You are on page 1of 8

DAILY PROGRESS CHECK BUILDING

10.11.2023
LOT 1 – GENERAL ASSEMBLY

n. Worker 00 ACTION PLAN


- Supplier must to be fixed
Due date 16/11/2023

General Progress 0%

12.00 am – 10/11/2023 ACTIVITIES DETAILS COMMENT

SPECIFIC MEETING FOR


LOGO + totem 
SUPPLIER
- Mezzanine Mezzanine 
- Doors/rollup doors + frame Doors + frame 

Status legend:  Done /  On going /  Deviation under control / Major issue

05.00 pm – 09/11/2023
LOT 2 – SITE ACCESS

n. Worker: 04 for external ACTION PLAN


lighting fixing - Green areas with another supplier

Due date 16/11/2023

General Progress 0%

12.00 am – 10/11/2023 ACTIVITIES DETAILS COMMENT

Perimetel access wall 

Gravel laying 

Road boarder installation 

BV global cold cover – metal sheet cover 


fencing closure

(north+south+ stellantis BV)
pavè for pedestrian in access zone 

water evacuation channel (cleaning + closure) 

safety barrier + turnstile 

05.00 pm – 09/11/2023
Status legend:  Done /  On going /  Deviation under control / Major issue
LOT 3 – ACCESS SECURITY BUILDING

n. Worker 00 ACTION PLAN

Due date 16/11/2023

General Progress 0%

12:00 am – 10/11/2023 ACTIVITIES DETAILS COMMENT

facade 

Frame + windows + doors 

Status legend:  Done /  On going /  Deviation under control / Major issue

05.00 pm – 09/11/2023
LOT 4 – ADMINISTRATIVE BUILDING

n. Worker 10 ACTION PLAN

Due date 16/11/2023

General Progress 0%

ACTIVITIES DETAILS COMMENT

12.00 am – 10/11/2023 Floor 0 

Floor 1 (23/11/23) 

Stairs 

Ceiling 

Doors 

Windows 

Painting wall 

Pipe installation 

Toilet 
05.00 pm – 09/11/2023 Air conditioning system 

Electric installation (cable, cable tray) 

Fire detection 

Facade (tiles + cleaning) 

Status legend:  Done /  On going /  Deviation under control / Major issue


LOT 5 – NORTH SIDE ACTIVITIES

n. Worker 06 ACTION PLAN

Due date 16/11/2023

General Progress 0%

12.00 am – 10/11/2023 ACTIVITIES DETAILS COMMENT


WC women : concrete slab +

foundation
WC women: underground pipe

installation
WC women : cover the area 

WC men : concrete slab + foundation 


WC men : underground pipe

installation
WC men : structure 

WC men : mansonary works 


05.00 pm – 09/11/2023 WC men : estetique works

(doors, painting)
Asphalt + quality park 

Perimetel wall 

Status legend:  Done /  On going /  Deviation under control / Major issue


LOT 6 – WEST SIDE ACTIVITIES

n. Worker 00 ACTION PLAN

Due date 16/11/2023

General Progress 0%

12.00 am – 10/11/2023 ACTIVITIES DETAILS COMMENT

OR43 small guardian building 

Perimetel access wall + fencing 

GA west side second skin installation 

Rooftop finalizing activities (HVAC) 

Gravel laying 

Status legend:  Done /  On going /  Deviation under control / Major issue

05.00 pm – 09/11/2023
LOT 6 – EAST SIDE ACTIVITIES

n. Worker 04 ACTION PLAN

Due date 16/11/2023

General Progress 0%

10.00 am – 10/11/2023 ACTIVITIES DETAILS COMMENT

Logistic building second skin install. 

Road C 

Pedestrian way 

Second paint coating locker room 

Gravel laying 

Status legend:  Done /  On going /  Deviation under control / Major issue

04.00 pm – 09/11/2023