The Fichtner Group
Established in 1922
Germany's largest independent engineering
and consulting company
Over 1400 employees worldwide
Working for public- and private-sector infrastructure
service providers with the focus on utilities
Annual revenue of 190 million euros in 2009
(consolidated)
ABOUT FICHTNER INDIA
Started in 1987 as a joint venture.
Equity structure had undergone major changes during the
last 23 years.
Presently Fichtner GmbH & Co KG holds 84% of the
equity as Indian Promoters disinvested last financial
year.
Balance equity held by Dr. Sharan, Founder Director and
senior professionals of the company.
Head office in the city of Chennai and Branch offices at
Mumbai & Bangalore.
Has established itself as a premier engineering consultancy
company in India.
Annual Turnover 2009-10 : Rs.800 Millions
Growing at the rate of 30 to 35% in the last three years.
FICHINEk Ind|o |s on ISO 001:2000
compony cert|||ed by IbV Ind|o.
FICHTNER India has vast Experience and Expertise in Power and Water Sector
SECTOR OF ACTIVITIES
Steam Power Plants
Industrial power plants, cogeneration plants
Gas turbine power plants
Combined cycle power plants
Engine cogeneration plants, diesel power plants
Renewable energies
Electrical networks and components
Switch yards, Sub-stations & switchgears
Network control and load dispatch centers
I&C, protection and telecommunications
Energy master plans
Energy supply concepts
Energy saving studies
Studies
Generation
Transmission
POWER
Thermal Technology
Membrane Technology
Sea Water Desalination
Urban Water Supply Schemes
Combined Water Supply Schemes
Water Distribution Networks
Water Treatment & Conveyance
Underground Sewerage Systems
Low Cost Sanitation
Integrated Land Development
Storm Water Drainage Projects
WATER &
INFRASTRUCTURE
POWER
Techno-Economic Feasibility Report
Detailed Project Report
Project Development
Project Management
- Technical specifications
- Procurement assistance
- Basic & detailed engineering
- Inspection & expediting
Site Management
- Supervision of construction &
erection
- Testing & commissioning assistance
- Quality control implementation
- Measurement & certification
Due Diligence
RANGE OF SERVICES
Conceptual Studies
Master Plans
Feasibility Studies
Survey & Investigation
Project Reporting & Monitoring
Detailed Project Reports
Financial Viability Analysis
Technical Audit
Inspection & Quality Control
Unaccounted for Water (UFW)
Leak Detection Studies
Rehabilitation and Augmentation Studies
WATER & INFRASTRUCTURE
DISCIPLINE
CHENNAI
OFFICE
MUMBAI
OFFICE
B'LORE
OFFICE
SITE
SERVICES
TOTAL
Management 5 2 2 1 10
Business Development 5 2 - - 7
Mechanical 75 23 32 13 143
Civil & Structural 92 14 19 19 144
Electrical 37 28 15 6 86
Control & Instrumentation 23 9 4 - 36
Water & Infrastructure 39 - - 39
System Admin. 8 2 1 - 11
Admin / HRD / Finance 39 16 8 1 64
Total 323 96 81 40 540
INFRASTRUCTURE
Office Floor Area
55000 Sq. ft.
Communication Facilities
Broad Band Internet Connection
E- Mail Facilities
ISDN
Telephone, Fax
Video Conferencing
Computer Aided Design & Engineering
MS Windows based network with more than 300 engineering and design work stations.
All required software including special purpose software like
AUTOCAD CAESER II
STADD PRO DigSILENT
KPRO PDS
ETAP CADWORKS
PIPENET INTOOLS
GT PRO
INTERNATIONAL EXPERIENCE
DETAILED ENGINEERING FOR EPC CONTRACTORS
1100 MW COAL FIRED PP - Mitsui Babcock
750 MW CCPP - MHI, Japan
660 MW CCPP - Siemens, Germany
600 MW GTPP - MHI, Japan
500 MW GTPP - Enka Teknik, Istanbul
480 MW GTPP - BEMCO,KSA
420 MW GTPP - BEMCO, KSA
355 MW CCPP - Hanjung, Korea
388 - 400 MW CCPP - Lotte, Korea
300 MW CCPP - Lakdhanavi Ltd,, Sri Lanka
120 MW HFO FIRED PP - Ansaldo, Italy
100 MW GTPP - Techmaster, Lebanon
OWNERS ENGINEERING TO UTILITIES
2000 MW LNG BASED CCPP - Petronas+TNB
120 MW GAS FIRED POWER PLANT - Eurochem Nigeria
15 MW DGPP - Rolls Royce Power Ventures,
UK
OWNERS ENGINEERING IN RENEWABLES
Solar Thermal Power Plants in India, Iran and Spain
SITE SERVICES
Fichtner, KSA
Rolls Royce Power Ventures, Nigeria
COAL BASED POWER PLANTS
Total plants engineered by Fichtner 302
group in the last 20 years
Fichtner Germany 158
Fichtner India 144
COAL / LIGNITE BASED POWER PLANTS
500 MW 200 MW AND BELOW TOTAL
CRITICAL & ABOVE ABOVE & 200 MW
LESS THAN
500 MW
Fichtner group 39 56 43 164 302
Fichtner Germany 12 29 25 92 158
Fichtner India 27 27 18 72 144
Completed DPR 2x800 MW Videocon Power Ltd. 8
Completed DPR 2x800 MW ILFS TN Power Co Ltd 7
Completed DPR 2x800 MW KPCL 6
Completed DPR 2x800 MW KPCL 5
Completed DPR 2x800 MW KPCL 4
Completed Feasibility Report 2x800 MW TNEB- Udangudi 3
Completed Pre-Feasibility Report 2x800 MW NLC, Neyveli 2
Completed Pre-Feasibility Report 3x800 MW Gagan Power Ltd. 1
800 MW
COMPLETED ASSIGNMENTS
Period of
Execution/Status
Description of Service Size Client SI No
L|st o| Super Cr|t|co| Fower F|onts
Completed
BTG Spec
Preparation
Chattisgarh 2x660 MW Jindal Power Ltd. 16
Completed DPR
Kahalgaon Dist,
Bihar
2x660 MW
Bihar Power
Infrastructure Co Ltd.
15
Completed DPR Piprainti Dist., Bihar 2x660 MW
Bihar Power
Infrastructure Co Ltd.
14
Completed DPR
Lakhisarai Dist.
Bihar
2x660 MW
Bihar Power
Infrastructure Co Ltd.
13
Completed DPR Navasari, Gujarat 2x660 MW ILFS TN Power Co Ltd 12
Completed DPR Nagapattnam Dist. 2x660 MW
Empee Power & Infra
Ltd.
11
Completed DPR Nagapattnam Dist. 2x660 MW
NSL Nagapattnam
Power And Infra Pvt.
LTd.
10
Completed Pre-Feasibility Report
Chindwara Dist.,
MP
2x660 MW
SKS Ispat & Power
Ltd.
9
660 MW
COMPLETED ASSIGNMENTS
Period of
Execution/Status
Description of
Service
Location Size Client SI No
L|st o| Super Cr|t|co| Fower F|onts
2010 - 2014
DPR + OES in Limited
Packages
Raigarh,
Chattisgarh
2x660 MW Godawari Energy Ltd. 27
2010 - 2014
DPR + OES in
Multiple Packages
Banka, Bihar 4x660 MW
JAS Infrastructure
Capital Pvt.
Ltd.(Abhijeet)
26
2010 - 2014
OES in 2 Package
Basis(BTG + BOP)
Krishnapatnam, AP 2x660 MW
Thermal Powertech
corporation India Ltd.
25
2009 - 2014
DPR +BTG Spec
Preparation + OES in
Multiple Packages
Angul/Orissa 4x660 MW Bhushan Energy 24
2009 - 2010
DPR + Selection of
BTG contractor
Chattisgarh & Bihar 2x660 MW
Adhunik Power &
Natural Resources Ltd.
23
2008 - 2013
OES in Limited
Package Basis
Tiroda ,
Maharashtra
3x660 MW
Phase - I
Adani 22
2010 - 2014
OES in Limited
Package Basis
Tiroda ,
Maharashtra
2x660 MW
Phase - II
Adani 21
2010 - 2014
DPR + OES in Limited
Package Basis
Dahej, Gujarat 4x660 MW Adani 20
2010 DPR Orissa 2x660 MW
PTC Energy (Sahara
Group)
19
2010 Due Diligence Krishnapatnam, AP 2x660 MW
Sembcorp Industries
Ltd.
18
660 MW
2009 - 2012
DES of BOP in
Multiple Packages
Krishnapatnam, AP 2x800 MW TATA Projects Ltd. 17
800 MW
PROJECTS UNDER EXECUTION
Period of
Execution/Status
Description of
Service
Location Size Client SI No
L|st o| Super cr|t|co| Fower F|onts
COMBINED CYCLE POWER PLANTS
Total plants engineered by Fichtner 170
group in the last 20 years
Fichtner Germany 128
Fichtner India 42
COMBINED CYCLE POWER PLANTS
Type of Gas Turbine No. of projects
of Major Projects
- LM 6000 PC 1
- Fr 5 3
- Fr 6B 3
- Fr 6FA 4
- Fr 9E 4
- Fr 9FA 8
- ABB type 8C 1
- Fr 7 EA 2
- MW 701 F 2
- MW 701 1
- Siemens V-94.2 2
- Siemens V-94.3A 1
- Siemens SGT 5 4000F 1
- Siemens SGT 5 4000E 1
- Others 8

You might also like