BREACHES
Summary
Forensic engineering analyses of the two breaches that resulted in the catastrophic
flooding of the Lower 9th Ward and adjacent areas shows that failure of the flood protection
structure (levee, floodwall, supporting sheet piles) was due primarily to multiple flaws and
defects embedded in this flood protection structure during its life-cycle. These flaws and defects
included those developed during the concept development (e.g. failure to recognize I-wall
tension gap), design (e.g. failure to properly evaluate soil conditions and characteristics),
construction (e.g. failure to drive sheet piling to depths sufficient to prevent excessive water
intrusion), operation (e.g. failure to provide adequate safe-guards to adjacent flood protection
structure during IHNC lock expansion activities), and maintenance (e.g. failure to respond to
early warnings of potential for excessive seepage). Hurricane Katrina provided a test of this
The available information indicates a high degree of correlation of the site clearing work
for the USACE Lock Expansion Project at the East Bank Industrial Area (EBIA) sites and the
two breach locations in the flood protection structure adjacent to the Lower 9th Ward. This
remediation work (removal of soils, formation of cavities, vibrations) very probably had
important effects on the soils relied upon to provide stability and protection for the flood
protection structure. Removal and disturbance of the surface soils overlying the permeable sub-
soils (marsh layers) would have facilitated the under seepage discussed in this Appendix. In
addition, removal of the soils on the canal side of the floodwall would have reduced the lateral
C.1
History of IHNC and East Bank Industrial Area
Since the founding of New Orleans by the French in 1718, a navigation channel between
the Mississippi River and Lake Pontchartrain had been proposed. This would allow intercoastal
commerce to connect with river and seaborne commerce (Figure C.1). The Port Authority of
New Orleans (established 1896) recognized that the problem with establishing a water link was
the fluctuating flow of the river and the difference in the elevations of the river and Lake
Pontchatrain. Thus, locks would be needed to control the flow between the river and the lake.
Figure C.1: Map of the City of New Orleans (1829, Historic New Orleans Collection)
C.2
In 1914 the Port Authority received authorization from the state legislature to locate and
construct a deep-water canal. The proposed canal would be 5.3 miles long and up to 1,600 feet
wide, located just downstream of the Army’s riverfront supply center (about 2 miles downriver
Construction of the IHNC was started in 1918 with the excavation necessarily proceeding
from the lake toward the river. Excavation work started with construction of parallel dikes on
either side of the canal so hydraulic fill could be placed behind the dikes. Hydraulic excavation
was used wherever possible to excavate the channel, when the materials were easily loosed.
Draglines were employed to scoop out the more resistant soils dragging it up onto the dikes
which were gradually built up to become permanent protective levees. Buried cypress stumps
slowed progress by jamming the suction dredges and stalling the dragline buckets. From the
outset, contractors battled the problems with stability of the canal slopes, as water and the soft
The canal excavation was completed in 1919 and work then shifted to the lock structure
located 2,000 feet from the Mississippi River at the south end of the canal (Figure C.2). Very
severe problems were encountered during construction of the IHNC locks due to slumping soils
and running sands (indicating high water conductivity and flow). Soil borings (Figure C.3)
disclosed the presence of extensive buried layers of “humus.” These layers existed to
penetrations exceeding 30 feet. These layers represented the layers of swamp (hard growth) and
marsh (soft growth) that had been buried with dredge spoil and fill imported to raise the ground
elevation.
C.3
Figure C.2: IHNC channel dimensions (USACE 1971)
Figure C.3: Soil borings performed in vicinity of IHNC lock disclose the presence of extensive
layers of buried “humus” underlying the east bank (present area of the Lower 9th Ward) (USACE
1971)
Upon completion, the Port Authority set about developing piers, docks and quays along
the INHC to increase cargo handling. The Port Authority also made available adjacent lands for
use by industries. Much of the area on the west side of the IHNC was built during World War II.
The eastern side was developed after the early 1950s (Figure C.4).
C.4
Figure C.4: IHNC 1964 (USACE photograph)
The gulf coast portion of the GIWW (Gulf Intracoastal Water Way) is a protected
shipping channel between Port Isabel, Texas and Apalachee Bay Florida. In 1944, under the
USACE authorization, the GIWW was rerouted to pass thorough the southern part of the IHNC
and tie in with the Mississippi River. The MR-GO and its tie-in with the GIWW were completed
in the 1960s. Thus, the IHNC became intimately connected with the Gulf of Mexico through the
hurricane Betsy in September 1965 when both sides of the IHNC in the vicinity of the Lower 9th
Ward experienced breaks (Figure C.5). Some 6,560 homes and 40 businesses were flooded in
water up to 7 feet deep on the west side of the IHNC. The east side of the IHNC also failed,
flooding the present Lower 9th Ward in water up to 9 feet deep (Figure C.6).
C.5
Figure C5: Hurricane Betsy flood inundation map (USACE 1965)
Figure C.6: Flooding east of IHNC – Lower 9th Ward following hurricane Betsy (USACE
photograph)
C.6
The USACE report on hurricane Betsy (1965) states that both internal levee failures and
overtopping along the IHNC occurred on both the west and east sides. No details concerning the
mechanisms of failure were provided. Following hurricane Betsy, the IHNC levees were
heightened using steel sheet piles and concrete I-walls in the 1980s and 90s.
By the late 1990s work was underway to expand the IHNC locks to relieve shipping
congestion and allow further expansion of the Port of New Orleans. Congress authorized the
study for the lock enlargement / replacement in 1956. The proposed new locks would require a
bypass channel that would be constructed at the East Bank Industrial Area (EBIA). The EBIA is
located in the Lower 9th Ward, west of the floodwall and east of the IHNC, between Florida
Available documentation indicates that the USACE purchased the EBIA site from the
Port of New Orleans in order to proceed with the bypass channel construction (Washington
Group International - WGI, “Project Work Plan, Project Site Development and Remedial Action
of East Bank Industrial Area, Inner Harbor Navigation Canal Lock Replacement Project,” report
to USACE, New Orleans District, 2000). WGI began working at the job site in January 2001.
C.7
The EBIA consists of 32 acres of former industrial sites previously leased from the Port
of New Orleans to private owners. The EBIA consisted of six facilities named for their former
occupants. These included (starting at the south) the International Tank Terminal, Saucer
Marine, Mayer Yacht – Distributors Oil, Indian Towing, McDonough Marine, and Boland
Marine.
At one time, underground storage tanks were located at both the Boland property and the
Saucer property. These tanks were reported to have been removed. The State of Louisiana listed
contacted the Louisiana Department of Environmental Quality and reported that the company
The EBIA had a long history spanning more than 4 decades of industrial use by marine
service and petroleum distribution companies. Purportedly, tenants contaminated the property as
a result of their industrial operations. Also of particular significance at the EBIA was the active
placement of construction materials (concrete rubble) and solid wastes (barges, metal turnings,
concrete blocks) to protect the properties from the effects of ship wakes. These two activities had
two primary impacts derived from the existence of hazardous constituents that could negatively
affect: 1) the environment at the time of construction, and 2) construction of the bypass channel.
To ameliorate these potential negative effects, the USACE New Orleans district
contracted with WGI to characterize and remediate the EBIA’s environmental contamination and
identify and remove construction materials likely to interfere with bypass channel construction.
For remediation, the specifications required the canal bank be excavated to a depth four
feet below the existing grade and fifteen feet from the edge of the water onto land. When
possible, the work was done during low tide to facilitate visual observation of the work. When
C.8
work was completed, the landside of these excavations became the ‘new’ shoreline. It is reported
by WGI (“Technical Completion Report,” 2005) that in the majority of cases the canal bank was
excavations to a deep as nine feet. The records provided by WGI indicate that a total of 12,259
tons of contaminated soils were removed from the Boland site and 35,636 tons of contaminated
In addition to removal of canal-side soils that had previously provided stability and
protection to the flood protection structure, numerous underground storage tanks and debris were
removed. At the Saucer site, large underground storage tanks had to be removed. In addition, a
buried railroad tank car required construction of a cofferdam so that the tank car could be filled
with air, floated free, lifted and transported from the site. At the northern Boland site, a wharf
extended along most of the IHNC. Following removal of the wharf materials, the piles
comprising the foundation were pulled and transported from the site.
Twelve abandoned barges were located on the EBIA site. Conditions of the barges ranged
from beached to completely sunken (embedded into the bottom). Ten of the barges were
removed from the southern Saucer site and two barges from the northern Boland site. WGI
completed its work, removed its equipment, and demobilized from the job site in May 2005.
The IHNC sits at the heart of the three main populated regions of New Orleans. As
shown in Figure C.8, a number of breaches developed along the IHNC during Hurricane Katrina,
contributing to the flooding of all three of the most heavily populated protected areas in this
event. This Appendix addresses the two breach locations on the east side of the IHNC adjacent to
C.9
Figure C.8: Map showing principal features of the protected areas in the New Orleans area (ILIT
2006)
These two breaches will be identified as the “North Breach” (approximately 100 feet
wide, south of Florida Avenue) and “South Breach” (approximately 1,000 feet wide, north of
North Clairborne Avenue). Figure C.6 shows the locations of the North and South Breaches – the
photograph was taken on 6 September 2005 (National Oceanic and Space Administration 2005).
C.7 shows a similar photograph taken about the same time from a different perspective showing
the breach sites at the Lower 9th Ward relative to the intersection of the MR-GO – GIWW and
IHNC.
C.10
Figure C.9: Aerial photograph of North Breach and South Breach sites taken 6 September 2005 (NOAA 2005). Postulated breach
initiation sites indicated. Note the USACE lock expansion site clearing ‘holes’ left immediately outside the floodwall protecting the
Lower 9th Ward (to top of photograph)
C.11
Figure C.10: Two Lower 9th Ward breach locations relative to ‘T’ intersection of IHNC with
MR-GO – GIWW (USACE IPET 2007)
Early the morning of 29 August 2005, the water level in the IHNC began to rise as a
result of the effects of the hurricane Katrina surge developed in Lake Borgne and its hydraulic
connectivity with the MR-GO - ICWW (Figure C.11). The main peak of this storm surge was
relatively short-lived, rising quickly over a period of several hours to a maximum elevation of
approximately +14 feet (MSL, Mean Sea Level) at approximately 8:30 a.m. (Central Daylight
12
Time), and then subsiding quickly thereafter. The hydrographs in figure C.11 are bsed on actual
measurements of the water levels versus time near the west bank corssing of the CSX rail line
across the IHNC channel. The ‘dip’ in the rising hydrograph at one of the stations wa caused by
As the water level in the INHC increased during hurricane Katrina, the water reached the
top of the earth levee on the east side and rose up the concrete floodwall (Figure C.12). The top
of the earthen berm had an elevation on the east side outside the I-wall alignment higher than the
land behind the levee, having been built-up with materials dredged from the IHNC to form the
EBIA. This bench extends 100 to 200 feet west of the I-wall alignment at an elevation of zero to
about 2 feet. Due to the USACE decision regarding the reference elevation for construction of
the I-walls, everything was built 2 to 3 feet too low (top of wall elevations 12 to 13 feet).
13
Figure C.12: As-built drawings for I-wall installation on the east bank of the IHNC adjacent to
the Lower 9th Ward.
North Breach
Available evidence indicates that the first of the two breaches to occur was the North
breach (USACE IPET 2007, Team Louisiana 2007). Based on timing established by ‘stopped
clocks,’ this breach appears to have fully developed by approximately 5:45 a.m., as floodwater
began to halt clocks in homes in the adjacent neighborhood shortly after that time (Team
Louisiana 2007). Eyewitness reports indicate that water was entering this area as early as 5:00
a.m. (USACE IPET 2007). It is likely that this early report of flooding is associated with the
onset of development of the breach (movement of the earth berm and concrete I-wall, Figure
C.4) and opening the vertical ‘expansion joints’ in the concrete I-walls. This behavior was
observed and photographed during the evolution of the breach at the 17th Street Canal.
Figure C.13 shows an aerial view of this feature. This was a relatively narrow feature,
less than 100 feet in width, and unlike the more massive second failure that occurred several
hundred yards to the south, there was no evidence of sustained overtopping adjacent to this
14
feature. The hydrographs indicate that the water level would have been at approximately +4.5
feet MSL at the onset of the failure and at approximately +9.0 feet MSL at the time of the full
development of the breach. This meant that the wall failed before the water reached the top of the
Identified in Figure C.13 and Figure C.14 (taken while water is flowing into the Lower
9th Ward) are ‘holes’ located immediately outside (IHNC side) the flood wall. This feature can
be seen more clearly in Figure C.15. This feature is in the immediate vicinity of one of the
underground excavations reported by WGI in the EBIA lock expansion site clearing report (WGI
2005).
Figure C.13: Photograph of the North Breach at Lower 9th Ward taken 29 August 2005 (USACE
IPET 2007). Note the water filled ‘hole’ immediately outside the flood wall on the IHNC side.
15
Figure C.14: Photograph of the North Breach taken while water is still flowing into the Lower 9th
Ward. Note the deep water filled ‘hole’ immediately outside the flood wall on the IHNC side.
Turbulent water indicates shallow inward flows taking place
Figure C.15: Photograph of North Breach taken shortly after passage of hurricane Katrina
showing breach repair operations underway. Deep hole located outside the wall is indicated.
16
South Breach
Several hundred yards to the south of the North Breach, a massive second breach
developed. Figure C.16 shows an oblique aerial view of the South Breach which ws
approximately 1000 feet in length. The large barge washed in through this very long feature is
visible in this photograph. The sheetpile wall is also clearly visible. The sheetpiles remained
interlocked throughout the severe inflow and scour caused by the breach. The concrete floodwall
atop the sheetpiles could not withstand the deformations developed by the sheetpiles as they
were stretched and much of the concrete I-wall panels spalled off of the top of the sheetpile
curtain. The large excavation ‘hole’ on the former EBIA site immediately outside the breach and
adjacent to the former alignment of the floodwall is indicated on Figure 16. This feature is in the
immediate vicinity of one of the underground excavations reported by WGI in the EBIA lock
Figure C.16: Oblique aerial photograph of South Breach showing barge and excavation ‘hole’
outside the floodwall alignment at the former EBIA site (FEMA 2005)
17
A similar but earlier photograph is shown in Figure C.17. This photograph was taken
during the water outflow the afternoon of 29 August 2005. The deep ‘holes’ immediately outside
the floodwall alignment at the north and south ends of the South Breach are indicated on the
photograph. The aerial photograph taken about the same time shown in Figure C.18 shows the
excavation holes at the north and south ends of the South Breach.
Figure C.17: Oblique photograph showing the South Breach with levee alignment and EBIA lock
expansion site clearing ‘holes’ immediately outside the north and south ends of the breach are
indicated (USACE IPET 2007)
18
Figure C.18: Aerial photograph shown the South Breach with EBIA lock expansion site clearing
‘holes’ immediately outside the north and south ends of the breach are indicated (NOAA 2005)
The near surface geology at this location is dominated by sediments deposited by past
distributaries of the Mississippi River with the exception of the area near Lake Pontchartrain.
Conditions near the lake (Figure C.19). The area at the IHNC - Lower 9th Ward is underlain by
swamp and marsh deposits that vary between 10 and 20 feet in thickness. Interdistributary
materials consist largely of fat clays below the marsh and swamp deposits. This layer, which also
contains zones of lean clays and slit, is approximately 30 to 35 feet thick. A complex estuarine
deposit exists below the interdistributary layer and is comprised of a complex mixture of clays,
silts, sands, and broken shell material. This deposit is about 30 feet thick and is underlain by
19
Figure C.19: Near-surface geology of area between 17th Street Canal and IHNC Lower 9th Ward area
20
South Breach North Breach
Figure C.20: East bank of IHNC geologic section through South Breach and North Breach sites (USACE IPEt 2007)
21
A centerline geologic section of the east bank of the IHNC (Figure C.20) shows the North
Breach and South Breach to be underlain by primarily gray clays with occasional plastic silt
strata. There are two significant marsh (swamp) deposits in the upper foundation soils.
Figure C.21 shows a cross-section through the South Breach. The top of the concrete
floodwall at this location is at approximately +12.7 feet (MSL). The clayey levee embankment
sits atop primarily gray clays (CH) with occasional plastic silt strata. There are two significant
“marsh” layers in the upper foundation as well. The sheet pile curtain supporting the concrete
floodwall is very short with its base at –8 feet MSL. This ‘short-sheet’ design fails to cut off flow
through the second primary marsh layer. The “marsh” layer is a variably interbedded layer of
organic silts, clays and peats. Lateral permeability of this ensemble is variable. There is a well
established history of underseepage problems along this and nearby levee frontages (ILIT 2006,
Figure C.21. Geologic cross section through the South Breach (CH – high plasticity clays, ML –
silts, CL – low plasticity clays)\
Geologists have determined that this location is crossed by a growth fault zone; the Lake
Borgne growth fault. Such growth faults are endemic to the southern coastal states (due to
22
compaction of soft underlying sediments, ground water withdrawal, petroleum production, and
other similar activities). These zones develop features like silt dikes such as was found at this
location (Gagliano 2005). Such features have been mapped in the center of the south breach that
developed in the Lower 9th Ward during hurricane Katrina (Figure C.22). These zones extend to
significant depths (well in excess of 100 feet). Earthquakes have occurred along these zones (one
reported in this area in 1964, Gagliano 2005). These growth fault zones could provide
weaknesses and high water conductivity (permeability) conduits in the soil column.
Figure C.22: Mapped growth fault (Lake Borgne fault zone) through center of South Breach
(Gagliano, Effects of Geological Faults on Levee Failures in South Louisiana, Testimony to U.S.
Senate Committee on Environment & Public Works, November 17, 2005)
23
Additional evidence for the nature of the under seepage potential at these two sites was
provided by an impressive “crevasse splay” (local term for fan shaped under seepage erosion
features, ILIT 2006). This crevasse splay developed at the outboard side of the interim repair
section at the south breach (Figure C.23). This crevasse splay occurred at the relatively low
reverse-flow gradients as the inboard area continued to drain after it had already been largely
unwatered by pumping after initial drainage through open breaches. This crevasse splay
undermined the otherwise continuous outboard side toe fill blanket along this frontage. The
location of this crevasse splay, coincident with the location of the south breach failure provides
strong support for the presence of a foundation stratum of very high lateral permeability at this
location.
Figure C.23: Crevasse splay induced by reverse flow beneath the interim repair embankment
24
A contractor was given the job by USACE to construct a cofferdam associated with
construction of a drainage culvert located north of this area during the period 1999 to 2003. As
shown in Figure C 24, the contractor experienced significant difficulties with water flooding and
soil heaving at depths between about –15 feet and –30 feet (McElwee personal communications
2005, 2006). Only after the sheetpiling were driven to penetrations of –60 feet were the water
flooding and soil heaving problems arrested. The excavated soils were highly organic silts and
clays.
Figure C.24: Soil heaving problems and seepage experienced during excavation of coffer dam
Soil sampling and testing results indicate marsh deposits in the upper layers – extending
to depths of –30 feet MSL. Based on knowledge of the geology of the area and the results from
25
soil exploration testing and sampling, the depths are highly variable (as would be expected for
the bottom of a swamp / marsh). The following quotations are from the soil boring logs that
sampled the soils in these layers: "Very soft, gray clay, saturated, with large amount of word
fragments and roots. High moisture content with trace organic matter, wood and significant
amount of roots. Grading to firmer with depth. Unable to perform vane due to large amount of
roots and wood in sample". "Very soft gray organic clay with humus and wood (Much wood at
19.5' - 20.0').” “ Very soft dark gray organic clay with humus and much wood".
Results from the USACE IPET and ILIT soil borings and in situ tests performed in this
area indicate the presence of “marsh” layers to a depth of –20+ feet (NAVD88). During the ILIT
sampling program, very high conductivity through the marsh layers was observed during drilling
through these layers at each of the sites in this area (Figure C.25). As the hole was drilled at one
location, the drilling fluids quickly communicated through the marsh layers to the nearby
adjacent holes which had been previously drilled. Examination of the samples indicated
distinctive preferential layering of the organic material indicating much higher horizontal water
26
Figure C.25: Observations of very high hydraulic conductivity associated with buried “marsh”
layers made during soil boring drilling operations at the Lower 9th Ward breach sites (Rogers
2007)
27
North Breach Analyses
Figure C.26 shows a cross-section through this breach site as employed in both finite
element analyses, limit equilibrium analyses, and finite difference analyses. The embankment
crest is at an elevation of approximately + 7.5 feet MSL and the upper portion of the
embankment consists of moderately compacted clay fill. The lower embankment section is older
historic fill and consists of locally available clays of relatively high plasticity. These are
marsh stratum is underlain by a relatively deep layer of soft, lacurstrine (lake) clays of relatively
high plasticity. This figure also shows the relatively extensive dredged sandy fill placed at the
outboard side of the floodwall to create additional land for the EBIA.
Note that the navigation channel lock expansion site clearing underground obstruction
removal excavation ‘holes’ are not included in this model. Currently, the author is performing
analyses to determine the effects of these holes on the performance of the levee – floodwall –
sheetpile system.
Figure C.26: Cross-section for analysis of the North Breach (Seed et al 2007)
28
Figure C.27 shows the USACE IPET investigation’s interpretation of the statigraphy and
shear strengths in the foundation soils beneath the inboard side levee toe at the North Breach.
The solid symbols are shear strength test data and the irregular line is IPET’s interpreted
undrained shear strengths from cone penetrometer testing (cone tip factor of NK = 15). The IPET
investigation concluded that the soils at this site were normally consolidated over their full
depths and the linear red lines int his figure are then the linearly increasing shear strength
The ILIT investigation (2006) and the later analyses summarized here (Seed et al 2007)
used more elaborate methods for interpretation of the shear strength data. For the soft clays at
this site, making use of the pore pressure measurements from the in situ piezocone data, the ILIT
investigation re-interpreted the shear strength data using site-specific and material-specific cone
tip factor value of NK = 12 as shown by the irregular fine blue line in Figure C.27. For the marsh
deposits, following the same procedures, the IPET interpretation used a site-specific and material
specific cone tip factor of NK = 15. Additional evaluation of the geology and depositional history
indicated that the entire profile could not be treated as normally consolidated and the assessment
of shear strength versus depth is shown in Figure C.27 by the heavy dashed red lines.
Figure C.28 shows results from a transient flow seepage analysis that determines the
calculated seepage exit gradients as they would have existed with the canal water at a level of
+14 feet MSL. These transient flow analyses modeled the progressive rise in storm surge levels
over the 24 hours before the failure at between 5:00 a.m. and 6:00 a.m. The analyses in Figure
C.27 were performed with a coefficient of horizontal permeability of Kh,marsh = 10-4 centimeters
per second (cm/s). Exit gradients had become unsafe with regard to initiation of erosion at an
earlier stage of this analysis, with exiting toe gradients reaching values of grater than 0.8 as early
29
as 5:00 a.m. The pore pressures under the inboard levee toe became potential unsafe with regard
C.27: Alternative intgerpretations of soil stratigraphy and shear strengths beneath the inboard
side levee toe at the North Breach site (Seed et al 2007)
30
Figure C.28: Hydraulic exit gradients for the North Breach. Horizontal permeability of 10-4 cm/s.
Storm surge at +14 feet MSL. (Seed et al 2007)
Even though a range of permeabilities and soil shear strengths were studied, they do not
explain the occurrence of failure at this site as early as between 5:00 a.m. and 6:00 a.m. The
conclusions drawn from the analyses were that under seepage and piping exacerbated by uplift or
‘blowout’ at the inboard toe of the levee was the principal cause of this failure. It is postulated
that the substantially shortened seepage paths caused by the water filled gap and the unfilled
excavations left immediately outside the floodwall and sheetpiling will show that ‘blowout’
conditions could have existed as early as 5:00 a.m. to 6:00 a.m., thus explaining the water
Analyses of this breach performed by the USACE IPET did not include permeability –
seepage effects based on ‘professional judgment’. Their analyses of lateral stability indicated a
31
Both sets of these analyses have not addressed the potential effects of the ‘holes’ that
existed on the IHNC side of the flood wall. As noted earlier, I am performing analyses to
determine the effects of these excavations. The analyses will include a broad range of parameters
to assist in development of additional insights into the reasons for the premature failure at the
North Breach.
Figure C.21 has presented a geologic cross section through the South Breach site. As for
the North Breach site, transient flow analyses were performed for this site. The analyses showed
that the rising storm surge in the canal was likely able to be partially effectively transmitted to
foundation soils beneath the inboard side levee toe. The storm surge rose slowly at first, raising
water levels in the IHNC from approximately +2 feet MSL to +5 feet MSL over a 22 hour
period, and then the rate of water level rise increased as the eye of the storm approached, raising
the water levels form + 5 feet to their full peak at approximately +14 feet MSL over an 11-hour
period, and overtopping the concrete flood wall height by a bit more than a foot.
As for the North Breach, these analyses do not include the effects of the navigation
channel lock expansion site clearing unfilled excavations left immediately outside two locations
along this stretch of the floodwall and sheetpiling. These effects will be addressed by future
analyses.
It is important to note that if these flood walls were designed, constructed, and
maintained at their authorized elevations, and if breaching had not developed, there would have
been minor overtopping and flooding of the Lower 9th Ward and adjacent areas.
Figure C.22 shows equipotential water pressure (contoured in 1 foot increments of water
head) contours and seepage vectors for transient flow analyses of conditions as the canal water
32
levels reached + 14 feet MSL. The equipotential contours are those calculated based on a lateral
coefficient of permeability for the “marsh” layer of Kh,marsh = 10-4 cm/s. A range of permeability
As shown in Figure C.23, the fraction of the steady state pore pressure that accrues at this
location is strongly affected by the lateral permeability of the marsh layer. For values of Kh,marsh
= 10-4 cm/s to Kh,marsh = 10-6 cm/s, the fractionof the full steady state pore pressure (1,080 pounds
per cubic foot) would be on the order of 85% to 77% of the steady state pore pressures . The
pore pressures correspond to the ‘gapped’ wall – sheetpiling cases wherein it is assumed tat a gap
opens between the sheetpiles and the levee embankment soils on the waterside as the canal water
reaches an elevation of approximately +11 to +12 feet MSL. Such gapping was noted in the
finite element analyses performed to model the behavior of this section. The effect of this gap is
to permit direct entry of high water pressures at the base of the sheetpile curtain during the later
states of the storm surge rise and this also adds to the pore pressure rise beneath the inboard side
Exit gradients at the toe were calculated to be marginally unstable with respect to
initiation of erosion and piping at this stage by approximately 8:30 a.m. for conditions
corresponding to Kh,marsh = 10-4 cm/s or greater. Hydrostatic forces on the upper clay layer
overlying the main marsh layer at the toe region were also marginally stable with regard to
33
Figure C.22: Equipotential contours when canal water levels reached +14 feet MSL. Contours
are at 1-foot intervals of water head (63 pounds per square foot). Horizontal permeability is
Kh,marsh = 10-4 cm/s (Seed et al 2007)
Figure C.23: Pore water pressure versus time at the top of the marsh layer at the toe of the levee
(location D Figure C.22) as a function of permeability of the marsh layer (Seed et al 2007)
34
Figure C.24 shows results from the finite element analyses fir conditions at a canal water
elevation of +13.5 feet MSL. Both the evolving outboard side ‘gap’ and the eroded inboard side
trench are present at this stage. As shown in Figure C.24, two distinct failure mechanisms are
approaching a failure state: an upper failure controlled by the relatively thin upper “marsh” layer,
and a deeper mechanism along the top of the main lower “marsh” layer.
Figure C.25 shows the calculated evolution of the Factor of Safety (water driving forces
divided by soil resisting forces) as canal water levels rose. At a water level of approximately +10
to +12 feet, a water-filled ‘gap’ began to open on the outboard side of the sheetpile curtain, and
the analytical case began to transition form the ‘un-gapped case’ to the ‘water –filled gap’ case.
Based on both conventional limit equilibrium analyses coupled with transient flow seepage
analyses, and finite element analyses which internally incorporated the seepage analyses, the best
analytical estimate was that failure would occur at a canal water elevation of about +12.5 to
+14.5 feet MSL. This is in very good agreement with the observed field performance at this
section which suggests that the failure occurred at a canal water level of approximately +12.5 to
+ 14 feet MSL.
35
C.24:Relative shear strain levels at a canal water elevation of +13.5 feet MSL at the South
Breach (Seed et al 2007)
C.25: Evolution of the Factor of Safety as canal water levels rose at South Breach (Seed et al
2007)
36
Summary and Conclusions
At the site of both breaches, as the water level continued to rise the concrete floodwall
and supporting sheet pilling leaned toward the protected side. Due to the levee crown (top)
elevation (below water level at this time) and levee cross-section, water intruded into a gap that
developed between the sheet piling and supporting soils on the canal side. This allowed
substantial increases in the water lateral pressures acting on the floodwall – sheet piling – soil
levee system. In addition, the leaning floodwall and sheet piling effectively cut the supporting
At the same time, the current (Seed et al 2007) transient flow analyses show that the
rising storm surge in the IHNC was effectively transmitted to the inboard side levee toe area.
Based on the analyses summarized here, by about 8:00 a.m., approximately 75% to 90% of the
steady state flow surge-induced pore pressures reached the foundation soils beneath the inboard
toe of the levee. It is important to note that these flow analyses did not include the dramatically
shortened flow paths caused by the gaps formed behind the floodwall nor of the site clearing
unfilled excavation holes. Abundant evidence of flood side cracking and sinkhole formation on
the protected side was found in the surviving I-wall segment between the north and south
breaches. These under seepage effects would have had extremely important effects on the soil
The IPET study did not analyze the potential effects of under seepage: “Piping and
erosion from under seepage is unlikely because the I-walls were founded in a clay levee fill, a
marsh layer made up of organics, clay and silt, and a clay layer. Because of the thickness, the
low permeability of these materials, and the relatively short duration of the storm, this failure
mode was considered not likely and was eliminated as a possible mode of failure” (IPET, 2007).
37
Both the NAE/NRC and ASCE IPET oversight and review committees criticized the IPET lack
of recognition and treatment of under base seepage effects in their analyses of the breaches that
As noted earlier, (due to their lower than authorized elevation and the surge water
conducted into the IHNC by the ICWW and MRGO) from about 7 a.m. to 10 a.m., the
floodwalls would have been overtopped. Because no protection (armoring) had been provided
for the levee behind the floodwalls (e.g. splash pads), as the water overtopped the floodwalls,
trenches were eroded behind the floodwalls. This led to removal of substantial portions of the
levee and consequently reduced the lateral capacity of the flood protection structure (Figure
C.26).
Figure C.26: Surge overtopping scour trench developed behind I-wall at south breach (USACE
IPET 2007)
38
Analyses performed by the author indicate that sections of the I-wall could have failed
due to removal of the lateral support caused by erosion of the deep trenches (5 to 6 feet) formed
behind the supporting sheet piles. These analyses and conclusions have been corroborated by
Gordon Boutwell (Flooding Evaluation Tank T-250-2, Murphy Oil Facility, Meraux, LA, Expert
Report, August 2006) and NIST (2006). This possibility needs to be further analyzed to
determine if it could have been a controlling mode of failure for some sections.
As the water continued to rise in the INHC, under the increased lateral pressures, the soil
levee supporting the floodwall and sheet piling deformed laterally and differentially. The
floodwall had vertical ‘water stops’ that separated the individual panels that comprised the
concrete floodwall (expansion – settlement joints). Significant wall movement was found in the
wall sections adjacent to the north breach. However, no such movement was evident adjacent to
the south breach. As the flood protection structure deformed laterally under the water pressure, it
is likely in the breach sections that the vertical water stops separating adjacent sections of the
concrete flood wall opened sufficiently to all water to jet through the openings and erode the
soils on the protected side of the levee. This behavior was photographed as the breach at the 17th
Street Canal developed (Kardon, Bea, Williamson, “Validity and Reliability of Forensic
Engineering Methods and Processes,” Proceedings 4th Forensic Congress, ASCE, 2006; IPET
Report 2006). This could help explain the report given by IPET that eyewitnesses indicated that
water in the 9th Ward near Florida Avenue was accumulating as early as 5 AM when the water
level in the IHNC was still well below the top of the floodwall.
Lateral translational instability was apparently involved at both north and south breaches.
Inspections of the flood protection structure north and south of the North Breach indicated
39
significant movements had occurred in the adjacent sections of the flood protection structure.
However, the IPET analyses (2006, 2007) reached somewhat different conclusions for
both the North Breach and the South Breach. IPET attributed the North Breach to a deep, semi-
rotational failure through the soft gray clays of the foundation, and at an early time (well before
6:00 a.m. with water level at about 11 feet – well below the top of the floodwall) in order to
explain the eyewitness observations cited earlier. This would indicate an ‘unexpected’ failure.
The early eyewitness reports of water accumulation at the levee toe could be explained as
resulting from water flowing through the water stops that could have been opened by differential
deformations developed in the supporting soils. IPET stability analyses of the South Breach
resulted in computer factors of safety larger than unity with the water level at the top of the wall
and a crack behind the wall, indicating that the walls at those locations would have remained
stable if none of the soil supporting the wall had been removed by erosion. As noted, IPET
choose not to investigate the effects of under seepage and hence the effects were not included in
their analyses.
Additional evidence for the nature of the under seepage potential at these two sites was
provided by an impressive “crevasse splay” (local term for fan shaped under seepage erosion
features, ILIT 2006). This crevasse splay developed at the outboard side of the interim repair
section at the south breach (Figure C.23). This crevasse splay occurred at the relatively low
reverse-flow gradients as the inboard area continued to drain after it had already been largely
unwatered by pumping after initial drainage through open breaches. This crevasse splay
undermined the otherwise continuous outboard side toe fill blanket along this frontage. The
location of this crevasse splay, coincident with the location of the south breach failure provides
40
strong support for the presence of a foundation stratum of very high lateral permeability at this
location. This zone or stratum of very high lateral permeability could be associated with the
growth fault that has been mapped through the area of the South Breach (C.22).
Most egregious were oversimplified assumptions and analyses performed by the USACE
IPET concerning mechanisms of seepage and hydraulic uplift effects. Such mechanisms have
been well known for decades. Seepage beneath levees is discussed in depth in the USACE
Control.” This chapter begins as follows: “Without control, under seepage in pervious
foundations beneath levees may result in (a) excessive hydrostatic pressures beneath an
impervious stratum on the landside, (b) sand boils, and (c) piping beneath the levee itself. Under
seepage problems are most acute where a pervious substratum underlies a levee and extends
both landward and riverward of the levee and where a relatively thin top stratum exists on the
landside of a levee.” Inappropriate evaluation and analyses of the hydraulic and strength –
deformation characteristics of the highly pervious organic marsh (swamp) layers underlying
most of the greater New Orleans area has been a historic and pervasive ‘blind spot’. Forensic
engineering investigations subsequent to hurricane Katrina clearly have identified its potential
effects at the 17th Street Canal breach, the London Canal breaches, many of the important
breaches along the MR-GO protective structures, and at the two breaches at the Lower 9th Ward.
agreement; the flood protection structure adjacent to the Lower 9th Ward did not perform
acceptably or as intended in the original design. If the flood protection structure had been built
and maintained to the intended elevation, then no significant overtopping would have occurred.
With no overtopping, there would not have been any erosion of the supporting soils behind the
41
floodwall. If the potential for formation of a water filled gap between the flood wall and its
supporting sheet piling and the adjacent soils had been recognized, then the lateral stability
performance would have not been compromised. Similarly, if the potential for under seepage had
been recognized and the seepage prevented, then the lateral stability performance would not been
further compromised.
There is substantial evidence to indicate that the USACE lock expansion EBIA site
clearing and underground storage tank removal operations played important roles in initiation of
the North Breach and South Breach. The information reviewed by the author provided by the
USACE and Washington Group International has been limited. Time has not permitted review of
the large number of documents provided by USACE and Washington Group International.
The information that is available clearly indicates a high degree of correlation with the
site remediation work conducted by WGI in behalf of the USACE at the EBIA sites and the
breach locations in the flood protection structure adjacent to the Lower 9th Ward. This
remediation work (removal of soils, formation of cavities, vibrations) very probably had
important effects on the soils relied upon to provide stability and protection for the flood
protection structure. Removal and disturbance of the surface soils overlying the permeable
subsoils (marsh layers) would have facilitated the under seepage discussed earlier in this
Appendix. In addition, removal of the soils on the canal side of the floodwall would have
42