Professional Documents
Culture Documents
a. They will be checked, and if they are Done, the Product Owner typically accepts them.
b. They should be moved to the next Sprint Backlog.
c. They should be moved back to the Product Backlog, and will be taken care of in future Sprints.
2- When is a Product Backlog item ready?
a. TRUE
b. FALSE
4- Which of the following is needed for starting a new Sprint Planning?
a. None
b. Having the Product Backlog items clearly described and assigned to developers
c. Having the requirements specified and completely reflected in the Product Backlog
d. Having the items at the top of the Product Backlog small enough to fit into one Sprint
5- How much time should a Product Owner spend with the Developers?
a. FALSE
b. TRUE
7- The performance of the project should be measured at least __.
a. Once a day
b. Once per Sprint
c. Once a week
d. Before or after each release
8- Which element is NOT an attribute of Product Backlog items?
a. Description
b. Order
c. Owner
d. Estimate
9- Which of the following is correct about Developers?
a. They are accountable for maximizing the value of the work of the Developers.
b. They are accountable for maximizing the value of the product.
c. They measure the progress of Sprints.
d. They are accountable for all changes to the Product Backlog.
10- Which of the following describes the relationship between the Product Backlog and changes in the project environment?
a. TRUE
b. FALSE
14- There's a Scrum project that is supposed to have two releases: one in the middle and the other at the end of the
project. Which of the following statements is correct about this project?
a. Increments are created for investigation and adaptation; they don't have to be releasable.
b. All increments should be releasable.
c. Increments that are created before each release should be releasable.
d. Having releasable Increments depends on the preference of the operations'.
15- How is budgeting done in Scrum?
a. It's about dedication, and the intent and effort put into work.
b. It's about delivering all the items in the Sprint Backlog.
c. It's about achieving the result that you have committed to.
18- Which TWO statements best describe the Product Backlog?
a. FALSE
b. TRUE
24- Which of the following is NOT required by Scrum?
a. Release planning
b. Definition of Done
c. Sprint Retrospectives
d. Having timeboxed events
25- True or false? The Product Owner is the equivalent of project manager in Scrum.
a. TRUE
b. FALSE
26- When does a Product Owner cancel a Sprint?
a. When the forecast shows that we can't finish many of the items in the Sprint Backlog
b. When not enough information is available for the items in the Sprint Backlog
c. When the Sprint Goal becomes obsolete
d. When not enough resources are available for the project
27- True or false? Sprints can be cancelled only when no item is Done yet.
a. TRUE
b. FALSE
28- Which artifact contains a plan for realizing the Sprint Goal?
a. Product Backlog
b. Product vision
c. Sprint Backlog
d. Sprint Goal itself
29- The Developers are ready to start the first Sprint, but the Product Backlog is not yet ready. What should the Product
Owner do?
a. Ask the Developers to help you refine the Product Backlog instead of starting the first Sprint.
b. Let the Sprint begin, but only with the goal of completing the Product Backlog.
c. Let the team start the first Sprint, and continue refining the Product Backlog.
30- The Product Owner has some concerns about the Definition of Done. What should they do?
a. Cancel the Sprint Planning meeting, give them some time to prepare, and then hold another Sprint Planning.
b. Extend the duration of Sprint Planning and ask them to discuss the items more and reach agreement.
c. Ask the Developers to come up with their best guess and don't worry too much about their capacity.
d. Cancel the Sprint and start the next one when the items are clear.
32- Which of the following actions may a Scrum Master take in starting up a project?
a. FALSE
b. TRUE
34- Which of the following can be included in the Sprint Backlog?
a. Use Cases
b. User Stories
c. Tasks
d. All of these choices, and probably others!
e. Tests
35- Who does all the work required for Product Backlog items, to make sure they are usable?
a. Sprint Review
b. Sprint Planning
c. Sprint Retrospective
d. Product Backlog refinement
37- True or false? The Product Owner is the main person responsible for engaging the stakeholders.
a. TRUE
b. FALSE
38- True or false? It's up to the self-managing team to decide which Scrum artifacts are needed in the project.
a. FALSE
b. TRUE
39- True or false? The Developers are responsible for composing the Definition of Ready.
a. FALSE
b. TRUE
40- True or false? The Sprint Backlog is baselined at the end of Sprint Planning.
a. FALSE
b. TRUE
41- True or false? The Definition of Done can change during the project.
a. TRUE
b. FALSE
42- Which TWO of the following are outcomes of Daily Scrums?
a. FALSE
b. TRUE
47- True or false? Having the team members and a complete Product Backlog are the only things needed to start
the project.
a. FALSE
b. TRUE
48- Which TWO of the following are required by Scrum?
a. Burn-down charts
b. Sprint Retrospectives
c. Product Backlog refinement
d. Having full-time developers
e. Test-Driven Development
49- What happens between two Sprints?
a. TRUE
b. FALSE
52- True or false? The first Sprint can start as soon as the Product Backlog is complete.
a. TRUE
b. FALSE
53- What happens between a Sprint Retrospective and the next Sprint Planning meeting?
a. TRUE
b. FALSE
55- Which TWO of the following should NOT change during the Sprint?
a. Sprint Backlog
b. Product Goal
c. Minimum level of quality
d. Product Backlog
56- The Developers have realized that one of the planned works in the Sprint Backlog is not needed anymore.
What should they do?
a. Cancel the Sprint Planning meeting, give them some time to prepare, and then hold another Sprint Planning.
b. Extend the duration of Sprint Planning and ask them to discuss the items more and reach agreement.
c. Ask the Developers to come up with their best guess and don't worry too much about their capacity.
d. Cancel the Sprint and start the next one when the items are clear.
58- Which statement is NOT correct about Daily Scrums?
a. TRUE
b. FALSE
60- True or false? The Product Backlog only contains functional features, not non-functional features.
a. FALSE
b. TRUE
61- Who is responsible for explaining the Product Backlog items?
a. The Developers self-manage and talk to anyone necessary to find out what the items mean.
b. Product Owner
c. User representative(s)
d. Scrum Master
e. Customer
62- Which THREE statements best describe the Product Backlog?
a. FALSE
b. TRUE
64- Which TWO statements are correct about the number of Product Owners when there are three products being
developed using Scrum?
a. Transparency
b. Creativity
c. Collaboration
d. Value optimization
e. Adaptation
f. Inspection
66- When is user acceptance testing done?
a. What work am I going to do today to help the team achieve its goal?
b. How many hours did I spend on the project yesterday?
c. What is the progress of the Sprint?
d. What impediments are in my way or in the way of the team?
e. What work did I do yesterday to help the team achieve its goal?
f. What problems did I have yesterday?
71- True or false? The satisfaction of the end-users is more important than the satisfaction of the customer.
a. FALSE
b. TRUE
72- True or false? Scrum is a process for developing complex products.
a. FALSE
b. TRUE
73- What's the recommended number of Scrum Team members?
a. 4 to 12
b. 10 or less
c. 3 to 12
d. 3 to 10
e. 3 to 11
74- True or false? All items in the Product Backlog should be small.
a. TRUE
b. FALSE
75- How would you know whether a Scrum Team is cross-functional?
a. When the forecast shows that we can't finish many of the items in the Sprint Backlog
b. The customer doesn't have the authority to cancel the Sprint.
c. When not enough resources are available for the project
d. When not enough information is available for the items in the Sprint Backlog
77- Who can attend the Daily Scrum meeting?
a. Anyone
b. The Developers and the Scrum Master
c. The Developers
d. The Developers and the Product Owner
78- Which TWO of the following are correct about Developers?
a. It's a demo at the end of the Sprint for everyone in the organization to see the Increment.
b. It's an inspection of the Increment to collect feedback and see what to do in the next Sprint.
c. It's a meeting to receive the formal approval of the customer for the Increment.
d. It's a controlling mechanism for evaluating the work of developers.
80- Which of the following is a valid service from a Scrum Master to a Product Owner?
a. Help the Product Owner find techniques for managing the Product Backlog.
b. Help the Product Owner order the Product Backlog items in order to maximize value.
c. Act as the middleman between the Product Owner and the Developers, as requested or required.
d. Act as a proxy when the Product Owner is not available to the team.