Chemical Process CPS-028-2-0403 Operate utilities for chemical manufacturing plant Operate chilled water system NSC-2
Unit of Competence
Level
UNIT OF COMPETENCE
Operate chilled water system SN
LEVEL
NSC-2
ELEMENTS OF COMPETENCE
SKILLS STANDARD
UNIT OF COMPETENCE NSC-2 Operate chilled water system UNDERPINNING KNOWLEDGE
1 2 Process and instrumentation diagrams and technical manuals Organisational procedures related to commissioning of chilled water system Chilled water system operational pre-requisites Personal protective equipment Organisational procedures related to industrial health and safety Organisational procedures related to safety checks, pre-operational inspection and field-walk down Chemical process plants, chilled water systems and equipment Health, safety and environmental hazards Organisational procedures related to documentation Organisational procedures related to preparation to operate chilled water system
RANGE
Organisational procedures Commissioning of chilled water system Industrial health and safety Safety checks, preoperational inspection and field walk-down Documentation Preparation to operate chilled water system
EVIDENCE REQUIREMENTS
Performance Evidence All the performance criteria for this unit must be achieved and competence must be demonstrated across the range. Where performance does not provide evidence of competence, supplementary questions may be asked. Assessment Method Practical test Oral test
2 3 4
3 4 5
Process instrumentation and technical manuals Process and instrumentation diagrams Schematic diagrams Equipment list Technical specifications Safety checklist System operations manual Materials Safety Data Sheet
Knowledge Evidence Knowledge critical to performance must be assessed to demonstrate competence. Assessment Method Oral / Written test
Potential health, safety and environmental hazards are rectified and documented in accordance with established organisational procedures Where potential health, safety and environmental hazards cannot be rectified, appropriate person is informed Preparation to operate chilled water system is carried out and completed in accordance with industrial health and safety procedures Where preparation to chilled water system cannot be carried out or completed, appropriate person is informed
ELEMENT OF COMPETENCE 1 Prepare to operate chilled water system PERFORMANCE CRITERIA UNDERPINNING KNOWLEDGE
EVIDENCE REQUIREMENTS
Personal protective equipment Safety helmet Safety shoes Safety goggles Ear plugs Gloves Overalls
Plant and equipment Pumps Valves Piping system Compressor Lubrication system Evaporator Condenser Heat exchanger (absorber) Refrigeration system Electricity supply Tanks and vessels Cooling tower Cooling water system Chemical treatment systems Control instruments
ELEMENT OF COMPETENCE 1 Prepare to operate chilled water system PERFORMANCE CRITERIA UNDERPINNING KNOWLEDGE
EVIDENCE REQUIREMENTS
Compressed air systems Filters Strainers Pressure control devices Water analysers Drum screens and cleaning systems
Health, safety and environmental hazards Pressure build up Compressor and pump failure Hose rupture or leakage Faulty instruments Toxic and hazardous materials
ELEMENT OF COMPETENCE 1 Prepare to operate chilled water system PERFORMANCE CRITERIA UNDERPINNING KNOWLEDGE
EVIDENCE REQUIREMENTS
RANGE
Organisational procedures Start-up of chilled water system Communications Line up of chilled water system Chemical injection dosage Commissioning of water analysers Start-up of control system
EVIDENCE REQUIREMENTS
Refrigeration, chilled and cooling water systems are checked to ensure proper line up and integration in accordance with system requirements and established organisational procedures Chemical injection dosage to chilled water system is adjusted and maintained in accordance with established organisational procedures Water quality analysers are commissioned in accordance with established organisational procedures Instrument controls are commissioned and checked for functionality in accordance with established organisational procedures Control system is set to appropriate pressure, temperature, level and flow settings in accordance with established organisational procedures Non-conformances and abnormalities are identified, rectified and documented in accordance with established organisational procedures Where start-up of chilled water system cannot be carried out or completed, appropriate person is informed
Chilled water system Pumps and valves Piping system Electrical supply Control instruments Heat exchanger (absorber) Vessel and control system Cooling tower Chemical treatment and injection system Type of chemical Quantity Compressor Lubrication system Evaporator
5 6 7 8 9 10
7 8
Refrigeration system
ELEMENT OF COMPETENCE 2 Start-up chilled water system PERFORMANCE CRITERIA UNDERPINNING KNOWLEDGE
EVIDENCE REQUIREMENTS
Non-conformances and abnormalities Failure and malfunction Pump Actuator Valve Dampers Control equipment
Electricity supply failure Instrument air supply failure Water supply failure Water quality Excessive vibration Pumps Motors
High filter and strainer differential pressure Pressure build up System leakage Water temperature Toxic and hazardous materials
ELEMENT OF COMPETENCE 2 Start-up chilled water system PERFORMANCE CRITERIA UNDERPINNING KNOWLEDGE
EVIDENCE REQUIREMENTS
Appropriate person Supervisor Relevant process units Utility plants Process plants
ELEMENT OF COMPETENCE 3 Monitor and maintain chilled water system PERFORMANCE CRITERIA
1 Chilled water system operation is monitored and maintained in accordance with given work instructions and established organisational procedures Plant and equipment are routinely inspected to ensure good working condition in accordance with established organisational procedures 3 Chilled water tank is monitored Refrigeration system, compressor and lubrication is monitored Water level and quality, pumps and heat exchanger are monitored 4 5 6
RANGE
Organisational procedures Monitoring and maintaining operation of chilled water system Inspection of plant and equipment Water quality Industrial health and safety
EVIDENCE REQUIREMENTS
2 3
Operating parameters for temperature, flow, pressure and level are monitored and maintained in accordance with established organisational procedures Water samples are tested to ensure water quality falls within prescribed specifications in accordance with established organisational procedures Abnormalities encountered during monitoring and maintaining of condensate system are rectified, documented and reported to appropriate person in accordance with established organisational procedures Relevant industrial health and safety precautions are adhered to during monitoring and maintaining of chilled water system in accordance with established organisational procedures Where monitoring and maintaining of chilled water system cannot be carried out or completed, appropriate person is informed
Monitoring chilled water system and equipment Chilled water tank Pumps, valves and actuators Heat exchanger Filter Strainer Refrigeration system Operating parameters Pressure Flow Temperature Level Nitrate pH Water conductivity Total dissolved solids
4 5
Water quality
ELEMENT OF COMPETENCE 3 Monitor and maintain chilled water system PERFORMANCE CRITERIA UNDERPINNING KNOWLEDGE
EVIDENCE REQUIREMENTS
Electricity supply failure Instrument air supply failure Water supply failure Water quality Excessive vibration Pumps Motors
High filter and strainer differential pressure Pressure build up System leakage Water temperature Toxic and hazardous materials
Industrial health and safety precautions Use of personal protective equipment Use of safety checklist and inspections
10
ELEMENT OF COMPETENCE 3 Monitor and maintain chilled water system PERFORMANCE CRITERIA UNDERPINNING KNOWLEDGE
EVIDENCE REQUIREMENTS
Appropriate person Supervisor Relevant process units Utility plants Process plants
11
RANGE
Organisational procedures Shut down of chilled water system Industrial health and safety Communications Isolation, depressurisation and drainage of chilled water system Inspection of plant and equipment Documentation
EVIDENCE REQUIREMENTS
Personal protective equipment Safety helmet Safety shoes Safety goggles Ear plugs Gloves Overalls
Chilled water system is depressured and chilled water is drained, where required, in accordance with established organisational procedures Inspection of plant and equipment is carried out to confirm status, and to ensure proper shut down, depressurisation and drainage in accordance with established organisational procedures Abnormalities encountered during shut down of chilled water system are rectified, documented and reported to appropriate person in accordance with established organisational procedures Shut down of chilled water system is accurately documented in accordance with established organisational procedures Shut down of chilled water system is carried out and completed in accordance with industrial health and safety procedures Where shut down of chilled water system cannot be carried out or completed, appropriate person is informed
Industrial health and safety precautions Use of personal protective equipment Use of safety checklist and inspections Use of lock out and tag out tags Draining of condensate
9 10 11
12
ELEMENT OF COMPETENCE 4 Shut down chilled water system PERFORMANCE CRITERIA UNDERPINNING KNOWLEDGE
EVIDENCE REQUIREMENTS
Abnormalities in shut down Plant and equipment Failure Faults Damage Malfunction
Appropriate person Supervisor Relevant process units Utility plants Process plants
13
II A
PERFORMANCE CRITERIA
Prepare to operate chilled water system Reference is made to process and instrumentation diagrams, commissioning procedures and technical manuals related to plant and equipment prior to commencement of work activities
REMARKS
Chilled water system operational pre-requisites and any given work instructions are clarified with appropriate person
Appropriate personal protective equipment is worn in accordance with established organisational procedures
Perform the following tasks within 1 hour 20 minutes: Prepare to operate chilled water system within 20 minutes
Inspection and field walk-down is carried out to verify plant and equipment status in accordance with established organisational procedures Plant and related equipment are checked Valve status is checked Line-up status is checked Service and utility supply are checked
* Please tick
14
NRIC TELEPHONE
PERFORMANCE CRITERIA
REMARKS
Start-up chilled water system within 20 minutes Monitor and maintain chilled water system within 20 minutes Shut down chilled water system within 20 minutes
Potential health, safety and environmental hazards are rectified and documented in accordance with established organisational procedures
Where potential health, safety and environmental hazards cannot be rectified, appropriate person is informed
Preparation to operate chilled water system is carried out and completed in accordance with industrial health and safety procedures
Where preparation to chilled water system cannot be carried out or completed, appropriate person is informed
B 9
Start-up chilled water system Start-up of chilled water system is carried out in accordance with given work instructions and established organisational procedures
10
Communication with appropriate persons from relevant process units is carried out in accordance with established organisational procedures
* Please tick
15
NRIC TELEPHONE
PERFORMANCE CRITERIA
REMARKS
11
Chilled water system is lined up in accordance with system requirements and established organisational procedures Tank Pump Heat exchanger Safety and drain valves
12
Refrigeration, chilled and cooling water systems are checked to ensure proper line up and integration in accordance with system requirements and established organisational procedures
13
Chemical injection dosage to chilled water system is adjusted and maintained in accordance with established organisational procedures
Water quality analysers are commissioned in accordance with established organisational procedures
15
Instrument controls are commissioned and checked for functionality in accordance with established organisational procedures
* Please tick
16
NRIC TELEPHONE
PERFORMANCE CRITERIA
REMARKS
16
Control system is set to appropriate pressure, temperature, level and flow settings in accordance with established organisational procedures
18
17
Non-conformances and abnormalities are identified, rectified and documented in accordance with established organisational procedures
23
18
Where start-up of chilled water system cannot be carried out or completed, appropriate person is informed
25
C 19
Monitor and maintain chilled water system Chilled water system operation is monitored and maintained in accordance with given work instructions and established organisational procedures Plant and equipment are routinely inspected to ensure good working condition in accordance with established organisational procedures Chilled water tank is monitored Refrigeration system, compressor and lubrication is monitored Water level and quality, pumps and heat exchanger are monitored
33
20
36
* Please tick
17
NRIC TELEPHONE
PERFORMANCE CRITERIA
REMARKS
21
Operating parameters for temperature, flow, pressure and level are monitored and maintained in accordance with established organisational procedures
22
Water samples are tested to ensure water quality falls within prescribed specifications in accordance with established organisational procedures
23
Abnormalities encountered during monitoring and maintaining of condensate system are rectified, documented and reported to appropriate person in accordance with established organisational procedures
24
Relevant industrial health and safety precautions are adhered to during monitoring and maintaining of chilled water system in accordance with established organisational procedures
25
Where monitoring and maintaining of chilled water system cannot be carried out or completed, appropriate person is informed
D 26
Shut down chilled water system Shut down of chilled water system is carried out in accordance with given work instructions and established organisational procedures
* Please tick
18
NRIC TELEPHONE
PERFORMANCE CRITERIA
REMARKS
27
Shut down sequence and system status are clarified with appropriate person in accordance with established organisational procedures
28
Safety precautions are adhered to and personal protective equipment is worn in accordance with established organisational procedures
29
Communication with appropriate persons from relevant process units is carried out in accordance with established organisational procedures
30
Chilled water equipment operation is stopped and chilled water system is isolated in accordance with established organisational procedures Refrigeration system Pumps Heat exchanger
31
Chilled water system is depressured and chilled water is drained, where required, in accordance with established organisational procedures
* Please tick
19
NRIC TELEPHONE
PERFORMANCE CRITERIA
REMARKS
32
Inspection of plant and equipment is carried out to confirm status, and to ensure proper shut down, depressurisation and drainage in accordance with established organisational procedures
33
Abnormalities encountered during shut down of chilled water system are rectified, documented and reported to appropriate person in accordance with established organisational procedures
34
Shut down of chilled water system is accurately documented in accordance with established organisational procedures
35
Shut down of chilled water system is carried out and completed in accordance with industrial health and safety procedures
36
Where shut down of chilled water system cannot be carried out or completed, appropriate person is informed
E 37
Complete work activities within time scale Work activities are completed within agreed time scale for the unit of competence
* Please tick
20
Knowledge
NRIC TELEPHONE UNIT OF COMPETENCE NSC-2 Operate chilled water system COMPETENT* YES NO
UNDERPINNING KNOWLEDGE
Prepare to operate chilled water system Process and instrumentation diagrams and technical manuals
REMARKS
* Please tick
21
NRIC TELEPHONE
UNDERPINNING KNOWLEDGE
REMARKS
Organisational procedures related to safety checks, preoperational inspection and field-walk down
10
B 11
Start-up chilled water system Organisational procedures related to start-up of chilled water system
* Please tick
22
NRIC TELEPHONE
UNDERPINNING KNOWLEDGE
REMARKS
12
13
14
15
16
17
* Please tick
23
NRIC TELEPHONE
UNDERPINNING KNOWLEDGE
REMARKS
18
C 19
Monitor and maintain chilled water system Organisational procedures related to monitoring and maintaining operation of chilled water system
20
21
22
23
* Please tick
24
NRIC TELEPHONE
UNDERPINNING KNOWLEDGE
REMARKS
24
D 25
Shut down chilled water system Organisational procedures related to shut down of chilled water system
26
27
28
Organisational procedures related to isolation, depressurisation and drainage of chilled water system
29
* Please tick
25
NRIC TELEPHONE
UNDERPINNING KNOWLEDGE
REMARKS
30
31
* Please tick
26
I certify that the candidate has/has not achieved all the competencies required in this unit of competence.
I have audited the assessment and certified that it has been conducted as stipulated by the skills standard
Remarks
Remarks
27
UNDERPINNING KNOWLEDGE
Prepare to operate chilled water system 1
QUESTIONS
Why is it necessary to refer to process and instrumentation diagrams during preparation to operate chilled water system?
What operational pre-requisites should be in place prior to operation of chilled water system?
List the personal protective equipment required to be worn prior to field-walk down of chilled water system.
What industrial health and safety procedures related to personal protective equipment should be observed prior to commencement of work activities?
28
SN
UNDERPINNING KNOWLEDGE
QUESTIONS
Organisational procedures related to safety checks, preoperational inspection and field-walk down
Explain what must be documented during preparation to operate chilled water system.
10
10
Explain the main tasks required to be performed when preparing to operate chilled water system.
B 11
Start-up chilled water system 11 What must be checked when starting-up chilled water system?
29
SN
UNDERPINNING KNOWLEDGE
QUESTIONS
12
12
13
13
How is communication between field and console technicians usually carried out?
14
14
15
15
16
16
17
17
30
SN
UNDERPINNING KNOWLEDGE
QUESTIONS
18
18
C 19
Monitor and maintain chilled water system 19 Explain the routine tasks performed during monitoring and maintaining of chilled water system.
Organisational procedures related to monitoring and maintaining operation of chilled water system
20
20
21
21
Where can information relating to required operating parameters for temperature, flow, pressure and level be found?
22
22
23
23
List one common fault during monitoring and maintaining chilled water system and explain how it is rectified.
31
SN
UNDERPINNING KNOWLEDGE
QUESTIONS
24
24
List two safety precautions which should be observed during monitoring and maintaining of chilled water system.
D 25
Shut down chilled water system 25 How often is shut down of chilled water system carried out, and what are the possible reasons for shut down?
26
26
List two important safety procedures which must be observed during shut down of chilled water system.
27
27
Who are the parties involved in shut down of chilled water system, and how is communication carried out?
28
Organisational procedures related to isolation, depressurisation and drainage of chilled water system
28
29
29
32
SN
UNDERPINNING KNOWLEDGE
QUESTIONS
30
30
List three abnormalities in plant and equipment which can occur after shut down of chilled water system.
31
31
33
Skills and Curriculum Development Division Singapore Workforce Development Agency, c/o SPRING Singapore 2 Bukit Merah Central #14-00, Singapore 159835 Telephone: (65) 6223 0012 Facsimile: (65) 6276 5062 Website: http://www.wda.gov.sg/nsrs Email:wda_nsrs@wda.gov.sg