QC~PLAN.

Project No. & Name: Name of Client/ Consultant: SL. ACTIVITY CONTROLLING NATURE & EXTENT ACCEPTANCE CRITERIA - Pre-plastering check signed off by discipline supervisor

Plastering
Doc.No.CIVIL QC~Plan- 013/ REV. 0 PERSON RESP. AT LOCATION Engineer / Foremen/ Quality Engineer Engineer / Foremen/ Quality Engineer RECORD Plastering - Insp. Report CIVIL QC~Form- 013-01/ REV 0 --

No. 1 Check if all concealed services have been placed as required 2 Check background preparation

DOCUMENT OF INSP./TEST Drawings Verification, 100% Contract Documents

- Clean and wet - Chases made for conduits filled with cement sand mortar after placing the service conduits - Contamination of oil, salt, loose materials, loose render, paint, splashes, dust removed - Concrete surfaces hacked Check provision of metal Drawings Visual, 100% - Metal lathes / polythene mesh of specified Engineer / lathing and corner beads Contract Documents widths provided at junction between Foremen/ concreted works and masonry works and Quality along chases in the blockwork Engineer - Corner beads provided at edges susceptible to breakage or as specified Check spatter dashing/ Drawings Visual, 100% - Spatter dashing/ rush coat carried out on the Engineer / Rush coat (if required) Contract Documents masonry work prior to plastering in 1 : 2 Foremen/ (if not specified) cement and sand mortar Quality or as specified and cured for 24 hours at least Engineer Check mortar preparationContract documents Visual, 100% - Mixed to specified proportions Engineer / and maintaining check at mixing area (1:2:2 if not specified) or as specified by Foremen/ proportion with the Quality Engineer (2:2 = fine: coarse sand) Quality help of "Measuring - Preparation of mortar should be on Engineer Boxes" clean and proper surface

Drawings Visual, 100% Contract Documents

Plastering - Insp. Report CIVIL QC~Form- 013-01/ REV 0

Plastering - Insp. Report CIVIL QC~Form- 013-01/ REV 0 Daily masonary log CIVIL QC~Form- 012-01/ REV 0

QC~ PLAN.
Project No. & Name: Name of Client/ Consultant: SL. ACTIVITY CONTROLLING NATURE & EXTENT ACCEPTANCE CRITERIA

Plastering
Doc.No.CIVIL QC~Plan- 013/ REV. 0 PERSON RESP. AT LOCATION Engineer / Foremen/ Quality Engineer RECORD Plastering - Insp. Report CIVIL QC~Form- 013-01/ REV 0

No. 6 Check application of plaster

DOCUMENT OF INSP./TEST Contract documents Visual

Check curing

Check finish

- Plaster applied to thickness specified - Number of layers as specified (If not specified, use the below mentioned guidelines) Thickness One coat - 12 mm Two coat - 18 mm Contract documents Date upto which curing - Cured for period required is to be done should be( minimum 5 days if not specified) mentioned on the plastered area Contract documents Visual, 100% - Areas to receive tilling works combed rough

Final inspection after completion

Drawing, Contract specs.

Visual, 100% Physical, 100%

Tolerances in plaster finish - 3mm in 1.80 meter stretch - 10mm for soffits - No bond failure - No recurrent dampness - Good apearance

Engineer / Foremen/ Quality Engineer Engineer / Foremen/ Quality Engineer Engineer / Foremen/ Quality Engineer

Daily masonary log CIVIL QC~Form- 012-01/ REV 0 Plastering - Insp. Report CIVIL QC~Form- 013-01/ REV 0 Plastering - Insp. Report CIVIL QC~Form- 013-01/ REV 0