Professional Documents
Culture Documents
CC5001 Week 6 Planning 2012 13
CC5001 Week 6 Planning 2012 13
Completion
Planning Stage
Inputs
Why plan?
The planning process Objectives Work Breakdown Structure Estimating Scheduling Outputs
Inputs
Feasibility report
Project objectives & scope
Inputs
Authorisation to proceed to next stage
client organisations
Project manager also signs to confirm acceptance of
Why plan?
Proactive rather than reactive
Who does what, when and how? What resources are required and when?
Why plan?
Planning has its own costs
Benefits must outweigh costs
Good planning will benefit the project
Why plan?
If we fail to plan
we plan to fail!
Planning stage:
Baseline plan what, when and how things should be done what resources are required
Completion stage:
Plans provide a basis for final evaluation
Objectives
Clear project objectives are vital to planning
Allow success of the project to be evaluated Enable priorities to be set Enable conflicts to be resolved Provide direction and motivation Published so key stakeholders are aware of them Must be SMART
Objectives
S
M
= Specific and written down
= Measurable = Agreed, Aligned, Achievable = Realistic, Relevant = Time-framed
A
R
Objectives
Some examples:
Increase UK sales volume of ring binders by 5% by 30 June 2013
the objective is: specific and written down measurable increase UK sales volume of ring binders by 5% achievable by the staff concerned, agreed by those involved, aligned to the requirements of the organisation relevant to organisations sales targets, realistic in terms of outlets time-framed by 30 June 2013
Objectives
Some examples:
Reduce staff absenteeism in SE department by 30% by 31 Dec 2013
the objective is: specific and written down measurable reduce staff absenteeism in SE dept by 30% achievable by the staff concerned, with health awareness courses, agreed by those involved, aligned to the requirements of the organisation relevant to the work of the organisation, realistic in terms of health care provision time-framed by 31 December 2013
Objectives
Some examples:
Hand in CC5001 assignment to UG Office by week 20
the objective is: specific and written down measurable hand in CC5001 assignment to UG Office achievable by students concerned, with lectures and seminars, agreed by academic & admin staff, aligned to the requirements of the module relevant to the work of the module, realistic in terms of lecture schedule time-framed by week 20
SMART Objectives
Caution:
We do NOT have separate objectives for each element
there is not a measurable objective, a realistic objective, etc.
activities
Each activity broken down into individual tasks
WP 1
WP 2
WP 3
WP 4
Activity 1.1
Activity 1.2
Activity 1.3
Activity 1.1
Task 1.1.1
Task 1.1.2
Task 1.1.3
Task 1.1.4
WP 1
WP 2
WP 3
WP 4
Activity 1.1
Activity 1.2
Activity 1.3
Activity 4.2 Task 4.2.1 Task 4.2.2 Task 4.2.3 Task 4.2.4 Task 4.2.5
Be agreed
Estimating
Accurate & timely estimates crucial to
success of a project Accuracy of estimate linked to uncertainty Level of uncertainty must be documented Estimates must be constantly updated as new information becomes available
Estimating
Level of uncertainty depends on:
Quality of information available
Estimating
Factors in project estimate uncertainty:
Requirements change over time needs managing estimate revisions must follow immediately Complete tasks/activities left out of plan
Estimating
Estimates can be broken down into:
Cost
Effort Time (duration)
Resources
Estimating
If it takes 10 days for 1 person to dig a hole:
two people may complete the task in half the time needed by one person
...but 100 people trying to dig the hole may take longer than 10 days
getting in each others way not enough tools for everyone not enough room arguing about who does what...
Estimating
Planning meals: people/resources/time
if there is enough food for 12 lunches this would last one person every day for 12 days (providing the food doesnt go off!) or two people every day for 6 days or four people every day for 3 days or 12 people for one day (a party!) but there is not enough for 14 people on one day, and there is not enough for one person for 14 days
this hasnt included costs for storage, preparation, time for
preparation, freezing/thawing/cooking, effort in preparation (does it take 12 times longer to cook 12 meals than 1?), washing up, etc...
Estimating
Labour intensive projects: start with effort Cost, duration & resources then estimated
Estimating
WBS is a useful tool in estimating
Each task estimated separately
All task estimates give overall project estimate
Planning
Check suggestions for further reading Try out tasks (including past exam questions)
Further reading
Burke, R (2003) Project Management: Planning and Control
Techniques, Wiley Bentley C.(1997) PRINCE 2: A Practical Handbook, ButterworthHeinemann Central Computer & Telecommunications Agency (1997) PRINCE 2: An Outline, London: The Stationery Office Field M & Keller L (1998) Project Management, International Thomson Business Press Brooks F. (1995) The Mythical Man-Month (Anniversary Edition), Addison-Wesley