Project Management Lecture

Project Scheduling (2)

Ayanda Pekane

Department of Information Systems

Department of Information Systems


Project Schedule (Gantt Chart)
• Allocate Team members to activities
• Estimate Work activities
• Gantt Chart method or technique
A Gantt chart technique provides a standard time format for
displaying project schedule information by listing project
activities and their corresponding start and finish dates in
calendar format.
• Communicate progress

Department of Information Systems


Estimation Techniques

• Analogous estimating (similar project


estimation)
• Parametric estimating (historical data
estimation)
• Delphi technique (the expert)
• Bottom up (small to big)
• PERT (most optimistic and pessimistic)

Department of Information Systems


Kloppenborg, Contemporary Project Management, 4th Edition. © 2019 Cengage. All Rights Reserved. May not be scanned, copied
or duplicated, or posted to a publicly accessible website, in whole or in part.
Develop a Gantt Chart

Department of Information Systems


Critical Path Method (CPM)

• The first major task in developing the


project schedule is to identify the critical
path,which is “the sequence of activities
that represents the longest path through
the project, which determines the shortest
possible duration.
• Predict the total duration of the project

Department of Information Systems


Determining the Critical Path for Project X

7
Simple Example to Determine the
Critical Path

C=2 4 E=1
A=2 B=5
start 1 2 3 6 finish

D=7 5 F=2
a. How many paths are on this network diagram?
b. How long is each path?
c. Which is the critical path?
d. What is the shortest amount of time needed to complete this project?

Department of Information Systems


Program Evaluation and Review
Technique (PERT)

Department of Information Systems


PERT Formula and Example

Department of Information Systems


Gantt Chart

Department of Information Systems


Lets get to work!

• Project Charter of your project has been


approved
• Create your high level project schedule
• Deliverables and tasks are clearly defined
• Step 1: Create a PBS for the project
• Step 2: Create a WBS
• Step 3: Create a network diagram

Department of Information Systems


Product Breakdown Structure

Department of Information Systems


Work Breakdown Structure

Department of Information Systems


Network Diagram

Department of Information Systems


End!