MQCHD Test Question
MQCHD Test Question
2. A one-lane road, with of 3.5 meters and shoulder width of 0.5 meter on
each side of the pavement was designed to have sub-base and base
coarse with a combined thickness of 300mm. If the thickness of the
sub-base is 125mm, the spreading and compaction of the sub-base and
base coarse shall be carried out in
a. 3 layers over the full width of 4.5 m
b. 2 layers over the full width of 4.5 m
c. 3 layers over the full width of 3.5 m
d. 2 layers over the full width of 3.5 m
9. The number of sets of beam test specimens that should be taken from
700 sq.m. of concrete pavements, 0.23 cm thick poured on a single day should be:
a. 2
b. 3
c. 6
d. 9
10. Three cores taken from a pavement section poured on a single day were tested to
have strength as follows:
Core
1 3650
2 3000 86% of 3500 psi
3 2450 70% of 3500 psi
Average 3033 87% of 3500 psi
If the required strength is 3500 psi concrete are represented by the cores
a. Maybe accepted, subject to price adjustment
b. Is considered adequate
c. Is considered inadequate
d. May be recored at the initiative of the implementing office
11. Forms for concrete pavement shall remain in place undisturbed for not less than
13. How many measurements are needed for thickness determination of concrete
cores?
a. 4
b. 6
c. 8
d. 9
15. What is the single factor that determines the strength of concrete?
a. Slump
b. Water-cement ratio
c. Cement factor
d. Gradation of aggregates
16. What is the curve formed on a maximum dry density and optimum moisture
content graph?
a. Parabola
b. Hyperbola
c. Straight line
d. None of the above
17. Which of the following is accepted for concrete with fc at 28 days of 3500 psi?
a. 3275 psi; 3020 psi; 2630 psi
b. 2640 psi; 3010 psi; 3030 psi
c. 3030 psi; 2790 psi; 2599 psi
d. 3300 psi; 3330 psi; 2620 psi
20. The most commonly used method in the design and evaluation of bituminous
concrete mixes
a. Design mix
b. Marshall stability
c. Index of retained strength
d. Immersion / compression test
21. Which of the following penetration grade of asphalt is used in cold climate?
a. 120/50
b. 85/100
c. 60/70
d. 40/50
22. If sea water is used in a concrete mix, shat will be the effect on the hardened
concrete pavement?
a. Strength is affected
b. Scaling at surface
c. Cracks at the side
d. Steel bars will rust
23. The job mix formula contain the following provision except
a. Grading of aggregate
b. Temperature of aggregates and asphalt
c. Index of retained strength value
d. Type of asphalt and percentage
29. The dividing size between coarse and fine aggregates used in asphalting is
a. no. 4
b. No. 8
c. No. 16
d. No. 30
33. The variation on tolerance of the surface from the testing edge of the straight edge
in contact with the surface of asphalt pavement is
a. +/- 2mm
b. +/- 4mm
c. +/- 6 mm
d. – 5 mm
34. The specific irregularity tolerance for item 201 is
a. 5 mm
b. 10 mm
c. 15 mm
d. 20 mm
42. Item 310 mixture shall have an index of retained strength of not less than
a. 66
b. 70
c. 97
d. 107
43. Final compaction and smoothing of item 310 should be done by a
a. pneumatic – tired roller
b. Sheep foot roller
c. Vibratory roller
d. Tandem smooth wheel roller
44. Item 310 mixture shall be delivered to the paver at a temperature not less than
a. 66 ºC
b. 97 ºC
c. 107 ºC
d. 110 ºC
45. In the asphalting of a two lane, 500 meter road which lasted for three days, how
many core samples should be taken from the pavement if no sample was taken at
the end of each days operation?
a. 3
b. 5
c. 6
d. 10
46. Which of the following provisions is not included in the job – mix formula?
a. Mixing time
b. Grading of aggregates
c. Asphalt cement
d. Temperature at delivery
50. After final rolling, the compacted asphalt pavement shall have a density equal
top, or greater than % of the laboratory compacted density.
a. 90
b. 95
c. 97
d. 98
51.Scales for weighing aggregates and cement shall be accurate within % throughout
the range of use. Scales shall be inspected and sealed as often as the Engineer may
deem necessary to assure their continued accuracy,
a. 1.0%
b. 1.5%
c. 0.5%
d. 2.0%
52. When cement is placed in contact with the aggregate, batches maybe rejected
unless mixed within ____ hours of such contact.
a. 1.5 hours
b. 2.0 hours
c. 0.5 hours
d. 2.0 hours
53. When mixed at the site or in a central mixing plant, the mixing time not be less
than ____ nor more than ____unless mixer performance test prove adequate mixing
of concrete in a shorter time period.
a. 30 seconds nor more than 90 seconds
b. 50 seconds nor more than 90 seconds
c. 60 seconds nor more than 120 seconds
d. 90 seconds nor more than 120 seconds
54. The flow of water shall be uniform and all water should be in the drum by the end
of the first ____seconds of the mixing period.
a. 45 seconds
b. 30 seconds
c. 15 seconds
d. 20 seconds
55. Concrete not place within ____minutes from the time the ingredients were charged
into the mixing drum shall not be used.
a. 120 minutes
b. 150 minutes
c. 60 minutes
d. 90 minutes
56. When concrete is delivered in truck mixers, additional water maybe added to the
batch and additional mixing performed to increase the slump to meet the specified
requirement if permitted by the Engineer, provided all these operation are
performed within ____after the initial mixing operation and water and cement ratio
is not exceeded.
a. 30 minutes
b. 15 minutes
c. 45 minutes
d. 60 minutes
57. A sample from a bituminous mix weighs 1000 grams. At extraction, it was found
out that the dry aggregate weighed 950 grams, What is the % of asphalt by weight
of mix?
a. 5.2%
b. 5.0%
c. 5.4%
d. 4.8%
58. The minimum penetration of the preservative with the surface of the timber piles
shall be ____.
a. 150 mm
b. 20 mm
c. 250 mm
d. 10 mm
59. The contractor shall submit in writing a job-mix formula for the mixture supported
by the laboratory test data along with samples of resources of components and
viscosity-temperature relationship to the Engineer for testing and approval at least
____.
a. two weeks
b. three weeks
c. one week
d. four weeks
60. The concrete samples should be stored in a moist conditioned temperature within
the range of ____until the time of test.
a. 18*C to 24*C
b. 15*C to 18*C
c. 14*C to 24*C
d. 18*C to 28*C
61. This is used in soil stabilized road surface due to its high____ property, tha is, it
absorb and retain water.
a. Potassium Chloride
b. Calcium Chloride
c. Magnesium Chloride
d. Sodium Chloride
62. The mass % wear of soil aggregate used in cement/lime proportions should not be
more than ____.
a. 40%
b. 50%
c. 45%
d. 55%
63. The uniform rate at which the movable head of CBR machine tray is ____.
a. 0.07 in/min
b. 0.10 in/min
c. 0.08 in/min
d. 0.09 in/min
64. Cast in place concrete shall not be post-tensioned until at least ____ and until the
compressive strength has reached the strength specified
a. 7 days
b. 10 days
c. 14 days
d. 20 days
66. Specification requires one (1) Quality test for every ___of asphalt.
a. 20 tons
b. 200 tons
c. 50 tons
d. 40 tons
67. The ___is the most commonly used method in the design and evaluation of
bituminous concrete mixes.
a. Job Mix Formula
b. Design Mix
c. Marshall Stability
d. Extraction
68. Vibration shall operate a frequency of 8,300 to 9,600 impulses per minute under
load at a maximum spacing of ___cm.
a. 30 cm
b. 50 cm
c. 60 cm
d. 40 cm
69. The specific gravity of Sodium Sulfate used in soundness test for aggregate should
be within the range of ___.
a. 1.151 to 1.174
b. 1.250 to 1.178
c. 1.051 to 1.154
d. 1.058 to 1.184
70. The specific gravity magnesium sulfate solution used in soundness test for
aggregate should be within the range of ___.
a. 1.280 to 1.408
b. 1.180 to 1.308
c. 1.295 to 1.308
d. 1.195 to 1.318
71. Aggregate accounts for 92-95% of the weight of the bituminous mixture asphalt
accounts for 5-8% of the weight of the mix. The exact percentage to be used is
determined by the ___.
a. Trial Mix
b. Design Mix
c. Job Mix
d. Job Order
74. ___is applied on existing bit, or cement concrete surface with bituminous materials.
a. Bituminous Prime Coat
b. Bituminous Tack Coat
c. Bituminous Seal Coat
d. Bituminous Surface Treatment
75. The solution used in the soundness test of aggregate shall be cooled to a
temperature of 21+of-1*C and maintain at that temperature for at least ___.
a. 24 hours
b. 36 hours
c. 48 hours
d. 18 hours
76. Proper compaction of the fill materials is very important, as it will ____.
a. Increase in the shear strength
b. Decrease permeability
c. Minimize compressibility
d. All of the above
82. In concrete acceptance, core will be considered adequate if the average strength of
the cores is equal to what?
a. 80%of specified strength &if no single core is less than 75% of specified strenght
b. 90%of specified strength & if no single core is less than 80%of specified
strength
c. 85%of the specified strength & if no single core is less than 75% of specified
strength.
83. Before the cement is to be used, sampling must be done at least ___before use.
a. one week
b. 14 days
c. two weeks
d. 12 days
84. Asphalt cement shall not be used while it is foaming nor shall be heated at
___anytime after delivery.
a. 107*
c. 120*
b. 159*
85. Moisture content of aggregates in bit.mix shall not exceed ___of the time it is
introduce into the mixing unit.
a. 1.5 mass %
b. 2.0 mass %
c. 1 mass %
86. Batching tolerance for Sand and Aggregates is ___.
a. 1 %
b. 2%
c. 3%
87. Between stage of curing, concrete shall not be exposed for more than how many
hours?
a. 24 hours
b. 3 hours
c. ½ hours
d. 72 hours
88. As Materials Engineer, what will you do with major honeycomb area that is
considered as defective work?
a. Plaster
b. Payment of the concrete will be made an adjustment
c. Removed and replaced at the expensed of the contractor
89. If the strength of control specimen does not meet the requirement and not feasible
to obtain cores due to structural consideration, as Materials Engineer what will be
your decision?
a. Remove and Replaced
b. Area will not be paid
c. Payment will be made at an adjusted price
90. After concrete has been placed, it is advisable to maintain fully wetted and in
position for how many hours?
a. 14 hours
b. 24 hours
c. 72 hours
d. 15-18 hours
91. Rock shall be excavated to a depth ___below sub grade within the limit of the
roadbed
a. 100 mm
b. 150 mm
c . 200mm
92. Minimum penetration of all piles shall be ___.
a. 3 meters
b. 6 meters
c. 7 meters
d. 4.5 meters
93. Piles shall not be driven within 7 meters of concrete less than ___
a. 7 days
b. 14 days
c. 28 days
101. Submission of sample minimum quantity of material for asphalt cement is ___
a. 5 kg.
b. 10kg
c. 20kg
d. 100kg
102. For how many years does the small Contractor given to procure necessary testing
equipment?
a. 2 years
b. 4 years
c. 5 years
d. 6 years
103. The depth of the weakened joints must be less than ___ and a width of ____.
a. 40mm & 6mm
b. 50mm & 5mm
c. 40mm & 5mm
d. 50mm & 6mm
104. Used of bituminous cold mix for potholes patching during rainy/wet period is
acceptable
a. True
c. False
105. In soil boring shall be carried to a depth of at least ___below the proposed grade
line.
a. 0.5m
b. 1.0m
c. 1.5m
d. 1.8m
106. The test that determine the pile bearing capacity by loading one or more pile and
measuring settlement under load is ___
a. Vane shear test
b. Plate bearing test
c. Pile load test
107. The weight of disturbed samples from hard auger or split spoon shall be at least__.
a. 1 kg
b. 20kg
c. 10kg
d. 100kg
108. The length of Shelby Tube of an undisturbed sample is ____.
a. 10”long
b. 18”long
c. 20”long
109. For small project where quantity of steel bars is 10,000kg.or less, what is the basis
of acceptance of material?
a. No testing
b. P.E.Certificate
c. Mill Certificate
110. ___determine the best combination of the material that will produce
potentially stable & durable mixture.
a. Job mix formula
b. Marshall formula
c. Design of bit.mix
111. ___is the rate of loading for concrete cylinder sample subject to compression test
a. 20-40psi/sec
b. 20-50psi/sec
c. 15-40psi/sec
d. 15-50psi/sec
112. In soil exploration, if the characteristic of rock is questionable, the minimum
depth of boring into the bedrock should be ____.
a. 1.5m
b. 2.0m
c. 2.5m
d. 3.0m
113.Determine the soil bearing capacity by loading a steel plate usually 30”diameter.
a. Vane shear test
b. Plate bearing test
c.Pile load test
d.None of the above
114. How many hours do aggregate stockpile or binned for draining before being
batch?
a. 1 hour
b. 6 hours
c. 12 hours
d. 24 hours
115.What is the rate of loading of concrete beam tested for flexural stress?
a.125-175psi/sec.
b. 115-150psi/sec
c. 110-150 psi/sec
d. 130-175 psi/sec.
116. What is the relative strength of mortar at 7 & 28 days of fine aggregates, when
tested for the effect of organic impurities, which is higher than the standards?
a. not less than 90%
b. not less than 80%
c. not less than 95%
d. not less than 98 %
117.In concrete sampling paste shall be of normal consistency of ______ when the rod
settles to a point below the original suface in 30 seconds.
a. 10+/- 1 mm
b. 11+/- 1 mm
c.15 +/- 1 mm
d. 20 +/- 1 mm
118. What is the curing temperature of a concrete sample?
a. 10-15 *C
b. 18-24*C
c. 15-18*C
d. 16-27*C
119.What is the wash loss of fine aggregates in the no.200 sieve?
a. 1 %
b. 2 %
c. 3 %
d. 4 %
120. Retarder can delay the setting time of concrete up to how many hours?
a. 1 hour
b. 2 hours
c. 4 hours
d. 8 hours
121.Super plasticizer can increase the strength of concrete up to how many percent ?
a. 40-60 %
b. 50-60 %
c. 50-70 %
d. 60-70%
125. In the absence of beam mold in site, cylinder mold is allowed by specification.
What is the required strength?
a. 2500 psi
b. 3000 psi
c. 3500 psi
d. 4000 psi
126.Prime coat shall be left undisturbed for at least ______.
a. 6 hours
b. 12 hours
c. 24 hours
127.The first phase of rolling the spread bituminous mix is called breakdown rolling
which is carried out by pneumatic roller, temperature requirement must be
________.
a. 200 – 225 *F
b. 190-199 8F
c. 160-180 *F
d. 150-185 *F
128.How many gradation ranges for hot plant mix bituminous pavement are there in
the blue book?
a. 5
b. 6
c. 7
d. 8
129. What is the plasticity index of mineral filler?
a. not greater than 4
b. not greater than 6
c. not greater than 8
d. zero
130.If no core had been taken at the end of each day of operation and the project has
already been completed, a core shall be taken ________
a. for every 75 l.m./lane
b. for every 150 l.m./lane
c. for every 100 l.m./lane
d. for every 1,000 l.m./lane
134.________ is the limit were further loss of water due to evaporation which sill not
result in reduction of volume.
a. Plastic Limit
b. Liquid Limit
c. Shrinkage Limit
135.________ a classification of soil which 35% or less the particles pass through no.
200 sieve .
a. Grain size soil
b. Granular Materials
c. Silty Clay Materials
d. Clayey Materials
136.________ a classification of soil which 35% more of the particles pass through
200 sieve.
a. Course Sand Soil
b. Granular Materials
c. Silty-Clay Materials
d. Clayey Materials
140.It indicates very poor subbase materials when G.I. is equal to _____.
a. 0
b. 5
c. 10
d. 20
144.When the value of G.I. Is negative, what will be the soil performance?
a. Poor Subgrade
b. Very good Subgrade
c. Good Subgrade
d. None of the above
147.Percent passing loose for coarse aggregates when tested for clay lump is _______.
a. 1.0 percent
b. 0.25 mass percent
c. 0.8 percent
d. 1.0 mass percent
148.The mass percent passing loose for coarse aggregates when tested soft fragment is
_______.
a. 0.10
b. 0.25
c. 3.5
d. 1.0
148.If slag is used, the density of coarse aggregate is ________.
a. 30-100 kg/cu.m. .
b. 150 kg./cu.m.
c. 1,120 kg/cu.m
d. 1,400 kg/cu.m.
149.Mass percent loose for fine aggregates when tested in Clay lumps is ____.
a. 0.10
b. 0.25
c. 0.80
d. 1.0
150. _______ is a type of cement which shall be transferred to an elevated, air tight and
weather proof bins storage.
a. Portland Cement
b. Pozzolan Cement
c. Bulk Cement
d. None of the above
151.Scales for weighing aggregates and cement shall be accurate within _____.
a. 0.1%
b. 0.25%
c. 0.5%
d. 1.9%
152._______ determines the resistance of the emulsion to break with mixed with
mineral aggregates.
a. Viscosity Test
b. Distillation Test
c. Spot Test
d. Cement Mixing
159.The batches shall be so charged into the drum that a portion of the mixing water
shall enter in advance of the cement and aggregate. The flow of water shall be
uniform and all water should be in the drum by the end of the _____________
of the mixing period.
a. 20 seconds
b. 15 seconds
c. 10 seconds
160. The time elapsed from the time water is added to the mix until the concrete is
deposited at the site shall not exceed ____________when concrete is hauled in the
truck.
a. 60 minutes
b. 70 minutes
c. 90 minutes
161.When concrete is delivered in truck mixers, additional water may be added to the
batch and additional mixing performed to increase the slump to meet the specified
requirement if permitted by the Engineer, provided all these operation are
performed within __________ after the initial mixing operation and the water and
cement ratio is not exceeded.
a. 42 minutes
b. 45 minutes
c. 47 minutes
162.Concrete not placed within ___________ from the time the ingredients were
charge into the mixing drum should not be use.
a. 90 minutes
b. 92 minutes
c. 95 minutes
165.Aggregate account 92-95% of the weight of the bituminous mix while asphalts for 5-
8% of the weight of the mix. The exact percentage to be used is determined by the
_________.
a. Blue smoke
b. Job Mix
c. Extraction Test
169. Cast in place concrete shall not be post-tensioned until at least ________.
a. 5 days
b. 10 days
c. 15 days
170. This characteristic generally used for calculation of the volume occupied by the
aggregate in various mixture containing aggregates including Portland Cement
Concrete, Bituminous Concrete and other mixtures that are proportioned or analyzed
on an absolute volume basis.
a. Apparent Specific Gravity
b. Marshall Stability Test
c. Bulk Specific Gravity
174. These are widely used to control the characteristics of soil which are to be
incorporated in roadway.
a. Shrinkage Limits
b. Cement and Soil Limits
c. Liquid and Plastic Limits
175. This is defined as the highest moisture content of which the mass attains its
minimum volume but continues to lose weight /mass.
a. Shrinkage Limits
b. Cement and Soil Limits
c. Liquid and Plastic Limits
176. _____________________is an apparatus used in determination of specific gravity
of Hydraulic Cement.
Answer: Le Chattelier Flask
178. Asphalt shall be homogeneous, free from water, and shall not foam heated to
_________________.
Answer: 175*C (347*F)
179. __________________, Test of Asphalt indicate the rate at which the asphalt
emulsion will break when mix with aggregate.
180. The lost in weight of rock use in gabions when tested to sodium sulfate,
soundness loss shall not exceeds ______.
Answer: 9%
Answer: +/- 3%
182. The pour point of concrete joint sealer shall be at least ________ lower than the
safe heating temperature, which is the maximum temperature to which the material
may be heated without exceeding the permitted flow.
Answer: 90
185. The penetration piston of CBR machine should have a uniform penetration at a
rate of _________________.
Answer: 1.30mm/min.
186. During soaking maintain the water level in the mold and the soaking tank is
approximately _____________ above the tope of the specimen.
Answer: 49.63+/-0.23 mm
189. The temperature of the asphalt cement delivered to the mixer shall be required to
achieve a kinetic viscosity in the range of
Answer: 10 – 71*C
193. When the tar is used for seal coats, It shall be heated to free flowing not to exceed
___________.
Answer: 107* C
Answer: Consolidation
196. The weight of disturbed samples from hard auger or split spoon shall be at least
___________.
200. ___________ determine the soil bearing capacity by loading a steel plate usually
30 inches in diameter.
203.A document which prevents the test result and other information relevant to test is
called _____________.
204. is a document signed by the Director of BRS issued to Testing laboratory authorizing
them to perform the required test in behalf of D PWH.
Answer: Permeability
209. For liquid asphaltic materials, this test is run on the residue after distillation.
214. Plant –mixed bituminous mixtures should be sampled in accordance to the Standard
Method of Sampling Bituminous Mixture. A sample not less than ______ is taken
and place in sample bag that would insure against contamination. This is taken every
75 cum. or 130 tons of mix.
Answer: 10 kg.
215. The bearing blocks of the compression machine should be at least ______ greater
than the diameter of the specimen.
Answer: 3.0 %
216. The bottom bearing block shall be at least ___________thick when new bottom
bearing block shall be at least _______ thick after any resurfacing operations.
Answer: 16-27*C.
218. The apparatus used to determine the flash point of asphaltic material is called
_________________.
Answer: Cleveland Open Club
219. The asphalt samples for ductility and penetration test should be subjected to
water bath at a temperature of 25* C for __________.
Answer: 1 ½ hours
220. The concrete shall not be left exposed for more than ___________.
Answer: ½ hour
223. The _______ test determines the asphalt content in the bituminous mix.
a. Grading
b. Bulk Specific Gravity
c. Extraction
d. Absorption
224.In a bituminous mix, there are 3 kinds of aggregate. What kind of passes the no.
200 sieve?
a. Coarse
b. Fine
c. Mineral Filler
d. Admixture
225. Liquid asphalt is also called ________.
a. Cutback Asphalt
b. Emulsion
c. Blown Asphalt
d. Asphalt Cement
226.The apparatus/equipment used in the liquid limit and plastic limit test is called
_______.
a. Sieves and chisel
b. Attenberg Dev.
c. Mortar and glass pestle
229.What is the specification of mass percent passing in sieve 0.075 mm. No. 200
sieve grading “A” for aggregate base course.
a. 20-14
b. 0-12
c. 0-6
234. In the absence of concrete beam mold at the project site, are concrete cylindrical
molds allowed by the specification to be used in sampler for Item 311-PCCP?
a. Yes
b. No
235. The minimum percent compaction for embankment is ______.
a. 92.0 %
b. 97.0 %
c. 95.0 %
236. The minimum percent compaction for base of the road is _______.
a. 100.00%
b. 105.00 %
c. 110.00%
237. The CBR value of aggregate base course is not less than _____.
a. 80.0 %
b. 85.0 %
c. 90.0 %
238. The CBR value of aggregate subbase course is not less than ____.
a. 25.0 %
b. 30.0 %
c. 35.0 %
239. The minimum compressive strength for Class A concrete is ______.
a. 3,000 psi (20.7 MN/sqm.)
b. 2,400 psi (16.7 MN/sqm.)
c. 5,000 psi (37.7 MN/sqm.)
244. The apparatus used to measure the thickness or height of compacted bituminous
paving mixture.
a. Ruler
b. Vernier Califer
c. Steel Tape
245.It is used in calculating the unit weight of the mixture and the degree of
compaction of the asphalt pavement.
a. Bulk Specific Gravity of compacted bituminous mixtures using saturated surface
dry specimen.
b. Dry unit weight of compacted bituminous mixtures
246.The test which covers the quantitative determination of bitumen in hot mixed
paving mixtures and pavement samples for specification service evaluation, control
and research.
a. Extraction
b. Spot Test
c. Flash Point
249.The method used to determine the grading of aggregate extracted from bituminous
mixture is _______.
a. Mechanical analysis of extracted aggregates
b. Stability Test
c. Viscosity Test
250.The drying temperature of sample is _______.
a. 110 +/- 5* C
b. 100 * C
c. 100 +/-5 *C
251._______ is a solid asphalt which is a basic constituent of all other asphalt called as
hot asphalt or penetration grade asphalt.
a. Asphalt Cement
b. Cutback Asphalt
c. Emulsified Asphalt
255.It is a kind of liquid asphalt which is a mixture of asphalt cement and water with
emulsified with pungent odor.
a. Emulsified Asphalt
b. Asphalt Cement
c. Rapid Curing Asphalt
259.An apparatus used to determine the specific gravity of asphalt is called ______.
a. Metal Pycnometer
b. Glass Pycnometer
c. Any bottle
261.A process of volatilization test which measures the relative proportion of asphalt
to oil.
a. Distillation
b. Extraction
c. Float Test
262._____ is a period wherein the asphalt begins to melt.
a. Softening Point
b. Fire Point
c. Boiling Point
274. The rate of application of prime coating using cutback asphalt is _______.
a. 1-2 liters/sqm.
b. 0.5-1.0 liter/sqm.
C. 2.0-3.0 liters/sq.m.
275. The rate of application of tack coating using liquid or emulsified asphalt is
_______.
a. 0.2-0.7 li./sqm.
b. 0.1-0.5 li./sqm.
c. 2.0 li/sqm.
276.The rate of application of seal coat using asphalt cement is ______.
a. 0.9-1.8 li./sqm.
b. 10-11 li.sqm.
c. 8.0-9.0 li./sqm.
277. The rate of application of seal coat using cutback asphalt is _____.
a. 1.5-3.0 li./sq.m.
b. 2.0-3.0 li./sq.m.
c. 1-2 li/sq.m.
278. The primary quality control mechanism for the production of asphalt mixes with
high degree of uniformity that will satisfy job requirement is ________.
a. Job mix formula
b. Quality control formula
c. Assurance
279.The percent asphalt content in hot laid bituminous mixture range from
________.
a. 5.0-8.0%
b. 4.0-6.0 %
c. 5.0-10.0 %
280. The placing of temperature for bituminous mixture measured in the truck prior to
dumping is ________.
a. at least 107*C
b. at least 120*C
c. at least 150*C
281.The second phase of rolling the spread bituminous mixture is called breakdown
rolling which is the one responsible to attain the maximum density. The rolling is
carried out by the use of ________.
a. pneumatic roller
b. steel roller
c. sheepfoot roller
282.The significance of the final rolling is to remove the roller marks to previous
rolling in order to have a good finish pavement with a temperature of 160*C.
a. True
b. False
c. Maybe
291. _______ is the type of cement to be used in the DPWH Portland Cement Type II.
a. Portland Cement Type I
b. Pozzolan Cement
c. Portland Cement II
292. If the fine aggregates are subjected to five cycles of sodium sulfate soudness test,
the weighted loss shall not exceed _________.
a. 10 mass percent
b. 5 mass percent
c. 3 mass percent
293. Specimen of coarse aggregates are subjected to five cycles of sodium sulfate
soundness test, the weighted loss shall not exceed _______.
a. 12 mass percent
b. 15 mass percent
c. 10 mass percent
294. The mass percent of wear of coarse aggregates for Item 311 when tested by
AASHTO 96 is not greater than __________.
a. 40 %
b. 45 %
c. 50 %
295. The design of concrete mix specified by the blue book is based on _______.
a. Absolute Volume Method
b. Area Method
c. American Method
296.The minimum flexural strength requirement of beam sample when tested by the
third point of loading method is __________.
a. 3.5 Mpa
b. 3.8 Mpa
c. 4.0 Mpa
297. The minimum flexural strength requirement of beam sample when tested by
midpoint method is ________.
a. 4.5 Mpa
b. 3.5 Mpa
c. 5.0 Mpa
301.The initial setting time of Portland Cement is not less than ________.
a. 30 min.
b. 60 min.
c. 90 min.
d. 45 min.
302.The standard sand used in testing the mortar strength of Portland Cement is called
________.
a. Ottawa Sand
b. Beach Sand
c. River Sand
303.The apparatus used in determining the fineness of Portland Cement air
permeability is _________.
a. Blaine Air Permeability Apparatus
b. Sieve No. 200
c. Gilmore
305.The apparatus is used to determine the initial and final setting of cement in the
laboratory is ________.
a. Gilmore needle
b. Balley needle
c. Vicat apparatus
306.The compressive strength of cement mortar Type IP sample in seven days is not
less than _______.
a. 19.3 MN/sqm.
b. 20 MN/sqm. (Type IP=19 MN/sqm.)
c. 24 MN/sqm.
307. What is the appearance of the molded cement paste which fails to meet the
autoclave expansion?
a. crumble
b. Shiny
c. changes color
311.There are two layers in performing sampling of beam samples. How many number
of blows are required per layer?
a. 63 blows
b. 75 blows
c. 50 blows
312.There are three layers in performing sampling of concrete cylinder how many blows
are required per layer?
a. 25 blows
b. 30 blows
c. 35 blows
313.The formula which determines the proportion of the mix which can meet the
desired strength requirement of concrete is called _______.
a. Quality Control Program
b. Program of Work
c. Work Schedule
314. It is prescribed in each project based on estimated quantities and specifies the
kind and number of test for each item of work.
a. Minimum number of work
b. Minimum Testing Requirement
c. Work Schedule
315.Embankment materials delivered at the job site was about 12,000 cum. The
minimum test requirement calls for 1-GPC, for every 1500 cum.
a. 10-GPC
b. 8- CPC
c. 6-GPC
327.Based on the maximum dry density obtained by laboratory test the degree of
compaction required for aggregate subbase should be at least _________.
a. 99.0 %
b. 98.0 %
c. 100.0 %
328.Per our present Specification for Highways and Bridges including amendments, it is
mandatory to open PCCP to traffic not later than _____.
a. 7 days after pouring
b. 14 days after pouring
c. 21 days after pouring
d. 28 days after pouring