Professional Documents
Culture Documents
Standrd Bidding Document, Bidding Document Preparation, Biddes Qualification
Standrd Bidding Document, Bidding Document Preparation, Biddes Qualification
PROCUREMENT OF
WORKS AND
CONSULTANCY
SERVICES
STANDARD BIDDING
DOCUMENT,BIDING
DOCUMENT
B2 TRAINING ON PROCUREMENT OF WORKS AND CONSULTANCY
SERVICES
PREPARATION,
BIDDER'S ELIGIBILITY, IPFMRP – CDP Project
QUALIFICATION AND
EVALUATION
CRITERIA
Provision Relating to Bidding
Bidding Document
Qualification of Bidder
Bidder's Eligibility Criteria
Criteria for Qualification of a
Presentation Construction Entrepreneur
Outlines Criteria of Qualification for JV
Pre-Qualification of Bidders
Bidders Evaluation Criteria
Post-Qualification of Bid
Document
Provision Relating to Bidding (Rule 31)
Procurement to be Made through Bidding: A Public
Entity shall have to procure construction work valuing
above 20 million Rupees through a bid.
In the conditions set forth for International Bidding
(Section 15) of the Act, construction works shall have
to be procured by inviting an open international level
bidding.
Disclosures of Evaluation and Qualification Criteria is
an essential elements for transparancy in procurement
and also for competitive purpose.
FAMILIARITY WITH THE RELEVANT KEY WORDS
“Bid” means a document setting out price, proposal or rate
submitted by a bidder in the format specified by a Public Entity as per
the notice published by that entity for procurement;
“Bidder” means any person, firm, organization or company that
submits or may submit bid to take part in procurement proceedings;
“Bidding Document” means a document prepared by the
concerned Public Entity making invitation to bid for submission by
bidders by filling up or preparing price or proposal or rate in such
document and this term also includes instructions to bidders,
specifications, drawing, design, terms of reference, schedule of work,
evaluation criteria, bill of quantities, conditions of contract and
similar other documents;
“Procurement Contract” means a procurement contract entered
into between a Public Entity and a supplier or construction
5
entrepreneur or consultant or service provider
BIDDING DOCUMENT CONTENTS (SEC. 13)
PPA has stated that Bidding Documents should be prepared prior to invitation to
bid.
As per PPA , a PE shall have to prepare the bidding documents and shall contain the
following matters:-
(a) The nature of procurement, time required for procurement and technical
specifications thereof,
(b) If prequalification (PQ), criteria for bidder qualification
(c) Site visit, information relating thereto,
(d) Pre-bid conference - prior to submission of bid, information relating to such
conference
BIDDING DOCUMENT CONTENTS (SEC. 13)
(e) Instructions for preparing and submitting bids, the place and deadline for the
submission of bids and the place, date and time for the opening of bids,
(f) Component of price, the currency or currencies in which the bid price may be
stated, the currency and the source and date of the related exchange rate to be used
for comparison of bids,
(g) The criteria and methodology for the evaluation of bids and the selection of
bidder,
(h) The preferences to be given, if any, for domestic goods and local construction
entrepreneurs, provision relating thereto,
BIDDING DOCUMENT CONTENTS (SEC. 13)
(q) Provision that any bidder may make an application, for review, against any error or
decision made by the Public Entity in carrying out bid proceedings,
(r) Provision that the documents proving technical capacity and financial proposal
(bid price) have be submitted in one
(s) Such other matters determined by the PPMO as to be involved in the PQ
documents or bidding documents.
BIDDING DOCUMENT CONTENTS (SEC. 13)
The Public Entity shall make available the bidding documents upon collection of the
charges as prescribed to any person, firm, organization or company that requests for
the bidding documents in accordance with the notice for invitation to bids, and
where prequalification is required to participate in the procurement proceedings, to
those persons, firms, organizations or companies that have been pre-qualified and
request for such documents.
Public Procurement Monitoring Office,
website:ppmo.gov.np
10
BIDDING DOCUMENTS
Purpose:
Equal Information to ALL Bidders
What is to be Procured
Technical Requirements
How to Prepare a RESPONSIVE BID
Evaluation Criteria
Form of Contract
BIDDING DOCUMENTS
14
Invitation for Bid
Publication of Procurement Notice
Place and Period in Which the Bidding Documents are Made Available
Date of Closing and Extensions, if any
Pre-bid Conference
Place of Submission of Bids
Date and Time of Public Bid Opening
15
Instruction to Bidders (ITB)
For bidders to prepare Responsive bid,
On composition of bidding documents and preparation of bids,
On bid submission, opening, evaluation, and award of contract,
Contents in ITB are to be changed as per project requirement
ITB will not be a part of contract,
16
Bid Data Sheet (BDS)
This section consists of provisions specific to each procurement and supplements the
information or requirements included in Instructions to Bidders (ITB)
BDS must refer to Instructions to Bidders (ITB) Clauses,
Bidding data is used to specify the ITB clauses by inserting specific data (name, days,
amount etc.) and required changes,
Bidding data replaces the ITB clauses, if changed,
Bidding data to be filled out by the Employer before issuance of the Bidding
documents.
17
Section I: Instructions to Bidders
A. General
1.1 In connection with the Invitation for Bids indicated in the Bid Data Sheet (BDS), the Employer, as
1.
Scope indicated in the BDS, issues this Bidding Document for the procurement of Works as specified in
of Bid Section VI (Works Requirements). The name, identification, and number of Contracts of the National
Competitive Bidding (NCB) are provided in the BDS.
22
D. Submission and Opening of Bids
ITB 21.1 Bidders shall have the option of submitting their bids ____[insert option 1: "by electronic
only"
option 2: or "by electronic or by mail / by hand / by courier"
option 3: "by mail / by hand / by courier"]___ .
ITB 22.1
For bid submission purposes only, the Employer’s address is :
Attention : …………………………
Address : ………………………….
The deadline for bid submission is :
Date : …………………………..
Time : ………………………….. [Insert time that is immediately after submission
deadline]
ITB 25.1
The Technical Bid opening shall take place at :
Address : ………………………
Date : …………………………..
Time : ………………………….
23
E. Evaluation and Comparison of Bids
ITB 34.1
a) Contractor’s proposed subcontracting: Maximum percentage of
subcontracting permitted is: 25% of the total contract amount.
b) Sub-contractors’ qualification and experience will not be considered
for evaluation of the Bidder. The Bidder on its own (without taking into
account the qualification and experience of the sub-contractor) should
meet the qualification criteria.
ITB 35.5
The amount of the performance security be increased by 50 percent on
the original bank guarantee of 5 percent (if quotated amount is within 15
percent below of estimate) of the quoted amount between the between
85 percent and the quoted bid price.
24
Section III: Evaluation and Qualification Criteria
This Section contains all the criteria that the Employer shall use to evaluate bids
and qualify Bidders by post-qualification exercise. GoN/DP requires bidders to
be qualified by meeting predefined, precise minimum requirements. The
method sets pass-fail criteria, which, if not met by the bidder, results in
disqualification.
In accordance with ITB 32 and ITB 35, no other methods, criteria and factors
shall be used.
The Bidder shall provide all the information requested in the forms included in
Section IV (Bidding Forms).
1. Evaluation
In addition to the criteria listed in ITB 35.2 (a) - (e) the following criteria shall
apply:
Note:
Use the evaluation criteria listed below as appropriate and required for the
project.
1.1 Adequacy of Technical Proposal
the requirements stipulated in Section VI (Works Requirements).
1.2 Multiple Contracts
Multiple Contracts, if permitted under ITB 35.4, will be evaluated as follows:
Award Criteria for Multiple Contracts [ITB 35.4:
25
Bidders have the option to Bid for any one or more Contracts.
Section III: Evaluation and Qualification Criteria
.
Qualification Criteria for Multiple Contracts:
The criteria for qualification shall be the sum of the minimum requirements for respective individual contracts
Contract 1: N1 contracts, each of minimum value V1;
Contract 2: N2 contracts, each of minimum value V2;
Contract 3: N3 contracts, each of minimum value V3;
----etc.
and
•Total number of contracts is equal or less than N1 + N2 + N3 +--but the total value of all such
contracts is
• equal or more than N1 x V1 + N2 x V2 + N3 x V3 +---.
1.3In Case, other than Multiple Contracts
Bidders have the option to Bid for any one or more Contracts.
1.4 Completion Time
An alternative Completion Time, if permitted under ITB 13.2, will be evaluated as follows:
[insert project specific requirements]
1.5 Alternative Technical Solutions
Alternative technical solutions, if permitted under ITB 13.4, will be evaluated as follows:
[insert project specific requirements]
1.6 Quantifiable Nonconformities and Omissions
Subject to ITB 14.2 and ITB 35.2, the evaluated cost of quantifiable nonconformities including
omissions, is determined as follows:
[Insert in bidding document: “Pursuant to ITB 31.3, the cost of all quantifiable nonmaterial
nonconformities shall be evaluated,
but excluding omission of prices in the BoQ.The Employer will make its own assessment of the cost
of any nonmaterial nonconformities
and omissions for the purpose of ensuring fair comparison of bids.”] 26
Evaluation and Qualification
Qualification for Eligibility
Nationality
Conflict of Interest
Government/DP Eligibility
Government owned Entity
UN Eligibility
Other Eligibility
Firm Registration Certificate
Business Registration Certificate
VAT and PAN Registration Certificate
Tax Clearance Certificate/Tax return submission
Evaluation and Qualification
Pending Litigation
Financial Situation
Joint Venture
Pending Litigation
All pending litigation must meet not applicable must meet not applicable
shall be treated as requirement requirement by
resolved against the by itself or as itself or as
Bidder and so shall in partner to past partner to past
total not represent or existing JV or existing JV
more than …percnt of
the Bidder’s net worth.
29
Evaluation and Qualification: Financial Situation
Criteria Compliance Requirement
Joint Venture
Single
Requirement All Partners Each
Entity One Partner
Combined Partner
Historical Financial Performance
Submission of audited balance must meet not applicable must meet not applicable
sheets and income requirement requirement
statements, for the last ……
years to demonstrate the
current soundness of the
Bidder’s financial position. As
a minimum, a Bidder's net
worth calculated as the
difference between total
assets and total liabilities
should be positive.
30
Evaluation and Qualification: Financial
Situation
Criteria Compliance Requirement
Joint Venture
Single All
Requirement Each One
Entity Partners
Partner Partner
Combined
Average Annual Construction Turnover
Minimum average annual must meet must meet must meet must meet
construction turnover of requirement requirement . . . . . . . . . ........
NRs. ………………….,
of the of the
calculated as total
requirement requirement
certified payments
received for construction
contracts in progress or
completed, within best
three years out of last
ten years..
31
Evaluation and Qualification: Financial
Situation
Criteria Compliance Requirement
Joint Venture
Single
Requirement All Partners Each One
Entity
Combined Partner Partner
Financial Resources
Using Forms FIN – 3 and FIN must meet must meet must meet must meet
- 4 in Section IV (Bidding requirement requirement ......... ........
Forms) the Bidder must
demonstrate access to, or of the of the
availability of, financial requirement requirement
resources such as liquid assets,
unencumbered real assets,
lines of credit, and other
financial means, other than any
contractual advance payments
to meet its current contract
commitments, plus:
the following cash-flow
requirement NRs ………..……………
Evaluation and Qualification: Experience
33
Evaluation and Qualification: Experience
??? ????
35
Evaluation and Qualification: Personnel
36
Evaluation and Qualification: Equipment
37
Bidding Forms
Forms provided by the Employer that the Bidder must complete and include in
its Bid
Standard Bidding Forms are:
Letter of Bid (Technical/Price)
Bid Security / Bid-Securing Declaration
Technical Proposal Format
Personnel/Equipment Forms
Bidder’s Qualification Forms
38
Bidding Forms
39
Preparation of Specs. and BOQ
Precise and clear Technical Specification
Permit widest possible competition
Clear statement of the required standards of
materials, Plant, other supplies, and workmanship
Specifications not to be restrictive
Required quantity with cross reference to
specification
40
General Conditions of Contract (GCC)
This Section of the Bidding Documents should provide:
Information on Matters governing the performance of the Contractor
Payments under the Contract
Matters affecting the risks, rights, and obligations of the parties
If duplication of a subject is inevitable in the different sections of the documents,
care must be exercised to avoid contradictions between clauses dealing with the
same matter.
41
General Conditions of Contract (GCC)
To be read in conjunction with the Special Conditions of Contract and other
documents as listed in Bidding document,
Should fairly express the Rights & Obligations of both parties,
To be written in Simple language and Standard clauses with no change,
Standard CoC can be different for Large, Medium, Small, admeasurement, lump
sum and design and build contracts
42
Special Conditions of Contract (SCC)
Special Conditions of Contract provides contract specific information in relation to
Clauses in CoC,
If provisions in CoC are not relevant to the Contract, those should be marked “NA”
(Not applicable).
If provisions in CoC are not sufficient to describe the contract specific information,
those clauses may be modified or some new provisions may be added, as needed.
Special Conditions of Contract to be filled by the Employer before issuance of Bidding
documents
43
SCC: Content to Fill-refer GCC
GCC 1.1(q) The Employer is ...........................
GCC 1.1 (v) The Intended Completion Date for the whole of the Works shall be ...
GCC 1.1(bb) & The Project Manager is ... .... . [insert name of Project Manager]
10.1
The Project Manager and Engineer are synonyms.
GCC 1.1 (ee) The Site is located at ... [insert location] and is defined in drawings No.
GCC 1.1 (hh) The Start Date shall be ... .. [insert date]
GCC 1.1 (ll) The Works consist of ... ...... [insert the name of Works to be completed by the
Contractor].
GCC 2.2 Sectional Completions are: ... .... .. [insert detail if applicable]
44
SCC: Content to Fill-refer GCC
GCC 2.3(i) The following documents also form part of the
Contract: ...............................
GCC 3.1 The language of the contract is ENGLISH/NEPALI
The law that applies to the Contract is the law of NEPAL.
GCC 11.1 The Project Manager …………. Delegate any of his duties and
responsibilities
GCC 14.1 Schedule of other contractors ……..[Insert details as appropriate]
GCC 19.1 The minimum insurance amounts and deductibles shall be:
1. The minimum cover for loss of or damage to the Works,
Plant and Materials is:
2. The maximum deductible for insurance of the Works and of
Plant and Materials is:
3. The minimum cover for loss or damage to Equipment is :
46
SCC: Content to Fill-refer GCC
GCC 34.1 The Contractor shall submit for approval a Program for the Works within
…………… days from the date of the Letter of Acceptance.
GCC 34.3 The period between Program updates is ….............. days.
The amount to be withheld for late submission of an updated Program
is ...............
47
SCC: Content to Fill-refer GCC
48
SCC: Content to Fill-refer GCC
GCC 56.1 The Bonus for the whole of the Works is ........................ per day. The maximum
amount of Bonus for the whole of the Works is ........................of the final Contract
Price.
GCC 57.1 The Advance Payments shall be: ............................... and shall be paid to the
Contractor no later than .................................
GCC 57.3 Deductions from … Exceeds 30% .Deduction will be at …………completely repaid
prior to the end of 80% of the approved contract period.
GCC 58.1 The Performance Security amount is ...................................
[insert amount including an additional amount based on ITB 40.1 and/or
ITB 35.5 if the Employer has increased the Performance Security amount]
GCC 71.1 The date by which operating and maintenance manuals are required is .................
The date by which “as built” drawings are required is .....................
GCC 71.2 The amount to be withheld for failing to produce “as built” drawings and/or
operating and maintenance manuals by the date required in GCC 58.1
is ..........................
GCC 72.3 (i) The maximum number of days is: ......................
49
Special Conditions of Contract
GCC 80 The Project Manager has to obtain the specific approval of the Employer for
taking any of the following actions:
a. Approving subcontracting of any part of the works under General
Conditions of Contract Clause 13;
b. Certifying additional costs determined under General Conditions of
Contract Clause 50;
c. Determining start date under General Conditions of Contract Clause 1;
d. Determining the extension of the intended Completion Date under
General Conditions of Contract Clause 35;
e. Issuing a Variation under General Conditions of Contract Clause 1 and
46, except in an emergency situation, as reasonably determined by the
Engineer; emergency situation may be defined as the situation when
protective measures must be taken for the safety of life or of the works or
of adjoining property.
f. Adjustment of rates under General Conditions of Contract Clause 45;
50
Points to Note:
SBD's should be prepared as per the provisions made in the prevailing PPA/PPR
and Technical Guidelines / Directives of PPMO :
PP Act in Force (2063 Poush 30, First Amendment on 2073 Asadh 30-
3 amendments upto now)
PP Regulation (2064 Bhadra 3). Nineth amend- 2076 Poush
Use PPMO’s model SBD (www.ppmo.gov.np)
If no model document available then prepare considering professional and as per
the work requirement and legal provision and obtain consent from PPMO to use
for the purpose ( i.e. EPC-Engineering, Procurement and Construction Contract,
PPP etc.)
Clauses/Requirements of SBD to be Made Consistent With the ACT and
REGULATION
If Bidding Documents clauses/ provisions contradicted with PPA & PPR then the PP
Law apply
51
Qualification of Bidder (Sec.10)
Bids, pre-qualification proposals shall be evaluated only in
accordance with the criteria set forth in the bidding
documents, pre-qualification documents.
The criteria shall equally be applicable to all bidders without
any discrimination.
No qualification requirements shall be prescribed for the
procurement of a construction work the cost estimate of
which is less than twenty million rupees.
The Public Entity may disqualify a bidder at any time if it finds
that the statement submitted by such bidder concerning the
qualifications was factually false or substantially incomplete.
Minor errors can be corrected by seeking information from
the concerned bidder.
Qualification of Bidder (Sec.10) Contd..
A bidder should fulfill qualification to obtain a
procurement contract.
Depending nature of solicitation, bidder has to be fulfill
qualification.
Bidder has to fulfill the qualification criteria set forth
in the bidding documents , if it is a bid or but if bidder
is applying for prequalification proceedings then the
qualification criteria set forth in the prequalification
documents should be fulfilled .
Qualification of Bidder (Sec.10) Contd…
Depending on the nature and complexity of the work the
following qualification criteria in the bidding documents
may be set forth: professional and technical
qualifications, equipment availability, past performance,
after-sale service arrangements, availability of spare parts,
legal capacity, financial resources and condition,
punishment for having committed professional offenses
and similar other criteria.
Criteria set forth in the bidding / prequalification
document should not allow or to prevent only a particular
class of construction entrepreneur from participating in
the procurement process.
Process and Stage of Bidding also be
considered while selecting Criteria (Sec 11)
PE should prepare criteria according to the process and
stage of the bidding, as follows:
•76