening
• Opening shall be on the same date of bid submission;
• Date, time and place as announced in the RFQ;
• Quotations shall be opened in public;
• Bidders names, offered amounts, Currency of bid, any discount are read aloud,
• Any envelope containing Substitutions, Modifications, or Withdrawals must be read
out and recorded;
• the reading should be from the original version of each bid;
• Quotations received after the time stipulated will not be opened;
• No bid should be rejected at the bid opening except those received after the
deadline;
• All records of bid opening are reported as a Minute of bid opening.
• Use the form in the Opening Minute to record readout price
Eligibility
20
Principles of evaluation
• Confidentiality of the process until the successful bidder is
notified;
• Written clarification on ambiguities or inconsistency may be
requested;
• No meetings or conversation between the Procuring Entities and
bidders during the bid evaluation process;
• No changes in the bid price or substance are allowed
Most Advantageous Bid (MAB)
24
Thank you