Professional Documents
Culture Documents
Chapter 39
Construction
Construction plays a major role in the success of any The field assembly of power generation facilities and
project. The construction organization must employ the associated environmental equipment requires ef-
erection techniques that complement the designers’ ficient, well engineered, well organized erection meth-
skill and the fabricators’ craftsmanship. Sound field ods to permit installation within a reasonable time and
assembly is essential for correct functional perfor- at minimum cost without sacrificing quality and safety.
mance of the completed installation. Efficient and safe Modularization of complex components together with
execution of any project requires that components be continuous advances in computerized drafting, mod-
on the job site at the right time along with the neces- eling, scheduling and tracking have become the norm
sary tools, equipment, labor and supervision. In ad- for these complex or fast track projects. The cost of
dition to properly erecting the components, a success- erecting a steam generating unit, such as that shown
ful construction organization possesses experience in in Fig. 1 represents a significant part of the total in-
estimating, planning, safety, quality control, cost vestment in the plant.
analysis, labor relations, tool and equipment design, Retrofitting an existing plant with environmental
technical services, and finance and accounting. A com- equipment presents a unique set of challenges requir-
petitive marketplace requires continuous improve- ing extensive planning and coordination between
ments in quality, safety and cost, together with reduced owners, engineers, manufacturers and constructors.
construction schedules, as contractors and owners strive (See Fig. 2.)
to minimize project costs and schedules. The most suc-
cessful projects maintain communication between engi-
neering and manufacturing operations, ensuring that
field erection is a continuation of the shop fabrication
process and not a completely independent event.
During initial project development, the construction
plan and work performance logistics must be evalu-
ated, then incorporated into the overall project design.
Schedule requirements, together with safety and site-
specific conditions, will affect the labor and erection
methods that will be used.
A number of boiler types are small enough to per-
mit shipment completely assembled. However, larger
industrial boilers, central station boilers, and environ-
mental systems are shipped to job sites in various
stages of fabrication and subassembly. A central sta-
tion boiler with its associated heat transfer equipment
and auxiliaries may weigh more than 12,000 t (10,885
tm), requiring the equivalent of 500 railroad cars to
ship the material to the site over a period of several
months. The modularized construction practices in use
today result in some boiler components weighing 400
to 1000 t (363 to 907 tm). Flue gas desulfurization
(FGD or scrubber) and selective catalytic reduction
(SCR) system modules for environmental retrofit work
may weigh between 50 to 150 tons (45 to 136 tm). In
these cases, overland and barge shipments can be- Fig. 1 Modern power plant construction includes appropriate
come unique operations. environmental equipment.
250 Craft 3
Craft 2
Direct costs 200 Craft 1
The direct costs associated with field construction
are developed and tied to a detailed task list by ap- 150
Installation factors 0
Following the direct cost estimate, several specific 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 42 45 47
factors are considered to finalize the direct work hour Weeks
requirements for each activity. These factors include Fig. 3 Typical labor requirements for a single boiler unit.
conducts a detailed planning session. Typical partici- formed to integrate design and construction consid-
pants include the project manager, scheduler/planner, erations, assuring a technically complete and
project superintendent(s), and other contributors as constructable design.
selected by the project manager. The basis for this An initial project kickoff period provides a detailed
planning session is the scope of work as originally project definition before any engineering releases are
defined and estimated, and the existing conditions of authorized. This definition period permits all involved
the construction site. During the session, missed scope to clarify details and better define owner and engi-
items or recent customer-initiated changes to the as- neering requirements. This phase is used to:
bid project are evaluated. The primary objective of this
1. document owner design, operating and mainte-
session is to document a detailed construction plan.
nance philosophy,
The information inputs needed and the outputs from
2. jointly review the specifications,
a successful planning session are shown in Table 1.
3. review subcontract vendor specifications,
Projects are defined by a series of work activities
4. allow the owner to review acceptable vendors,
arranged in a logical sequence. Detailed schedules are
5. establish procedures for project execution, and
then developed by sequencing all activities according
6. firmly establish the project’s schedule.
to their predecessor/successor relationships. These re-
lationships are used to assign activity durations, and A project team is utilized to effectively manage and
to allocate resources to complete the activity within the coordinate the multiple interfaces required for a large
desired time period. Resource allocations typically in- project. This team will establish all procedures and
clude labor plus heavy and specialized equipment.
Work activities are arranged into a work breakdown
structure and assigned activity codes. The activity
codes allow the work to be sorted by contract, area of Table 1
work, responsibility, component, or other required fac- Construction Planning Session
tors. These activities can then be used to monitor and Inputs and Outputs
track progress throughout the course of the project.
Schedules are established using computer-based Session Inputs
scheduling systems. A broad range of detailed graphic
schedules and reports, including time scale logic dia- Integrated overall project schedule
grams, bar charts, precedence diagrams, labor graphs, Contract documents such as commercial terms and
conditions and technical scope
earned value curves and job completion percentages Final estimate including worksheets and specified
are derived from such systems. These outputs permit material quantities
the overall coordination of several items: the work to Subcontract scope and commitments
be performed, labor by craft or specialty, erection Material and equipment delivery schedules and
equipment assignments, material deliveries, and criti- configurations
cal resource requirements. The goal of the planning Prior site reviews
session is to initially define the project in enough de- Customer/plant knowledge
tail to ensure that subsequent tracking and monitor- Labor agreements and availability
ing activities can effectively control all resources and
job progress, identify positive and negative deviations, Session Outputs
and prescribe necessary corrective actions. Detailed construction project management (CPM)
The level of detail developed in the work breakdown schedule and associated reports
structure is dependent on project complexity. Straight- Project safety plan
forward, short duration projects may be broken down Manpower loading and leveling
into less than fifty activities, whereas more complex, Equipment and critical resource loading and leveling
long-term projects may be defined by hundreds. Identification of subcontract work scope and schedule
requirements
Project work assignments for support disciplines
Construction project management Site organization chart
Earned value curves (measurement of performance
The successful completion of a large utility construc- against a detailed plan to predict final costs and
tion project requires a disciplined and proven approach schedule)*
for executing design, engineering, procurement, ex- Financial reporting
pediting, erection, inspection and commissioning. This Material delivery schedule
approach is required whether the project involves new Preferred material configuration
boiler erection, significant modifications to an exist- Modularization
ing unit, or the retrofit of environmental equipment. Field weld locations
Detailed project execution plans are developed to en- Maximum component rigging weight
Maximum component size
sure proactive control of scope, safety, quality, cost and Baseline weekly progress report format
schedule; report progress; identify deviations; forecast
trends; take corrective actions when necessary; pro- * Reference − Fleming, Quentin W. and Koppelman, Joel M.,
mote communications; and coordinate the activities of Earned Value Project Management, Project Management
all participants. The project team is responsible to Institute, Inc., Pennsylvania, September, 2000.
ensure that timely constructability reviews are per-
controls required for the coordination and routing of project managers, superintendents, and construction
documentation, design and engineering information, engineers work hand-in-hand with the engineering
technical interfaces, and correspondence. groups early in a project’s development cycle.
Once the construction phase of a project begins, the Since construction costs for some projects can ex-
site organization serves as the primary conduit for ceed 50% of a total project, the cost of labor presents
communication. Regular project meetings keep all par- both the greatest opportunity and greatest risk for
ticipants informed. almost any project. A design for constructability seeks
The key element of the project management ap- to minimize impacts and improve productivity through
proach is the scope-of-work document. Each working the elimination of rework and/or corrective action,
group involved in the project will develop a definition improve material deliveries, and incorporate some type
of objectives, scope of work for their activities, data col- of modularization.
lection needs, methodology or approach to the work,
end products, responsibilities for all involved, time du- Implementation
rations and schedules. Typical barriers to constructability implementation,
An integrated project schedule and report is devel- as identified by CII, include lack of disciplined coordi-
oped to cover all activities by involved participants. nation, failure to dedicate an individual administra-
Monthly progress reporting and performance measure- tor, and improper funding for the overall program. For
ments are completed using the earned value concept. a constructability program to be effective, these bar-
Schedule trends/projections are evaluated with action riers must be recognized and overcome.
plans formulated to regain or advance the schedule
targets included in each progress report. Outstanding Evaluation
or new actions are included. Potential threats to the
project’s goals are identified with alternative sugges- To help evaluate constructability efforts, feedback is
tions to reduce or eliminate any negative impact. needed throughout the project. During construction, it
is important to obtain an objective assessment of the
design documents from contractors and subcontractors.
Design for constructability Coordination and distribution of design drawings
The Construction Industry Institute (CII) defines will be monitored and reviewed prior to issuance for
constructability as a process of optimum integration construction. Innovative approaches, erection se-
of construction knowledge and experience into project quences, and cost saving measures will be reviewed
planning, design, procurement, and field operations to assure that the final product exhibits construction-
to achieve overall project objectives.1 CII recognizes friendly components. Constructability will also con-
that maximum benefits are achieved when people tribute to minimizing interference with existing plant
with construction knowledge and experience are in- facilities, thereby minimizing the effects on the oper-
volved with the project from its inception, and continue ating facility.
throughout its duration. The significance of this phi- The benefits are most evident during the construc-
losophy is best illustrated by Fig. 4. The ability to in- tion phase of a project once engineering and procure-
fluence overall project costs is greatest at the begin- ment are essentially complete. If flexibility in the
ning of the project and diminishes asymptotically with project schedule has already been consumed by engi-
the progression of time. neering and procurement, the cost impact on the
In the past, the term constructability was gener- project becomes significant. The cost of a day’s delay
ally associated with the quality of the various engi- early in a project is minimal, whereas, once construc-
neering groups’ approaches to erecting components. tion has started, costs could exceed 100,000 U.S. dol-
Specifically, it referred to issues or potential assump- lars for each day of delay. Savings and benefits lie in
tions made in association with the designer’s intent the reliability and predictability provided to the con-
that could preclude a component from being satisfac- struction plan through the efficient use of labor and
torily built or inspected (including errors and omis- equipment. Every job will have its share of delays due
sions). Information that lacked clarity was typically to late deliveries, equipment failure, and acts of na-
resolved through various means including drawing ture. Therefore, the goal of constructability is to se-
revisions, requests for information, engineering memo- lect those attributes of the project that can be controlled
randa, and nonconformance reports. Resolution al- and then exercise maximum influence over those of-
most always increased cost as a result of rework and/ fering the largest payback. The proper utilization of
or field delays while awaiting the design engineers’ constructability minimizes project risks such as labor
disposition. Many long-term projects now implement availability and maximizes opportunities through
constructability reviews of these design outputs prior productivity improvements.
to the start of construction.
The endorsement of CII’s philosophy and recogni- Integrated design process for retrofits
tion of its inherent benefits provides the foundation The integrated design process requires close coor-
for a successful project. The common goal is to ensure dination of design, manufacture, shipping and con-
the timely delivery of quality steam generation and struction processes. Retrofit projects for complex util-
environmental control equipment that is erected ity systems are unique and therefore require a signifi-
safely, efficiently, and cost effectively, subject to spe- cant amount of design integration. Several key steps
cific project constraints. This is accomplished when the are critical when these retrofit projects are considered:
environment. The integration of technology into the ing and compacting at the site. Other concurrent site
construction process increases the opportunity to ac- activities must be evaluated when planning for
complish these goals through the proper, effective and modularization.
innovative application of means, methods, techniques, Construction participation by all involved parties is
tooling and equipment. required in planning any project to enhance
A construction technology group normally supports constructability and identify intended erection methods.
the field construction program. These engineers pro- The erection method is influenced by the following factors.
vide construction engineering services, construction Retrofit versus new plant installation The construc-
logistics, and constructability reviews for each specific tion logistics associated with retrofitting, repairing or
product and configuration. Typical outputs include altering an existing unit are much different from those
recommended shipping sizes and configurations, rig- required for constructing a new unit. Logistics for new
ging weight and center of gravity calculations, crane plant construction are further diversified, depending
placement drawings, heavy lift and hauling plans, on whether the unit is to be built on an existing plant
and structural analyses of existing facilities for im- site, adjacent to existing units, or on a new site. Ret-
posed construction loads. rofit operations are generally performed in a pre-out-
age/outage/post-outage mode.
Approaches to construction – In planning retrofit work, an erection method that
erection methodology permits performing many tasks concurrently is cho-
There are three basic approaches that may be used sen. This optimizes equipment and labor and mini-
in a construction project: 1) knocked down, the tradi- mizes outage times. When constructing on an exist-
tional method, 2) field modularization, and 3) shop ing plant site, the erection method must maintain a
modularization. The knocked down approach is based productive interface between construction activities
on the erection of shop fabricated, standard-sized ship- and ongoing plant operations. Construction on a new
ping units that readily fit on a truck/trailer or rail car. site offers a contractor the greatest amount of freedom
The standard shipping units are erected one piece at in selecting the most cost-effective, efficient method for
a time in stick fashion. Field modularization combines executing the work; however, potential obstructions in-
these traditional ship units into larger components, or clude those areas of work occupied by other contractors.
modules, at the construction site for final installation. Plant arrangement The overall plant arrangement
Off-site assembly, shop modularization, or prefabrica- plays a key role in establishing the sequence for erect-
tion combine the traditional ship units into subassem- ing components and equipment. Plant arrangement
blies at the manufacturer’s plant. defines the available access routes for material flow
Modularization is an integrated approach to power from the laydown and storage areas to the final in-
plant construction whose concepts must be incorpo- stallation points.
rated at the earliest possible stages of a project’s plan- Scope The scope of work directly affects the con-
ning. The most successful projects have continued com- struction plan and completion of the construction.
mitment to this approach by the customer, the equip- Tools and equipment needed for one phase of the
ment supplier, and the erecting contractor. project may also be influenced by the requirements
While modularization may be cost effective, the ex- of other phases.
tent of effective modularization is site specific. Parameters Product and component parameters,
Modularization divides plant materials into subsets, including size, weight and shipping configurations,
or modules, that are assembled before being brought dictate the type and size of material handling equip-
to the construction site. (See Fig. 5.) The degree and
extent of modularization can vary considerably. In its
simplest form, a structural steel beam with shop-at-
tached clip angles is a module. At the opposite end of
the scale, a shop-assembled boiler complete with all
trim piping, instrumentation, and insulation and lag-
ging, or a 50-ton section of ductwork insulated and
lagged is also considered a module.
Boiler components have been modularized for some
time. Fig. 6 depicts furnace wall panels in which loose
boiler tubing and membrane stock are welded to form the
panels. Large modularized scrubber components are
shown in Fig. 7.
A modularized project requires more engineering
and design time than a conventional project. Planning
must consider the water and land routes used for ship-
ping the modules. Construction sites located on navi-
gable waterways have the greatest potential for ship-
ment of large modularized components. (See Fig. 8.)
Module unloading, site movements and erection
procedures must be carefully considered. Special con-
sideration must also be given to foundations, backfill- Fig. 5 Large scrubber modular components on a barge.
“Chicago Boom”
W
W
Monorail
Hoist and Load
W Blocks
Track System
on Rollers W
Taut Line or Cableway
System
with the ASME Code must be inspected by an autho- cant dividends over stick-built construction at the job
rized inspector at various stages of assembly to assure site. The project benefits in both labor savings and in
that all Code requirements are met. the potential for a reduced site completion schedule
Section I of the ASME Code contains requirements when high-cost field labor is replaced with lower-cost
for the installation of power boilers. ASME B31.1 con- shop labor.
tains requirements for the installation of boiler and The construction principles utilized for environmen-
non-boiler external piping. The state or jurisdictional tal equipment are the same. However, the method of
authority maintains rules and regulations that gov- construction differs significantly. SCR projects predomi-
ern the installation of boilers and establishes the ap- nantly consist of structural steel and fabricated plate,
plicable governing Codes. Section I of the ASME Code while FGD system projects consist of fabricated plate,
has been adopted by law in most states or jurisdictions. structural steel, process equipment and piping. There is
Whereas ASME governs new construction, the NBIC little in the way of operating equipment with the excep-
governs repairs and alterations to boilers and other tion of dampers, sonic horns or sootblowers, ammonia
pressure-retaining items. The NBIC requires the repairs vaporization equipment, and some piping and instru-
and/or alterations to comply, to the extent possible, with mentation. In these installations, the chemical process
the original Code of construction. As with the ASME required to support the operation utilizes additional
Code, the NBIC is mandatory only when adopted by a equipment to handle the lime or limestone reagents and
state or other jurisdictional authority. gypsum removal and drying.
Section I of the ASME Code specifies the nonde- Most SCR projects are designed with the reactor
structive examination (NDE) requirements for new and flues bottom-supported off structural steel. The
construction of power boilers. ASME B31.1 specifies primary component of FGD systems is the absorber
the NDE requirements for boiler and non-boiler ex- tower which is independently bottom-supported on a
ternal piping. NDE requirements for repairs and al- separate foundation. For SCR systems, close coordi-
terations are specified in the NBIC. The type and ex- nation is required between steel erection activities and
tent of NDE must be considered during the proposal, the installation of the interconnecting flues and reac-
planning and scheduling processes. For all construc- tor. Complicating matters on a retrofit project is the
tion, the applicable regulations and any additional space available for the SCR. The process temperature
NDE requirements exceeding the Code should clearly for most SCR systems requires the boiler flue gas to
be specified in contract documents. The nondestruc- be taken from an area immediately downstream of the
tive technologies are discussed in more depth in Chap- economizer, and before the air heater inlet. On large
ters 38 and 45. boilers, this tie-in point can be more than one hun-
dred feet (tens of meters) above ground level. Also,
since a reactor can contain nearly a million pounds
Construction of environmental equipment (450,000 kg) of catalyst at a significant elevation
Regulatory requirements associated with the Clean above grade, concerns for overturn and uplift forces
Air Act Amendments of 1990 caused many fossil fuel- may require a complex foundation design.
fired electric generating plants in the United States At many sites constructed decades ago, little con-
(U.S.) to install, or plan for the installation of, emis- sideration was given to future expansion and there-
sion reduction equipment. Many stations installed fore, current space limitations are a serious concern.
sulfur dioxide (SO2) scrubbers in the early 1990s which Many projects are faced with a significant rerouting
were then followed in the early 2000s by the installa- of the boiler exit gas to a point where space is avail-
tion of selective catalytic reduction (SCR) systems for able for either an SCR or FGD system. The flue gas must
nitrogen oxides (NOx) removal. then be routed back to continue its path through the air
While erection of environmental equipment is sig- heater for SCR applications or to the stack for FGD sys-
nificantly different from boiler erection, many of the tems. Each project poses a unique set of circumstances.
same principles and attributes of boiler erection ap-
ply. A modularized approach generally pays signifi- Sequencing and modularization
Early in the project, specific information about the
weight of ductwork sections and equipment must be
estimated. Many times the module boundaries are eas-
ily identified, due to equipment terminal points or ex-
pansion joint locations. Other times, sound judgments
must be made, based on experience. The erector is the
prime contributor to determining splice locations that
are best from a variety of standpoints, including ac-
cess, crane capacity and geometry.
The resulting erection sequence can then be used
in establishing schedule priorities for detail design,
material procurement and fabrication. To allow maxi-
mum flexibility for installation, schedule priorities
should be developed in accordance with erection plans.
Receiving materials far in advance of the time re-
Fig. 22 Welded handhole fitting for higher pressure boilers. quired at the job, or in a sequence that does not sup-
port planned erection, results in increased handling quires dampers and blanking plates to allow the bal-
costs. Without the proper materials, the constructor is ance of construction to take place subsequent to the tie-
forced to work on activities that deviate from the in- in. The blanking plates allow safe entry to the flues
tended plan, increasing overall project cost. during plant operation. However, this approach gen-
The erector should complete a constructability re- erally impacts the erection sequence and potentially im-
view prior to the issuance of key design outputs. This pacts the total construction cost. A second, shorter out-
review often uncovers missing or incorrect informa- age is then required to make the final tie-in of fluework.
tion. Early identification of potential problems can al-
leviate costly field rework or production delays due to
additional engineering evaluations and the resulting Construction safety
drawing revisions. A comprehensive safety program must be imple-
Once modules are identified and an erection se- mented at each construction site. The objective is to pro-
quence is established, the project team interacts with mote an awareness of safety among personnel and cre-
plate fabricators for delivery options. A modular con- ate a safe working environment to prevent injuries.
struction approach provides the project team with the BWCC has developed a Safety Program Manual in sup-
opportunity to review and approve the manufacturer’s port of a construction site safety program. The manual
plan for component fabrication. This process may re- has been specifically designed for construction and in-
sult in on-site productivity improvements as the con- cludes the requirements of 29 CFR 1926 Safety and
structor advises on alternative shipping configurations Health Regulations for Construction by the Occupa-
and rigging requirements, and gains valuable infor- tional Safety and Health Administration (OSHA). The
mation about the material to be received, thus help- contents of the Safety Program Manual include, but are
ing to identify the extent of preparatory work that will not limited to, the safety procedures outlined in Table 2.
be required on site prior to erection.
Fig. 23 is a typical arrangement for an SCR retro-
fit project. Identified in the figure are module bound- Internal cleanliness of pressure parts
aries utilized for design, procurement, planning and
erection activities. The individual modules are installed Manufacturing and shipping
in a defined sequence to maximize efficiency and mini- Many problems can develop during operations be-
mize erection time. This sequence, which usually starts cause of dirt or other foreign matter in the circulating
from the lowest to the highest point, builds from the system of a boiler. During the fabrication of drums,
reactor back to the boiler and involves the erection of tubes, headers, pipes or other pressure parts, precau-
sufficient steel to set the outlet or bypass flues. Once tionary measures must be taken to assure internal
the initial flues are set, steel progresses again to the cleanliness. For boilers that use welded stub construc-
point where additional flue sections can be set and the tion, the ends of all tubes and pipes, as well as the
reactor built. Ideally, horizontal runs of ductwork are stubs in the drums and headers, are closed with metal
bottom-supported, and require that the support steel caps and sealed with plastic tape. This usually makes
is first installed beneath the duct. Structural engineers it unnecessary to clean these components in the field.
should be aware of the construction/erection plan so Inevitably there are a few closure caps displaced dur-
that the steel erection sequence and requirements ing shipping, unloading and handling. In such in-
support the equipment’s erection sequence. These ac- stances, the construction crew must examine the com-
tivities require close coordination with the design en- ponents involved, perform any necessary cleaning,
gineers to ensure that the uncompleted steel structure and replace the caps as soon as possible.
is adequate to support the initial duct sections as they
are installed. Cover-plating the existing steel is fre- Field assembly
quently required prior to imposing additional loads Boiler pressure parts should be searched before
from the new structure and can be a time-consuming handhole and manhole closure fittings are installed.
and costly effort. If present, lead-based paint must be Reasonably straight tubes between headers or drums
abated from existing steel prior to any welding or may be probed by passing a ball through them. Bent
grinding operations. The use of bolt interface connec- tubes that will not clear themselves of foreign material
tions rather than welded connections could minimize by gravity may be probed by blowing a tight-fitting
lead abatement requirements. Close coordination with sponge through them. The butt welds in small diam-
plant operations is also required as a result of the eter tubes are examined radiographically for misalign-
numerous interferences with plant utilities supported ment or obstructions that may cause flow restrictions.
from the columns or beams being modified. Headers are checked with a light and mirror immedi-
Tie-in to the unit is the last activity phase, accom- ately before the end handhole fittings are installed.
plished during a planned unit outage. Depending No foreign material may enter the pressure part sys-
upon planned unit outages, however, there is flexibil- tem during assembly. Closures are left in place until re-
ity in the erection sequence. Many times a tie-in out- moval for welding or positioning equipment. If shop-in-
age occurs before construction of the SCR is initiated, stalled closures are removed to permit installation, tem-
especially if the plant has a major outage scheduled porary closures are placed over the openings to prevent
well in advance of the SCR completion. In these in- debris from entering the equipment. Prior to flushing or
stances, a gas bypass flue is installed which allows the final closing of equipment, a visual inspection is made
construction of the SCR during unit operation. This re- and foreign objects are removed from the equipment.
Expansion Joint
Damper Catalyst
Block
Future
Expansion Joint Catalyst
Sonic
Damper Damper Horn Block
Expansion
Joint
Economizer
Expansion
Joint
Expansion
Expansion Joint
Joint
Damper
Expansion
Joint
Air Heater
Removal of tube sections during repair or alteration at least 70F (21C). Nondrainable superheaters and
must be performed in a manner that prevents foreign reheaters are filled with demineralized water or con-
material from entering the tubes during the cutting densate, if available. As a boiler is being filled, it is
operation. Ends of existing tubes are plugged before vented at every available connection to allow water
machining new weld preparations. to reach every circuit.
Hydrostatic pressure is applied after the boiler is
filled. If a boiler feed pump or other high capacity
Post-construction testing pump is used, precautions must be taken to control the
pressure at all times. While water is being pumped into
Hydrostatic testing the boiler, continuous inspection is made to detect any
When all pressure part connections have been com- leakage. During hydrostatic testing, safety precau-
pleted, the steam generating unit is tested at a pres- tions must be observed, and nonessential personnel
sure specified by the applicable code; this is usually must be kept away from the test area.
1.5 times the maximum allowable working pressure The test pressure must be held long enough to al-
(MAWP). Before the test is applied, a final inspection low minute leaks to be detected. Following this hold-
is made of all welding. External connections, including ing period, pressure is reduced to MAWP and retained
all fittings, are completed within Code requirements. for an inspection period. During final inspection, ev-
Connections for flange safety valves are usually blanked. ery area of the pressure system is viewed for leakage
Welded safety valves are closed with an internal plug. and repaired if necessary.
Hydrostatic testing water must be clean and warm After inspection, the unit is drained and all
enough to bring pressure part metal temperatures to nondrainable parts are protected from freezing, if nec-
essary. The refractory, insulation and casing work are Refractory materials
then completed in areas left open for inspection. The furnace and other wall areas of modern fossil
Air testing fuel boilers are made almost entirely of water-cooled
tubes. The increased use of membrane walls has re-
Gas-bearing components, such as the boiler, flues duced the use of refractory in these areas. However,
and ducts are field-tested for leakage and tightness. castable and plastic refractories may still be used to
All boilers are tested by one of two procedures. Boil- seal flat studded areas, wall penetrations, and door
ers designed to operate with a positive pressure, and wall box seals. (See Chapter 23.)
wherein furnace leaks would emit gases from the Other than membrane wall construction, when
boiler setting, are tested following a pressure-fired tubes are tangent or flat studded, several types of plas-
procedure. Units designed for suction or balanced tic refractory materials are applied to the outside of
draft are tested following the balanced draft procedure. tubes for insulation or sealing purposes. When an
The pressure-fired air test procedure is a pressure inner casing is to be applied directly against the tubes,
drop test. A test is considered satisfactory when the the refractory serves principally as an inert filler
pressure is raised to 15 in. wg (3.74 kPa) maximum material for the lanes between tubes. It has a binder
and does not drop more than 5 in. wg (1.25 kPa) in that cements it to the tubes and it is troweled flush
ten minutes. If pressure can not be maintained, leaks with the surface of the wall.
are sought and corrected and the test is rerun until Smaller boilers may have furnaces constructed of
satisfactory tightness is achieved. On large units, it is tubes on wide-spaced centers backed with a layer of
common to install temporary bulkheads in flue and brick or tile. Brickwork of this type is supported by the
duct runs for individual tests. pressure parts and held in place by studs. The brick
The balanced draft testing procedure is commonly is insulated and made air-tight by various combina-
performed by pressurizing the system with the forced tions of plastic refractory, plastic or block insulation
draft fan while throttling the dampers at the downstream and casing.
test terminal. With the system pressurized, all field welds High quality workmanship is mandatory in the ap-
are inspected by sight and sound to detect leaks. plication of refractory material. Construction details
are clearly outlined on drawings and instructions that
Assembly of nonpressure parts also designate the materials to be used. These mate-
rials must be applied to correct contour and thickness
and auxiliaries without voids or excessive cracking. Skilled mechan-
While pressure parts are being assembled and ics and close supervision are essential.
tested, work is in progress on nonpressure parts and
auxiliary equipment. These components, including air Casing
heaters, fuel equipment, fans, duct work, refractory, In general, inner or outer boiler casing is used in
insulation and casing, require a large portion of the areas that are not membraned. Outer casing is applied
construction labor. They must be scheduled with con- outside of insulating materials and has, for the most
sideration for items that must be assembled in a pre- part, been replaced by sheet metal lagging. Inner cas-
scribed sequence. For example, air heaters are fin- ing is positioned inside of insulation and may be pres-
ished prior to erection of flues and ducts. Pulverizers sure or nonpressure casing.
are placed early enough for piping, drives and other The primary purpose of pressure inner casing is to
auxiliaries to be completed. prevent air and gas leakage from a steam generating
unit. The inner casing is seal welded to prevent leak-
age from the boiler setting and also serves as a base
for the application of insulation and lagging.
Table 2 In most cases, modern boiler casings feature welded
Selected BWCC Safety Procedures construction. For pressure casing, it is essential that the
for Construction strength of the weld equal the strength of the plate, that
the welds be free of cracks and pinholes, and that they
Posting requirements Welding, thermal cutting and present a good appearance. For pressure casing, tight-
Medical facilities and compressed gas cylinders ness is checked by a pressure drop air test. Nonpressure
treatment Fire protection casings are given a thorough visual inspection.
Safety training Steel erection
Hazard communication Confined space entry Insulation
Accident and personal Lockout/tagout
injury reporting Excavation and trenching Selecting the type and thickness of insulation applied
Personal protective Radiation protection to boiler surfaces is an essential part of the design work.
equipment Documentation and record- Specifications are written and drawings are made to indi-
Job safety analysis keeping cate the applied materials and the method of attachment.
Housekeeping Project site safety inspections Typical standards specify insulation blocks or insu-
Operator pre-qualification Subcontractor safety lation blankets. Some plastic insulation is used for fill-
Lifting equipment Material safety data sheets ing voids. The thickness of the insulation for all sur-
Hand tools Fall protection
faces is selected to give a specific surface temperature,
Electrical Floor, wall openings and
Scaffolds and ladders stairways e.g., 130F (54C) with 80F (27C) ambient air tempera-
ture and 50 ft/s (15.2 m/s) surface velocity. The prime
requisites for installing boiler insulation are that the is reasonable and it is extensively used in both indoor
material be tight, free of voids, well anchored, and re- and outdoor installations.
inforced where necessary.
Ductwork with heavy stiffeners at frequent inter-
vals presents a difficult insulating job. With the stiff- Pre-operational inspection
eners outside the flue and duct plate, the insulation A final inspection is made after erection work is com-
thickness is often increased over minimum require- pleted and the unit is ready for operation. This is the
ments to assure adequate coverage of the stiffeners. combined responsibility of the erection, service and
If the stiffeners are placed in a manner where stan- operating organizations.
dard insulation coverage is too costly, the insulation Externally, all components of the unit are checked
may be placed over the stiffeners. As an alternative, for expansion clearances. Obscure corners are exam-
inner lagging may be applied over the stiffeners and ined for any construction blocking or bracing that
the minimum required insulation is placed over the might have been left in place. Points reviewed for ex-
lagging. When insulation is applied at an appreciable pansion clearances are platforms and walkways con-
distance from a hot surface with a long vertical run, structed adjacent to external members that move with
air may circulate in the void. This increases heat the unit.
transfer into the insulation, which is undesirable. Of special importance in fossil fuel units is the re-
Where vertical runs exceed 10 ft (3 m), horizontal moval of combustible materials that may present an
barriers are installed between the duct and/or tube explosion hazard during initial firing. Internal cavi-
wall and insulation. ties are checked to ensure that all debris has been re-
moved. Tubes are given a final inspection for align-
Sheet metal lagging ment, particularly those that might interfere with
Outdoor boilers require the use of a durable water- sootblower operations. Movable connections between
proof lagging. A light gauge metal lagging (galvanized tubes are examined for expansion clearances and to
steel or aluminum) or outer casing is used on walls, see that all attachments are properly anchored.
flues, ducts, air heaters, vestibules, windboxes, down- On most units, construction schedules do not per-
comers, steam/water lines and other exposed compo- mit completion of insulation before the unit is fired. It
nents. The metal covering does not seal against air is important that this work be completed in areas that
infiltration but serves as a barrier to protect the insu- will be inaccessible or cause a safety hazard when the
lation against water and physical damage. The cost unit is in operation.
References
1. Constructability: A Primer, Publication 3-1, the Con- 2. Shapiro, H.I., Shapiro, J.P., and Shapiro, L.K., Ed.,
struction Industry Institute, Constructability Task Force, Cranes & Derricks, McGraw-Hill Education, November,
Bureau of Engineering Research, The University of Texas 1980.
at Austin, Austin, Texas, Third Printing, April, 1990.