Professional Documents
Culture Documents
1
1. SELECTION OF ALTERNATIVES
The main purpose of economic analysis is to help design and select projects that
contribute most to the national income of a country
The project design, therefore, should be compared with various other designs involving
differences in such important aspects as the scale of the project, the choice of beneficiaries,
the types of outputs and services, the production technology, location, etc.
The project should also be compared with the alternative of not doing it at all.
When used solely, economic analysis serves only a very limited purpose and hence should
not be the only base for decision. B/S economic viability will be undermined if financial
viability is not ensured 2
2. Identification of winners and losers
o A good project contributes to the country’s economic output it has the potential to make
everyone better off.
o Identifying those who will gain, those who will pay and those who will lose gives the
analyst insight into the incentives that various stake holders have to see that the project is
implemented as deigned.
3
3. Fiscal impact
• How and to what extent will the costs of the project be recovered from its beneficiaries?
• What changes in public expenditures and revenues will be attributable to the project?
4. Environmental impact
o In economic analysis, the externalities of a project on the environment should be
considered and, if possible, quantified and assigned a monetary value.
4
2. Numeraire
o One of the important aspects of economic pricing is the determination of the numeraire, the
o The choice of currency and price level in which to conduct the analysis must be decided
first.
o Financial analysis is usually conducted in the currency of the country undertaking the
o Economic analysis can be conducted in domestic with domestic market price or foreign
5
6
6.3. VALUATION AND SHADOW PRICES
THE VALUE OF INPUTS USED UP (COSTS) AND OUTPUTS PRODUCED (BENEFITS) OF A
PROJECT DEPEND ON
• VALUE JUDGMENTS BY GOVERNMENT, AS WELL AS
• ON TECHNICAL AND BEHAVIORAL PARAMETERS AND
• ON THE RESOURCE AND POLICY CONSTRAINTS.
• VALUE JUDGMENTS BY THE GOVERNMENT DETERMINE THE WEIGHT TO BE GIVEN
• TO FUTURE CONSUMPTION RELATIVE TO PRESENT CONSUMPTION: THAT IS,
TO GROWTH AS AGAINST PRESENT CONSUMPTION,
• TO BENEFITS FOR DIFFERENT CLASSES OF INCOME RECIPIENTS OR
DIFFERENT REGIONS; AND
7
8
6.4. ECONOMIC AND SOCIAL COST BENEFIT ANALYSIS
• A PROJECT WILL BE PROFITABLE TO SOCIETY:
• IF THE ECONOMIC/ SOCIAL BENEFITS OF THE PROJECT EXCEED THE ECONOMIC/ SOCIAL COSTS
• OR IF THE NET PRESENT VALUE OF THE PROJECT TO SOCIETY IS GREATER THAN ZERO.
9
6.5. APPROACHES OF MEASURING ECONOMIC COSTS & BENEFITS OF A
PROJECT
THERE IS CONCEPTUAL DIFFERENCE BETWEEN SOCIAL COSTS -
BENEFITS AND ECONOMIC COST - BENEFIT ANALYSIS.
THE RESULTS OF SOCIAL COST-BENEFIT ANALYSIS MAY DIVERGE FROM
THE RESULTS OF ECONOMIC COST-BENEFIT ANALYSIS.
BENEFITS OF A PROJECT.
• IF THE MARKET PRICES ARE ADJUSTED ONLY FOR MARKET
DISTORTIONS OF VARIOUS KINDS; DIRECT TRANSFER PAYMENTS &
EXTERNALITIES, IT IS SIMPLY ECONOMIC COST-BENEFIT ANALYSIS.
BUT, IF THE COMMODITIES ARE NON-TRADED, AND IF THE MARKET PRICES ARE GOOD
ESTIMATES OF OPPORTUNITY COST OR WILLINGNESS TO PAY,
13
BUT IF THE PRICES OF NON-TRADED ITEMS (GOODS AND SERVICES OR
FACTORS OF PRODUCTION) ARE DISTORTED,
• SER - IS THE SHADOW EXCHANGE RATE (ASSUMING THE OFFICIAL EXCHANGE RATE DOES
NOT ACCURATELY REFLECT THE TRUE VALUE OF FOREIGN CURRENCIES TO THE ECONOMY).
15
SHADOW EXCHANGE RATE
THE NEED TO DETERMINE THE FOREIGN EXCHANGE PREMIUM ARISES BECAUSE IN MANY
COUNTRIES, AS A RESULT OF NATIONAL TRADE POLICIES (INCLUDING TARIFFS ON IMPORTED
GOODS & SUBSIDIES ON EXPORTS), PEOPLE PAY A PREMIUM.
• THIS PREMIUM IS NOT ADEQUATELY REFLECTED WHEN THE PRICE OF TRADED GOODS ARE
CONVERTED TO DOMESTIC CURRENCY EQUIVALENT AT THE OFFICIAL EXCHANGE RATE.
16
• THE PREMIUM, THUS, REPRESENTS THE ADDITIONAL AMOUNT THAT USERS OF TRADED
GOODS ARE WILLING TO PAY TO OBTAIN ONE MORE UNIT OF TRADED GOODS.
Pd
SER
Pw
n
Pdi
SER f i
i1 Pwi
fi -the weight of the ith good
18
THE WEIGHTS (FI) ARE A FUNCTION OF THE QUANTITIES IMPORTED AND EXPORTED
AND OF THE ELASTICITIES OF DEMAND FOR THE VARIOUS IMPORTS AND THE
ELASTICITIES OF SUPPLY FOR THE VARIOUS EXPORTS.
19
Where
f im
- is weight of the ith import good
PEDI - ISx PRICE ELASTICITIES OF DEMAND OF THE ITH IMPORT
fi -is weight of the i export good
th
20
6.5.2. LITTLE-MIRRLEES APPROACH(BORDER PRICE)
• IT WAS THOUGHT THAT IF A PROJECT WAS
WORLD
ANALYZED
PRICES,
ATTHIS WOULD GIVE AN
INDICATION
FIRST OF WHETHER IT COULD SURVIVE IN THE LONG TERM IN THE FACE OF
INTERNATIONAL COMPETITION, AND
21
• IF WORLD PRICES ARE USED, THE ECONOMIC PRICE AT WHICH TO VALUE A PROJECT’S
OUTPUT IS
23
SO THE ECONOMIC PRICE FOR A NON-TRADED GOOD IS
• IN PRINCIPLE, TO FIND THE WORLD PRICE OF NON- TRADED GOODS, EACH GOOD
COULD BE DECOMPOSED INTO ITS TRADED AND NON-TRADED COMPONENTS IN
SUCCESSIVE ROUNDS
24
• THE DERIVATION IS AS FOLLOWS:
25
1
SCF
Pd
Pw OER
IS THE SHADOW EXCHANGE RATE I.E., THE PRICE OF GOODS IN DOMESTIC CURRENCY
RELATIVE
P TO THEIR WORLD PRICES
d
Pw
1 1
• SCF SHADOW PRICE
IS THE OF FOREIGN EXCHANGE (PF)
SER PF
OER
SER
OER
26
• WHERE FI - WEIGHTS FOR THE ITH COMMODITY
27
• TAKING THE FOLLOWING EXAMPLE CAN SUMMARIZE
LITTLE-MIRRLEES APPROACH OF ADJUSTING DOMESTIC
PRICES INTO ECONOMIC PRICES.
• A PROJECT THAT PRODUCES EXPORT GOODS CAN BE ASSESSED AS FOLLOWS:
EXCHANGE RATE.
29
6.7. VALUATION OF NON-TRADED GOODS
• NON-TRADABLE ITEMS ARE THOSE WHICH ARE NOT TRADED
INTERNATIONALLY.
• THEY INCLUDE ITEMS SUCH AS:
GOODS WITH VERY HIGH TRANSPORTATION COSTS SUCH AS GRAVEL; AND COMMODITIES
PRODUCED TO MEET SPECIAL CUSTOMS OR CONDITIONS OF THE COUNTRY.
• IF DETERMINATION OF PRICE TAKES PLACE IN THE WORLD MARKET, THE GOOD
SHOULD TRADABLE.
BE CONSIDERED
• IF THE SETTING OF THE PRICE TAKES PLACE BY SUPPLY AND DEMAND IN THE
LOCAL MARKET, THE GOOD SHOULD BE CONSIDERED NON-TRADABLE.
31
VALUATION OF NON TRADED GOODS WILL MAINLY DEPEND ON SUCH FACTORS
AS:
QUANTITY OF INPUT DEMANDED AND OUTPUT SUPPLIED
ELASTICITY OF DEMAND AND SUPPLY
MARKET IMPERFECTIONS;
GOVERNMENT INTERVENTION OF DIFFERENT KINDS;
TAXES AND SUBSIDIES THAT ARE TARGETED TO COMPENSATE
EXTERNAL COSTS
(OR BENEFITS) AND
OTHER INDIRECT TAXES, SUBSIDIES AND PRICE CONTROLS TARGETEDFOR SOME
OTHER PURPOSES.
32
6.8. VALUING OUTPUT USING MARKET PRICES
• THE WILLINGNESS TO PAY FOR THE OUTPUT OF THE PROJECT MAY BE
MEASURED BY THE MARKET PRICE PROVIDED THE FOLLOWING
CONDITIONS ARE SATISFIED:
1. THERE IS COMPETITIVE BUYING IN THE MARKET PLACE
34
6.9 VALUING NON-TRADED INPUTS
• THERE ARE THREE IMPLICATIONS OF USING INPUTS IN A PROJECT.
FIRST, THE MARKET PRICE OF THE INPUT MAY RISE AS A RESULT OF THE INCREASE IN
DEMAND FOR THAT INPUT.
SECOND, OTHER CONSUMERS OF THE INPUT MAY WIND UP USING LESS OF IT
BECAUSE THE PROJECT HAS TAKEN SOME OF THE INPUT OUT OF THE MARKET.
THIRD, PRODUCERS OF THE INPUT MAY MAKE MORE OF IT TO COVER THE
ADDITIONAL DEMAND OF THE PROJECT1
35
• THE RELATIVE SIZES OF DECREASED PRIVATE CONSUMPTION AND
INCREASED PRODUCTION WILL DEPEND ON THE RELATIVE
ELASTICITIES OF SUPPLY AND DEMAND.
• BOTH THE DECREASE IN PRIVATE CONSUMPTION AND THE INCREASE
IN PRODUCTION OF THE INPUT ARE COSTS OF THEPROJECT.
• THE DECREASE IN PRIVATE CONSUMPTION IS A COST BECAUSE
INDIVIDUALS WILL BE CONSUMING LESS OF A GOOD OR SERVICE
THEY DESIRE.
• THE INCREASE IN PRODUCTION IS A COST BECAUSE PRODUCTIVE
INPUTS WILL BE SHIFTED FROM OTHER ACTIVITIES TOWARD
36
REGULATION.
THEIR DOMESTIC PRICE MAY WELL RISE HIGH ABOVE THE PREVAILING
PRICE ON THE WORLD MARKET.
38
• IF THE QUESTION WERE TO EVALUATE WHETHER THESE
ITEMS SHOULD BE TRADED FREELY OR NOT,
PRICE.
6.11. VALUING EXTERNALITIES
• THE FINANCIAL COSTS OF THE PROJECT WILL
NOT INCLUDE THE COSTS OF THE EXTERNALITY
• HENCE, AN EVALUATION OF THE PROJECT
BASED ON PRIVATE MARGINAL COST (PMC) WILL
UNDERSTATE THE SOCIAL COSTS OF THE PROJECT &
OVERSTATES ITS NET BENEFITS.
METHODS
• SEVERAL METHODS ARE AVAILABLE TO VALUE ENVIRONMENTAL
EXTERNALITIES.
• SOMETIMES A PROJECT USES RESOURCES WITHOUT PAYING FOR THEM.
• FOR EXAMPLE A FACTORY MAY EMIT SOOT THAT DIRTIES
SURROUNDING BUILDINGS, INCREASING THEIR MAINTENANCE COSTS.
EXTERNALITIES.
47
METHODS FOR MEASURING ENVIRONMENT RESOURCE VALUES
ARE:
1 DIRECT METHODS:
.
MARKET PRICE
CONTINGENT VALUATION
2. INDIRECT METHODS:
TRAVEL COST
HEDONIC PROPERTY VALUE
HEDONIC WAGE VALUES
AVOIDANT EXPENDITURES
CONTINGENT RANKING
48
1. DIRECT METHODS:
49
• MORE COMPLICATED VERSIONS ASK WHETHER THE RESPONDENT WOULD PAY $X TO
PREVENT
COST OR THE
OBTAINING
EXTERNAL
THE BENEFITS.
• THE ANSWER MAY REVEAL FAIR ESTIMATE OF EXTERNAL COSTS AND BENEFITS IF THE
SURVEY IS MANAGED CAREFULLY.
50
2. THE DIFFICULTY IN ASSURING THE RESPONDENTS HAVE UNDERSTOOD OR ABSORBED
THE ISSUES IN THE SURVEY; AND
51
2. INDIRECT OBSERVABLE METHODS –
THESE ARE BASED ON OBSERVABLE BEHAVIOR
BECAUSE THEY INVOLVE ACTUAL (AS OPPOSED TO
HYPOTHETICAL) BEHAVIOR, AND
THEY ARE INDIRECT BECAUSE THEY INFER A VALUE
RATHER THAN ESTIMATE IT DIRECTLY.
a) TRAVEL COST METHODS:
• THIS ALLOWS THE ANALYST TO SEPARATE OUT THE RELATIONSHIP BETWEEN PROPERTY
VALUES AND POLLUTION.
53
THIS RELATIONSHIP CAN THEN BE USED TO PRODUCE A WILLINGNESS TO PAY
FOR POLLUTION REDUCTION.
54
d)AVOIDANCE EXPENDITURES :
• THESE ARE EXPENDITURES THAT ARE DESIGNED TO REDUCE
THE DAMAGE CAUSED BY
POLLUTION BY TAKING SOME KIND OF AVERTING OR DEFENSIVE ACTION.
• AN EXAMPLE WOULD BE
TO INSTALL INDOOR AIR PURIFIERS IN RESPONSE TO POLLUTED AIR OR
TO RELY ON BOTTLED WATER AS A RESPONSE TO THE POLLUTION OF LOCAL DRINKING
WATER SUPPLIES,
BUYING ‘TENTS’ TO PROTECT ONESELF FROM MOSQUITO CAUSING MALARIA, ETC.
SINCE PEOPLE WOULD NOT NORMALLY SPEND MORE TO PREVENT A PROBLEM
THAN WOULD BE CAUSED BY THE PROBLEM ITSELF
• AVERTING EXPENDITURES CAN PROVIDE A LOWER BOUND ESTIMATE OF THE
DAMAGE CAUSED BY POLLUTION
55
d)CONTINGENT RANKING:
• IN THIS METHOD RESPONDENTS ARE GIVEN A SET OF HYPOTHETICAL SITUATIONS THAT
DIFFER IN TERMS OF ENVIRONMENTAL AMENITIES (PLEASANTNESS) AVAILABLE AND
OTHER CHARACTERISTICS THE RESPONDENTS ARE PRESUMED TO CARE ABOUT,
AND ARE ASKED TO RANK THESE SITUATIONS IN TERMS OF THEIR
DESIRABILITY.
THESE RANKINGS CAN THEN BE COMPARED`THE
TO SEE
IMPLICIT TRADE OFFS
BETWEEN MORE OF THE ENVIRONMENTAL AMENITY AND LESS OF THE OTHER
CHARACTERISTICS
EXAMPLE: THESE CHARACTERISTICS COULD BE AN INCREASE IN PRICE RELATED
TO THE PRODUCT OR LOSS IN SOME BENEFITS RELATED TO IT.
56
6.11.2. VALUING HUMAN LIFE
• EXAMPLE:
• IF EACH PERSON IS WILLING TO PAY, SAY BIRR 5, FOR THIS RISK REDUCTION,
THEN THE IMPLIED VALUE OF A LIFE IS APPROXIMATELY BIRR 1.5 MILLION. 58
• 10-6.67=3.33 TOTAL REDUCTION IN DEATH PER MILLION PEOPLE
PREMATURE MORTALITY.
• THE DIFFICULTY ARISES WHEN COMPARING ESTIMATES BETWEEN COUNTRIES WITH
• ALTHOUGH MOST ECONOMISTS DO NOT FAVOR USING THIS METHOD FOR PROJECT
STATISTICAL LIFE,
VALUE.
CHAPTER 7
61
• When costs and benefits have been identified,
quantified and priced (valued), the analyst is trying to
determine
which among various projects to accept, which to reject.
• There are two methods for measuring the worthiness of
projects:
1. undiscounted & 62
• The arithmetic of these methods, and the way we interpret
the measures and their limitations, is exactly the same
63
• There are two critical points important to note
1. there is no one best technique for estimating project worth;
each has its own strength & weakness.
2. these financial and economic measures of investment worth
are only tools of decision-making,
i.e., they are necessary conditions & are not sufficient
64
The most used non-discounted measures of project
worth are
1. Ranking by inspection
2. Payback period
3. Return on investment
65
Here by simply looking at the investment costs and the
‘shape’ of the stream for the net value of incremental
production that one project should be accepted over another
if we must choose.
66
• The analyst can sometimes simply choose one project among
alternative projects by examining the following:
Total cost of investment and investment period;
The structure, & amount of costs and benefits;
total amount of the net incremental benefit;
The lifetime of the project, etc. 67
• If two projects have the same initial investment, and different
lifespan, the same proceeds throughout the period of the short-
lived investment, and if the long lived investment to earn
income after the end of the short-lived one, then, the long-lived
one is more desirable
Because all things being equal, the long-lived project
68
•Suppose two projects have the same life period,
identical initial investment outlay, and the net proceeds
throughout the life period is identical; in this case
although the total net proceeds is identical, the project
that earns more income early than the other is more
desirable.
•The problem with Ranking by inspection
method is that the selection lacks objectivity.
69
• The payback period is the length of time from the beginning
of the project until the sum of net incremental benefits of
the project equal to total capital investment.
70
• This method has two weaknesses:
1. it fails to consider the time & amount of net benefits
after the payback period.
71
Alternative Year Investment cost Net incremental
projects benefits
I 1 20000 -
2 2000
3 8000
4 12000
5 9000
II 1 20000 -
2 200
3 12000
4 8000
5 12000
III 1 20000 -
2 1000
3 5000
4 6000
5 8000
6 10000
7 5000
8 2000 72
• Project I & II have a payback period of 4 year.
• But project III has a payback period of 5 years.
• Thus, based on this criterion, project I & II have equal
higher rank than project III.
Therefore, the method fails to consider the time & amount of
net incremental benefit after the payback period- project III.
In addition, the method results equal rank for both project I
and II.
73
Yet we know by inspection that we would choose
project II over project I because more of the returns to
project II are realized earlier.
75
Investment Cost ($) Average Average Ranking
income($) income on
Cost (%)
A 20,000 0 0 4
B 20,000 660 3.3 3
C 20,000 800 4 1
D 20,000 800 4 1
76
Average income on cost has the disadvantage of not
taking into consideration the timing of the cash flow.
77
Thisis the ratio of average income to the book value of the
assets (i.e. the value after subtracting depreciation) stated in
percentage terms.
79
Proje ct Average net value Annual Net Average Average
of incremental deprecat average book value income on
benefit ion income book value(%)
80
Time value of money
• Present values are better than the same values in the future and
earlier returns are better than later.
• This shows that money has time value.
• Thus, to include the time dimension in our project evaluation, we
have to use discounting methods.
81
• Discounting is essentially a technique that ‘reduces’ future
benefits and costs to their ‘present worth’.
82
• Suppose a bank lends 1567.05 Birr for a project at 5%
interest rate.
• The project owner is supposed to repay the principal &
interest rate after 5 years.
• How much the owner will have to pay at the end of 5 years?
83
At = P(1 + r) t
At = total amount after t years
r = interest rate
t = time
P=Principal
A5 = 1567.05 (1 +
0.05)5
= 2000 Birr
84
• Suppose again a project is expected to obtain 2000
Birr after 5 years.
• Value of this money today can be calculated as:
At 2000
1567 . 05
P
1 r t
1 0 . 05 5
85
• The undiscounted measures of project worth have one
serious shortfall:
86
• By contrast discounted measures of project worth are based
on the concept that” to receive some today is better than to
receive more tomorrow”
• Commonly used discounted measures are:
Net Present Value
Internal Rate of Return
Benefit- Cost Ratio
Net Benefit - Investment Ratio
87
• It is the present value of expected future net cash flows, discounted at
the costs of capital, less the initial outlay.
n
NPV At t
t 1 1 r I
NPV - net present value
At = net cash flow for the year t
r - cost of capital
n- life of the project
I- initial outlay 88
•In the net present value method, the higher the
NPV, the more desirable the project is.
•
All projects that have a positive NPV are accepted and
projects that have a negative NPV are rejected.
89
However, in ranking mutually exclusive project (if one
is chosen, the other cannot be undertaken), ranking based on
NPV depends on the dissonant rate used.
90
Discounted measure of project worth based on discounted
91
• The internal rate of return is the rate of discount at which the total
discounted cash proceeds( benefits) expected from the project equals the
total discounted cash outlays (costs) required by investment.
In other words, the IRR is the rate which makes NPV of the project
equal to zero
92
n
At
I 1 r t
T 1
I –
investment
cost
At – Net benefit for year t
r - IRR
n - Life of the project
93
Illustration: For a project with investment cost of 1000 and net cash
flow of 200,400, 500 and 700 for four consecutive years, IRR is
formulated as
200 400 500 700
1000
1 r 1
1 r 2
1 r 3
1 r 4
94
• When r = 23.068 percent the value in the above
equation in the right hand side will be equal to
1000.0087 which is equal to the value in the left hand
side.
95
• The procedure to find r can be described as follows:
1. Select an arbitrary value of r;
2. Calculate the value of the right hand side equation with this
value of r.
3. If the RHS value is lesser than the value in the left hand,
reduce the value of r.
4. If the RHS is greater than the LHS, increase the value of r;
continue until this the RHS is very close to the LHS.
5. When the RHS is more or less equal to LHS, it is that value
of r, which is the IRR.
96
When using the IRR, the investment criterion is
that the IRR should be greater than the discount rate.
97
• Generally, for one single project, there is a relationship b/n the
present value, the rate of return, the cost and benefits
98
• When NPV is equal to zero, then
the IRR is equal to the rate of discount and discounted benefits
are equal to the discounted costs; and
100
BENEFIT-COST
Where RATIO…
Bt - are the benefits in period t
Ct - are the costs in period t
n - project life
r - discount rate
101
• The selection criterion for the benefit-cost ratio measure
of project worth is that
the discounted benefits should exceed discounted costs i .e
102
• It is suitable and convenient for ranking projects especially
when sufficient budget is not available to implement all
projects that satisfy other criteria.
That is, two or more projects may all have a positive NPV,
IRR that exceeds the discount rate, both financial and
economic discount rates, and a benefit-cost ratio of greater
than one.
103
• In this case, ranking could be made using net Benefit -
investment ratio.
n
( Bt Ct
Net benefit - investment ratio =
(1 r ) t
t1
n
I (1 r ) t
t 1
Where - Bt Benefits, Ct - costs, I- investment, r-discount rate, I-investment cost
104
• It is simply the present value of net benefits divided by the net
present worth of the investment.
105
The above measures of project worth may give different
ranking in different measures if projects that are being
compared are different in their:
1. Cash flow structure
3. Life time
106
1. Cash flow structure
Some projects may give high return in the early stage
of the project & decline thereafter & some other projects
may give lower return in the early stage & grow later in
the life of the project.
The former will be less sensitive to changes in discount
factor as compared to the latter.
Therefore, the ranking could be different in different
measures.
107
2. Magnitude of costs and benefits
For some projects the costs & benefits could be large in magnitude than
other projects. in this case ranking based on NPV & IRR may not give same
result.
3. Life time
Some projects have shorter life than others.
108
• If a firm or government has unlimited funds, which is rare
in reality, these differences have no significant implication
in the decision.
In such cases, projects with a positive NPV, the IRR value of
109
• However, if there is limited funds, as is often the case,
and if different criterion gives rise to different results,
a decision must be made as to which criterion to use
for selection.
Which criterion is then more appropriate to select
among such mutually exclusive projects?
110
Mutually exclusive projects
Two projects could be mutually exclusive (implementing
112
113
THANK 114
ASSIGNMENT- THIS IS A REQUIREMENT TO
COMPLETE THE COURSE.
• PLEASE IDENTIFY ANY PROFIT ORIENTED PROJECT IDEA AND PREPARE A COMPLETE PROJECT
PROPOSAL. THE PROJECT PROPOSAL SHOULD INCORPORATE ALL ASPECTS OF PROJECT
PREPARATION AS MUCH AS POSSIBLE.
• NB: THE LIFE OF THE PROJECT SHOULD NOT BE LESS THAN 7 YEARS AND THE PROPOSAL
SHOULD CLEARLY SHOW THE PAYBACK PERIOD, NPV, BCR AND IRR. (USE R=14)
115