You are on page 1of 7

Integrated Design and Construction for Cost Effective

SCR Projects
R.A. Kuchner
J.A. Hines
The Babcock & Wilcox Company
Barberton, Ohio, U.S.A.

Presented to: BR-1733


Power-Gen International 2002
December 10-12, 2002
Orlando, Florida, U.S.A.

Abstract sions and the process used to orchestrate them into an effective
The retrofitting of power plants with NOx control technolo- project will be discussed and placed into an economic perspec-
gies is a cost-intensive undertaking facing many utilities. Key tive. The paper will highlight some of the key opportunities for
to controlling the economic impact to the utility is the effective controlling Selective Catalytic Reduction project costs.
execution of these projects. B&W has successfully designed and
installed a number of Selective Catalytic Reduction systems for
both gas- and coal-fired boilers. The success of these installa- Introduction
tions is a direct result of the key decisions made during and the The promulgation of the Clean Air Act Amendments of 1990
integrated techniques applied to the design and installation of caused many fossil-fired electric generating plants to install or
these systems. The systems are comprised predominantly of plan for the installation of Selective Catalytic Reduction sys-
flues, ducts, structural steel, reactors, catalyst, and ammonia tems (SCRs) on their existing boilers to reduce the emissions of
systems, but may also need to include modifications to the ex- nitrogen oxides (NOx). These systems are typically installed in the
isting boiler or its ancillary equipment. flue gas stream between the boiler’s economizer and air heater.
The magnitude of the project can range from 10s to upwards The systems consist of a reactor(s) housing the catalyst, flues or
of 100 million dollars depending on the size of the units, the flue modifications to deliver and return the flue gases to the reac-
extent of the modifications needed, and site-specific conditions tor, control dampers or bypasses, the structural steel required to
and requirements. The cost of the engineered equipment and support the new equipment, ammonia delivery system, and possi-
the associated cost of installation are about equal in magnitude. bly modifications to the boiler or its ancillary equipment to deliver
Most system installations are retrofit projects. Optimizing the flue gases within the required temperature range. Boiler and ancil-
design of these unit-specific systems and the associated instal- lary equipment modifications might also include the costly stiff-
lation of these large components in typically restricted spaces ening of the boiler enclosure, flues and precipitator.
during the minimum duration outage(s) involve a number of For many natural-gas-fired installations, the catalyst required
compromises and decisions. Typically these projects involve to achieve the desired or required level of NOx reduction may
hundreds or thousands of tons of structural and plate steel and be small enough to be installed in a flue section between the
hundreds of thousands of manhours of field labor. The deci- boiler and air heater. Often the flue section need only be flared

Babcock & Wilcox 1


out and the reactor supported. Figure 1 illustrates an in-line,
gas-fired installation. The generating capacity of this unit is 340
MWe. For most coal-fired applications, the back end of the boiler
must undergo a major revision to enable the installation of the
much larger catalyst-containing reactor(s). Figure 2 illustrates
a large, 900 MWe coal-fired installation.
Except for a few recent new boiler installations, SCR instal-
lations are retrofit projects. These retrofit projects require the
economical integration of the SCR equipment (including the
necessary flues, reactor and structural steel) within the tradi-
tionally congested region between the back of the boiler and
the precipitator. For a quality installation, the SCR must be con-
sidered as part of the entire boiler/air pollution control equip-
ment system. All components must function effectively as an
integrated system. Obviously the performance and function of
the entire system must be accurately considered during the over-
all design process, but these are beyond the focus of this paper.
The economic success of an SCR project is largely depen-
dent on how well the system is arranged and how easily it can
be constructed. Until recently, the cost of engineering and sup-
plying the materials was approximately equal to the cost of erec-
tion. In the last few years, we have been able to lower the cost
of supplying the engineered materials, while experiencing mod-
erately increased costs of field labor. Even though this increased
field labor cost can be offset to some extent by improvements
in labor productivity, a current project model would reveal that
installation costs can now be 55-65 percent of the total project
cost. The delivered material cost is the cost of catalyst, struc-
tural steel, plate work for the flues and reactors, dampers, and po-
tentially fans and air heaters (or modifications thereof). The erec-
Figure 1 In-line, gas-fired SCR installation. tion costs are predominantly craft labor and equipment rentals. The

Figure 2 Large, coal-fired SCR installation.

2 Babcock & Wilcox


layout of the existing boiler system and the SCR-related flues, re-
actors and associated structural steel govern the complexity of the
project and significantly impact the erection costs.
These components represent a significant portion of the de-
sign effort, system materials and erection cost, and require close
attention to schedule integration. Installation of the steel, flues
and reactors are the schedule-critical components and usually
require the staged integration of each of these components. For
example, the systems are typically erected by alternately in-
stalling steel, flues, and reactor components until the structure
and major components are in place. The required quantities of
these materials vary considerably from project to project based
on the existing configuration of the boiler, precipitator and stack,
the configuration of the SCR components, and the extent of NOx
reduction required. Table 1 demonstrates some typical steel
quantities for gas- and coal-fired units of various capacities.
To execute a successful SCR project the delicate balanc- Figure 3 Delicate balance for a successful SCR project.
ing of the “scope, schedule and cost” triangle must be man-
aged (see Figure 3).
This balance is best managed by focusing the SCR design ties completes the definition of the project for all members of the
activities on achieving the most efficient SCR construction plan, design and construction team. Interferences are relatively inex-
while minimizing the material costs. This results in the lowest pensive to resolve at the design stage, but can be devastating to the
overall project cost. project budget and schedule when first recognized during the con-
struction process.
SCR projects typically span 15 to 30 months from award to
Integrated Design Process startup; this span is dependent upon the number of units to be
The key steps in designing an SCR retrofit project are: retrofit, the complexity of the installation and the utility’s
1. Define the scope—explicitly planned outage schedule. Retrofit projects are impacted by nu-
2. Define the general arrangement of all components in merous site-specific constraints that may lengthen the overall
concert with the existing structures and equipment project. Often the tendency is for project management and en-
3. Define the construction approach—early in the process gineering to initiate the design process and begin the fabrica-
4. Perform joint project management, engineering and con- tion of materials, well before the involvement of the construc-
struction reviews of the design tion manager and/or superintendent. This approach is usually
5. Iterate through 2, 3 and 4 above, to advance and evolve fraught with future project impediments. Joint planning and
the design. ongoing review of the design by project management, engi-
Explicitly defining the scope early in the process and assur- neering and the erector produce a higher quality, more eco-
ing that all project team members share a common understand- nomical and timely project.
ing of that scope are essential. The scope description and divi- Integrating the different perspectives, knowledge and con-
sion (assignment) of responsibility establishes the course the cerns of these three key project disciplines yields signifi-
project team will travel. The importance of scope definition cant benefits. However, the effort must be a process, not an
becomes magnified when subcontractors are employed, and re- event. It must be continuous to advance and evolve the de-
duces the probability of omitted scope and ineffective hand- sign to achieve the project goals—high quality product, low
offs. Without an explicit scope definition, developing an inte- cost and schedule compliance. One joint meeting will start
grated project schedule and making sound cost-based decisions the process, but a series of periodic meetings generates the
and trade-offs becomes a game of chance. As an adjunct to the benefits. The significant design and construction decisions
definition of scope, the common spatial understanding of the must be made in ways which balance the “scope, schedule
location of the new equipment in respect to the existing facili- and cost” triangle to benefit not just engineering or the erec-
tor but the overall project.
Some of the key decisions that need to be addressed by the
Table 1 team are:
Typical Quantities (Tons) of Steel for SCR Systems • What is the best physical arrangement of the equipment?
• How do we support the equipment?
Gas–fired Units 340 MW e 750 MW e • Do we use the existing or new steel?
Structural steel 40 790 • What gets done pre-outage, during the outage, and post-
Flues / ducts 20 720 outage?
Reactor 40 270 • What are the planned / available outages and the erection
sequence?
Coal-fired Units 270 MW e 900 MW e • What access exists? What do we do to provide the re-
Structural steel 850 1800 quired access?
Flues / ducts 380 700 • Do we modularize in the shop, in the field or not at all?
Reactor 320 840 • What is, and how do we manage, the availability of field
labor?

Babcock & Wilcox 3


A critical period occurs early in the project when the project steel. These include: poorly documented changes to the steel
scope, general arrangement, construction approach and sched- structure over time, physical deterioration of the steel, the cost
ule decisions are being defined and when the key subcontrac- of assessing the design margin available in the steel, and the
tors must be integrated into the project. Two specialized groups implications of making changes to steel designed to older “codes”
exist at Babcock & Wilcox to assist the project manager by di- and having to upgrade the steel to the more recent, more stringent
recting the subcontracts with the architect-engineering firm code. Experience has shown that for jobs involving “new steel”
doing the balance of plant design (foundations, steel, piping, and “integrating or reinforcing existing steel,” the rework or cor-
electrical, etc.), the structural steel fabricator, and flue and re- rective orders is much higher for the “reused” steel. Typically, 80
actor fabricator(s). One group focuses on technical issues, and percent of the corrective actions on a steel installation are associ-
the other focuses on commercial and interface issues. This sup- ated with connecting to or reinforcing the existing steel.
port early in the project provides the necessary attention to ef- The new steel offers few restrictions, but SCR steel is also
fectively address schedule-critical activities during the critical not a “greenfield” installation. The design of this steel still must
time frame when resources are typically overloaded. Once these contend with the restrictions of existing equipment and the abil-
specialized functions are executed, those persons can leave the ity to provide adequate foundations. Obviously the deadweight
project team and consult as required. (gravity load) of the SCR components is significant, but the
size of the reactors and flues and their exposure to the wind can
provide significant overturning (uplift) forces. New steel does
Structural Steel Design offer more options for the designer. However, experience dem-
The structural steel needed for an SCR retrofit is significant onstrates that input from the steel designer, the erector and the
because it usually represents a sizeable cost, governs the project fabricator are very important during the design phase and for
schedule, and when coupled with the flues and the reactor, es- developing the lowest cost steel design and lowest installation
tablishes the complexity of the project. Once the general ar- cost for the project. The decision as to the amount of shop as-
rangements of the flues and reactor are defined, the manner in sembly for built-up columns, bents and trusses is critical to
which the voluminous flues and the heavy and voluminous re- minimizing total overall cost for the customer. Key inputs are
actor are supported is a major consideration. The two “options” crane lifting capacity at the site and for the specific installation
for supporting these components are: 1) new, independent steel points, transportation limitations and cost for a particular jobsite,
or 2) reinforced, existing steel. However, in many instances both site access clearances/obstruction considerations, and the opti-
types of steel are needed. mized breakdown of shop versus field ground assembly.
The reactor with its heavy catalyst is usually supported by a Again, the integration and optimization of the design of the
free-standing single tower(s); for the more congested sites, a structural steel is not accomplished at one meeting, but via the
bridge consisting of a number of towers and trusses is used to process of the steel designer, fabricator and erector working
support it above existing equipment. Some existing conditions together and evolving the design throughout the design phase
may dictate the installation of the SCR along side the boiler or of the project.
precipitator. The flues leading to and from the reactor must be
routed from high within the boiler building to the external SCR.
In this area, the choice is to take advantage of the existing steel Flues and Reactor Design
and adequately reinforce it or to integrate new steel (columns and The flues and reactors needed for an SCR retrofit challenge
beams) within the existing building setting. Another consideration the designer and erector because of the large size of these com-
is the foundation requirements, especially within the confines of ponents which must be installed in typically very congested
the existing structure. Excavating, installing piles and pouring foun- spaces. Layout or routing is one issue and facilitating the effi-
dations may or may not be practicable depending upon the exist- cient and safe installation is another; both must be addressed by
ing conditions, the physical layout, and the extent of the modifica- the project team. Flue sizing and layout must address pressure drop,
tions required to accommodate the new loads. local pressures, local and average velocities, thermal expansion,
Although the cost per pound for the reinforcing steel may and for coal-fired units, ash entrainment (deposition). The plan-
not be significantly different than that for new steel, the cost of ning for flue installation must include defining the segmentation
installing and the risks associated with reinforcing existing steel of the flues, sequencing for erection, and determining how and
are significantly greater than new steel. Reinforcing usually in- where to fabricate the segments. Typically the labor in the
cludes replacing vertical and/or horizontal bracing, as well as fabricator’s shop is considerably less costly than field labor.
cover plating of existing members. Some erectors estimate that The goal is to shop-assemble or ground-assemble in the field
the cost for installing new steel is 15-20 manhours per ton, while as large a segment as can be lifted and maneuvered into place
the cost of reinforcing existing steel with extensive cover plat- through the supporting steel, thus minimizing the much more
ing may be as great as 120-130 manhours per ton. Weaving the difficult and labor-intensive assembly process at elevation. For
lengths of cover plating into the existing structure is often a large flues and ducts, preassembled modules are preferred. For
difficult and time consuming task, gaining access to the steel reactors, the two options usually considered are stacking
usually requires extensive scaffolding, field welding is very la- preassembled rectangular modules, or erecting fully assembled,
bor intensive, and touch-up painting can be quite extensive. A flat wall panels. Components for large boilers and units with-
significant additional cost associated with cover plating is the out navigable water access warrant shop assembly of truck-ship-
removal and reinstallation of the electrical, controls, lighting pable panels, which can then be assembled into the flues or re-
and communications cabling and various small-diameter pip- actors and insulated prior to erection. Despite the transporta-
ing which are normally hung from or attached to the faces of tion cost which may be on the order of $500,000, barge ship-
the structural steel. Other risks are inherently associated with ment of shop assembled and insulated modules is usually the
the extensive use of existing (often 30 to 50 year old) building more economical since it minimizes field assembly to the great-

4 Babcock & Wilcox


Prior to the issuance of key design outputs, the erector should
review and comment based on constructability. Many times a
preliminary review can catch simple items such as missing or
incorrect information. If not caught early, missing or incorrect in-
formation could lead to costly rework, or at a minimum, delays in
production during critical path activities while waiting for revised
engineering documents or pending engineering evaluation.
Once modules are identified and an erection sequence is estab-
lished, the project team can work with the plate fabricators on de-
livery. If the construction approach is to field assemble panels into
modules, this activity will provide the project team the opportu-
nity to review and approve the shop’s plan for panelization. The
benefits of this are twofold. First, it provides valuable information
Figure 4 Barge shipment of shop fabricated and insulated
and knowledge about the material to be received, including the
modules.
extent of work required on-site to pre-assemble modules. It is also
est extent and reduces the impact of potential field labor short- possible to suggest alternative shipping units that may save costly
ages. Figure 4 shows a barge arriving at a job site with fully field labor and improve on-site productivity. In most instances,
insulated flue and reactor modules. this activity adds little to no cost to fabrication.
This recent 270 MWe, coal-fired installation had 31 segments In nearly every large SCR project, the steel and flues are
of flues with some weighing up to 50 tons. These modules were installed in a defined sequence to maximize the efficiency of
shop fabricated, insulated and lagged. An ongoing project for a the erection and to complete the work in the minimum time.
380 MWe unit has plans for 35 segments weighing up to 130 This will involve building sufficient steel to set the outlet flues
tons, all being shop modularized, insulated and barged to the site. or bypass flues. Once those initial flues are set, steel progresses
Figure 5 illustrates the extent of segmentation necessary to again to the point where additional flue sections can be set and the
efficiently and economically erect SCR flues for a 900 MWe reactor built. Ideally, horizontal runs of ductwork are bottom-sup-
coal-fired unit. The total number of flue segments is 52. ported, which means the support steel must first be installed be-
The more preassembly done on the ground or in the neath the duct. In addition, tie-in steel or cover-plating the existing
fabricator’s shop, the greater the potential for a lower cost structure usually needs to be accomplished prior to loading the
project; however, the required amount of planning is consider- new structure. This may require close coordination with the engi-
ably greater for delivering shop-assembled modules. Simple lift- neers who design the structure to ensure the uncompleted structure
ing attachments exemplify this requirement. The lugs and sup- is adequate to support the initial duct sections installed.
ports needed to move large assemblies of flue or reactor sec- The engineers should be made aware of the construction /
tions within the fabricator’s shop and insulating area are not erection plan and provide minimum steel to be installed to sup-
necessarily those appropriate for loading and stacking barges, for port the erection sequence. Coverplating the existing steel can
tying down during shipment, for offloading, or for maneuvering be a time-consuming and costly effort. Many times the existing
the bulky modules up, into and through the support steel on site.
Careful attention to these and many other details is needed to as-
sure the desired economic benefit, efficiency and safety.
The integration of numerous design considerations must be
addressed early in the project by the project manager, designer
and erector to produce a quality and economical installation of
flues and reactor(s).

Sequencing and Modularization


Early in the project, specific information about the weights of
ductwork sections and equipment has to be estimated. Many times
the module boundaries are easily identified, due to equipment
terminal points or expansion joint locations. Other times, sound
judgments must be made based on experience. The erector is
the prime contributor in determining splice locations that are
best from a variety of standpoints, including access, crane ca-
pacity and geometry.
The resulting erection sequence can then be used in establish-
ing schedule priorities for detail design, material procurement and
fabrication. To allow maximum flexibility for installation, it makes
sense to prioritize those efforts in accordance with erection plans.
Receiving material far in advance of the time required at the
job, or in a sequence that does not support planned erection,
only adds cost and burdens the job with additional material
handling or overhead. It may also force the constructor to
work on activities that deviate from the intended plan. Figure 5 Flue segmentation for a 900 MW e coal-fired unit.

Babcock & Wilcox 5


steel is coated with lead-based paint, which must be abated prior can help improve productivity and limit adverse effects associ-
to any welding or grinding operations. It may be desirable to ated with weather and wind.
design alternative connections that bolt rather than weld in or- Due to the extensive work required inside the flues, large
der to minimize the extent of abatement. Also, it is likely that access doors can prove beneficial for workers and equipment.
there exist numerous interferences with plant utilities supported There are literally miles of welding to be accomplished inside
from columns or beams being modified. This makes the effort the reactor and ductwork. Module identification assists in stra-
even more deliberate and requires close coordination with plant tegic door placement, and in many instances, a door can be added
operations. if it helps the construction effort.
It may be necessary (depending upon anticipated plant out- A significant amount of scaffolding is generally required,
ages) to complete a unit tie-in prior to the SCR being con- and a good construction plan will identify those modules that
structed. This effort will focus on getting a clear gas path con- require scaffolding to access welding locations. Once identi-
structed and will include dampers and blanking plates to allow fied, scaffold brackets or fixtures can be installed on the ground
the balance of construction to take place subsequent to the tie- prior to lifting the modules into place. In addition, as the steel
in. The blanking plates allow safe entry to the flues during plant is erected, any permanent stairs, ladders, platforms and hand-
operation. If this approach is taken, it will impact the erection rails for the elevations should be delivered and installed. This
sequence and potentially add to the cost of construction. can help the project proceed safely, without the need for tem-
porary platforms or scaffold stair towers.

Cranes, “Constructability,” and Access


Each SCR project poses a unique set of circumstances, ei- Field Labor, Work Force Leveling and
ther due to the plant’s geographic location, available real estate Resource Requirements
and lay down area, or interferences (both above and below grade). Time of performance should be a significant concern for both
Since most SCR projects are retrofits, access is limited with many scheduling and cost. Many SCR projects have schedules that
interferences and obstructions. A typical SCR project can require overlap other SCR projects, sometimes within the same labor
the installation of 500 or more cubic yards of concrete, hundreds region. These overlapping schedules can have significant im-
of piles, thousands of tons of structural steel and plate work, and pact on all resources including labor and equipment. Many la-
literally miles of cable and raceway. A comprehensive construc- bor union locals are stretched to support a variety of projects. Ad-
tion plan with its intended rigging scheme is therefore critical. ditionally, labor rates have escalated during recent years. It may
One of the most critical decisions is crane selection. To se- become necessary to react to labor shortages by paying travel and
lect the appropriate crane(s), a determination must be made as subsistence, working overtime, or importing workers from outside
to the limiting component of the rigging scheme. If site condi- the region, or perhaps outside the country. The same issues hold
tions limit the crane size, the largest module (or assembly) to true for qualified supervision. It can be a significant effort to put
be fabricated or ground assembled will be limited by the crane’s the right people at the right place at the right time.
available hook (lifting) capacity. If adequate space is available Each project starts with an estimated number of total
and crane size is not an issue, the optimal or largest module to manhours. Only by knowing the estimated hours, as well as a
be erected must be determined. breakdown of the work by craft jurisdiction and the time of
Once the weight of the largest component is identified, crane performance, can a plan be developed. To adequately determine
selection can begin. Project economics may drive the decision the manpower for a project, and to address the fact that a sig-
away from the largest (and most expensive) crane. In many in- nificant portion of work will occur during planned maintenance
stances, the best crane for the project is not the one with the outages, total manpower requirements must consider not only
greatest capacity. Large cranes (over 250 ton capacity) can range the SCR project, but also the requirements to support the out-
in cost from $30,000 to $130,000 per month, and transportation ages planned at each unit. Therefore, recognizing the total mag-
costs to the job can exceed $100,000. Depending upon the SCR nitude of the projects at site is a key first step.
arrangement, two of these large cranes may be required. For The demands for construction labor have led to labor avail-
large projects posing unique or complicated arrangements, crane ability problems in several regions across the country. Figure 6
costs alone can exceed $250,000 per month. indicates how employment levels have increased over the course
Another factor is the impact of the crane’s bearing pressures of the last few years.
on existing soil. If the existing site soil conditions can not handle
the loads, considerable dollars and labor are often required. It
is also important to note that most cranes experience the great-
est load when merely raising a boom, not when lifting a load.
Overall, crane costs when projected over the duration of the
project, can be several million dollars.
Flues should be bottom-supported where possible, and ide-
ally the identified modules will be self-supporting (even if this
requires temporary shop-installed supports). This self-support-
ing feature allows modules to be released from the crane rather
than held in place until welded out or lashed off.
Weather is another factor. Winds in excess of 25 mph can
shut down crane operations, limiting the window of opportu-
nity for rigging components into place. Also, fit-up bolts be-
tween adjacent panels or modules should be considered. These Figure 6 Boilermaker national employment levels, 1997-2002.

6 Babcock & Wilcox


This graph represents the utilization of available boilermaker These subcontracts are often awarded to contractors located near
resources. For SCR projects, boilermaker work can be roughly the job site to take advantage of lower overhead, but also to
70-80% of the total direct manhours. In essence, the graph shows strategically align with the local economy. Finding qualified
that nationally, the boilermakers for the last few years have been vendors in disparate regions can be challenging as well. Ide-
at or near full employment. This fact makes it difficult to re- ally, there will be sufficient time to allow vendor qualification
cruit members to travel for project work when there is work in while the design is being developed and finalized.
their home local. Equipment is another key resource that requires planning
Sometimes it may be necessary to lure prospective talent relative to time of performance. On SCR projects, total equip-
into a region. This can include planning for and offering an ex- ment and non-labor costs can represent 10 – 20% of the project.
tended workweek during periods of peak labor demand. Per- It is critical to know that the right equipment for the job will be
haps it means that the standard workweek for a project in non- available when required. This may entail the issuance of pur-
outage periods is based upon 50 hours. This can help to ensure chase orders and incurring some costs well in advance of the
labor availability and labor retention. During the outage peri- date the equipment is needed merely to ensure its availability.
ods it is likely that additional overtime would be required.
During peak labor demand periods, if labor availability con-
tinues to be a concern, subsistence packages might be required, Summary
over and above the regular and overtime earnings. If all of this The retrofitting of a power plant with an SCR system is a
fails to attract qualified labor, it may be necessary to bring in cost-intensive effort. Key to controlling both cost and quality
workers from outside the country (i.e. Canada). All of these is the effective execution of the project. The success of these
initiatives have been used successfully on projects that have capital-intensive installations is a direct result of the key deci-
experienced labor availability issues. sions made before and during the project by the project man-
If executing an EPC project, other key resources impacted ager, designer and erector working as a team, and a result of the
by time of performance include qualified subcontractors for field integrated design and erection techniques applied throughout
construction scope that is not self-performed. Babcock & the project to structural steel, flues, ducts and reactors. This
Wilcox, for example, performs the mechanical portion or metal cooperative, multi-disciplined approach must be a continuous
trades portion of its work, but usually subcontracts and man- process and must be aimed at evolving the design and the in-
ages civil, electrical, and instrumentation and controls scope. stallation of the major components.z

Copyright © 2002 by The Babcock & Wilcox Company,


a McDermott company.
All rights reserved.

No part of this work may be published, translated or reproduced in any form or by any means, or incorporated into any information retrieval system, without the written
permission of the copyright holder. Permission requests should be addressed to: Market Communications, The Babcock & Wilcox Company, P.O. Box 351, Barberton,
Ohio, U.S.A. 44203-0351.

Disclaimer
Although the information presented in this work is believed to be reliable, this work is published with the understanding that The Babcock & Wilcox Company and the
authors are supplying general information and are not attempting to render or provide engineering or professional services. Neither The Babcock & Wilcox Company
nor any of its employees make any warranty, guarantee, or representation, whether expressed or implied, with respect to the accuracy, completeness or usefulness of
any information, product, process or apparatus discussed in this work; and neither The Babcock & Wilcox Company nor any of its employees shall be liable for any
losses or damages with respect to or resulting from the use of, or the inability to use, any information, product, process or apparatus discussed in this work.

Babcock & Wilcox 7

You might also like