Professional Documents
Culture Documents
0 1 2 3 4
NPV10% $56.50
The project would be rejected by an all-equity firm: NPV < 0.
APV Example (continued)
Now, imagine that the firm finances the project with $600 of debt at rB = 8%.
Pear’s tax rate is 40%, so they have an interest tax shield worth TCBrB = .40×$600×.08 =
$19.20 each year.
Discount the cash flow from the project to the equity holders of
the levered firm at the cost of levered equity capital, rS.
There are three steps in the FTE Approach:
Step One: Calculate the levered cash flows
Step Two: Calculate rS.
Step Three: Valuation of the levered cash flows at rS.
Step One: Levered Cash Flows for Pears
Since the firm is using $600 of debt, the equity holders only have
to come up with $400 of the initial $1,000.
Thus, CF0 = –$400
Each period, the equity holders must pay interest expense. The
after-tax cost of the interest is B×rB×(1 – TC) = $600×.08×(1 – .40)
= $28.80
CF3 = $375 – 28.80 CF4 = $500 – 28.80 – 600
CF2 = $250 – 28.80
CF1 = $125 – 28.80
–$400 $96.20 $221.20 $346.20 –$128.80
0 1 2 3 4
Step Two: Calculate rS for Pears
B
rS r0 (1 TC )( r0 rB )
S
B B
To calculate the debt to equity ratio, , start with
S V
4
$125 $250 $375 $500 19.20
PV 2
3
4
t
(1.10) (1.10) (1.10) (1.10) t 1 (1 . 08 )
P V = $943.50 + $63.59 = $1,007.09
B = $600 when V = $1,007.09 so S = $407.09.
$600
rS .10 (1 .40)(. 10 .08) 11.77%
$407.09
Step Three: Valuation for Pears
Discount the cash flows to equity holders at rS = 11.77%
0 1 2 3 4
PV $28.56
APV Example:
Worldwide Trousers, Inc. is considering replacing a $5 million piece of
equipment. The initial expense will be depreciated straight-line to zero
salvage value over 5 years; the pretax salvage value in year 5 will be
$500,000. The project will generate pretax savings of $1,500,000 per year,
and not change the risk level of the firm. The firm can obtain a 5-year
$3,000,000 loan at 12.5% to partially finance the project. If the project were
financed with all equity, the cost of capital would be 18%. The corporate tax
rate is 34%, and the risk-free rate is 4%. The project will require a $100,000
investment in net working capital. Calculate the APV.
APV Example: Cost
Let’s work our way through the four terms in this equation:
APV = –Cost + PV unlevered + PV depreciation + PV interest
project tax shield tax shield
The cost of the project is not $5,000,000.
We must include the round trip in and out of net working
capital and the after-tax salvage value.
NWC is riskless, so we discount it at rf. Salvage value should
have the same risk as the rest of the firm’s assets, so we use r0.
100,000 500,000 (1 .34)
Cost $5.1m
(1 r f ) 5
(1 r0 ) 5
$4,873,561.25
APV Example: PV unlevered project
5
UCFt 5
$1.5m (1 .34)
PVunlevered
project t 1 (1 ro ) t
t 1 (1 . 18) t
PVunlevered $3,095,899
project
APV Example: PV depreciation tax shield
PV depreciation D TC t
5
tax shield t 1 (1 r f )
5
$1m .34
t
$1,513,619
t 1 (1.04)
APV Example: PV interest tax shield
Turning our attention to the last term,
5
127,500
PV interest t
453,972.46
tax shield t 1 (1.125)
APV Example: Adding it all up
APV = $189,930