You are on page 1of 20

The Babcock & Wilcox Company

Chapter 39
Construction

Construction plays a major role in the success of any The field assembly of power generation facilities and
project. The construction organization must employ the associated environmental equipment requires ef-
erection techniques that complement the designers’ ficient, well engineered, well organized erection meth-
skill and the fabricators’ craftsmanship. Sound field ods to permit installation within a reasonable time and
assembly is essential for correct functional perfor- at minimum cost without sacrificing quality and safety.
mance of the completed installation. Efficient and safe Modularization of complex components together with
execution of any project requires that components be continuous advances in computerized drafting, mod-
on the job site at the right time along with the neces- eling, scheduling and tracking have become the norm
sary tools, equipment, labor and supervision. In ad- for these complex or fast track projects. The cost of
dition to properly erecting the components, a success- erecting a steam generating unit, such as that shown
ful construction organization possesses experience in in Fig. 1 represents a significant part of the total in-
estimating, planning, safety, quality control, cost vestment in the plant.
analysis, labor relations, tool and equipment design, Retrofitting an existing plant with environmental
technical services, and finance and accounting. A com- equipment presents a unique set of challenges requir-
petitive marketplace requires continuous improve- ing extensive planning and coordination between
ments in quality, safety and cost, together with reduced owners, engineers, manufacturers and constructors.
construction schedules, as contractors and owners strive (See Fig. 2.)
to minimize project costs and schedules. The most suc-
cessful projects maintain communication between engi-
neering and manufacturing operations, ensuring that
field erection is a continuation of the shop fabrication
process and not a completely independent event.
During initial project development, the construction
plan and work performance logistics must be evalu-
ated, then incorporated into the overall project design.
Schedule requirements, together with safety and site-
specific conditions, will affect the labor and erection
methods that will be used.
A number of boiler types are small enough to per-
mit shipment completely assembled. However, larger
industrial boilers, central station boilers, and environ-
mental systems are shipped to job sites in various
stages of fabrication and subassembly. A central sta-
tion boiler with its associated heat transfer equipment
and auxiliaries may weigh more than 12,000 t (10,885
tm), requiring the equivalent of 500 railroad cars to
ship the material to the site over a period of several
months. The modularized construction practices in use
today result in some boiler components weighing 400
to 1000 t (363 to 907 tm). Flue gas desulfurization
(FGD or scrubber) and selective catalytic reduction
(SCR) system modules for environmental retrofit work
may weigh between 50 to 150 tons (45 to 136 tm). In
these cases, overland and barge shipments can be- Fig. 1 Modern power plant construction includes appropriate
come unique operations. environmental equipment.

Steam 41 / Construction 39-1


The Babcock & Wilcox Company

local labor productivity, overtime and multiple shift


work inefficiencies, repair difficulty factors, and site-
specific conditions.
Indirect labor and support requirements
Once the direct work hour costs have been devel-
oped, indirect labor support requirements can be ap-
plied. These are driven by man days and individuals
available for the project timeline. Examples include
the general foreman, laborers, operating engineers,
unloading crews, and any other individuals needed to
support the installation labor activities.
Other factors
While detailed estimates are required for specific
projects, total estimates for nominal scope jobs fre-
quently fall into general ranges. For coal-fired utility
boilers of nominal scope, erection work hours usually
Fig. 2 SCR retrofit construction. range from 1.25 to 2.0 work hours per kilowatt. In
other cases such as retrofit SCRs or FGD systems, the
estimates do not fit such ranges well because of the
Estimating and cost development dramatically different equipment scopes and configu-
The estimating process begins with a complete un- rations possible for a given size unit.
derstanding of the project work scope and specifications The estimated time required to complete a project
for performance. The estimator prepares a detailed list is related to the number of estimated work hours.
of work activities or tasks for the entire project utiliz- There is a limit, however, for any given unit, to the
ing specifications and drawings obtained from the number of workers that can be efficiently employed.
owner and the component supplier’s engineering func- If more than an optimum number are employed, the
tion. Direct work hours for each labor category are lack of adequate work space results in diminishing
then assigned to each activity based upon historical returns and excessive costs. Fig. 3 shows the typical
data and general experience. For example, insulation number of weeks required for various work hour ex-
is estimated based upon the number of hours per unit penditures for a single boiler unit, and the maximum
area [ft2 (m2)] times the insulated area of the proposed number of people utilized during peak operations.
equipment. The total hours for each craft and for the Erection time span can also be affected by perform-
total project are then calculated. The totals are fre- ing on a multiple shift or overtime basis. With these
quently corrected for a variety of factors, e.g., local alternatives, significant additional costs can be in-
labor productivity, overtime and site factors. To the curred due to the inefficiency resulting from working
direct labor total, indirect labor such as supervisors, longer hours, hours not worked, fatigue, or shift turn-
foremen and housekeeping, etc., are added to produce over inefficiencies.
a total project estimate.
Scope Schedule and project plan development
Historical performance, accumulated through on- The construction schedule is a key input to the in-
going experience and applied through an estimating tegrated project schedules that focus on all of the dis-
database, provides the basis for the initial estimate. ciplines needed to complete a given project.
The estimating process utilizes a variety of sources to Upon contract award, the construction project team
develop a detailed understanding of a project’s specific
work scope. These sources include product specifica-
tions, equipment and layout drawings, site visits, cus- 300
tomer interaction, engineering, and internal data de-
veloped from experience on similar projects.
Average Workforce Per Week

250 Craft 3
Craft 2
Direct costs 200 Craft 1
The direct costs associated with field construction
are developed and tied to a detailed task list by ap- 150

plying historical work hour rates associated with a spe- 100


cific quantity of material. These quantities may in-
clude tonnage, linear feet or square feet (meters). 50

Installation factors 0
Following the direct cost estimate, several specific 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 42 45 47
factors are considered to finalize the direct work hour Weeks
requirements for each activity. These factors include Fig. 3 Typical labor requirements for a single boiler unit.

39-2 Steam 41 / Construction


The Babcock & Wilcox Company

conducts a detailed planning session. Typical partici- formed to integrate design and construction consid-
pants include the project manager, scheduler/planner, erations, assuring a technically complete and
project superintendent(s), and other contributors as constructable design.
selected by the project manager. The basis for this An initial project kickoff period provides a detailed
planning session is the scope of work as originally project definition before any engineering releases are
defined and estimated, and the existing conditions of authorized. This definition period permits all involved
the construction site. During the session, missed scope to clarify details and better define owner and engi-
items or recent customer-initiated changes to the as- neering requirements. This phase is used to:
bid project are evaluated. The primary objective of this
1. document owner design, operating and mainte-
session is to document a detailed construction plan.
nance philosophy,
The information inputs needed and the outputs from
2. jointly review the specifications,
a successful planning session are shown in Table 1.
3. review subcontract vendor specifications,
Projects are defined by a series of work activities
4. allow the owner to review acceptable vendors,
arranged in a logical sequence. Detailed schedules are
5. establish procedures for project execution, and
then developed by sequencing all activities according
6. firmly establish the project’s schedule.
to their predecessor/successor relationships. These re-
lationships are used to assign activity durations, and A project team is utilized to effectively manage and
to allocate resources to complete the activity within the coordinate the multiple interfaces required for a large
desired time period. Resource allocations typically in- project. This team will establish all procedures and
clude labor plus heavy and specialized equipment.
Work activities are arranged into a work breakdown
structure and assigned activity codes. The activity
codes allow the work to be sorted by contract, area of Table 1
work, responsibility, component, or other required fac- Construction Planning Session
tors. These activities can then be used to monitor and Inputs and Outputs
track progress throughout the course of the project.
Schedules are established using computer-based Session Inputs
scheduling systems. A broad range of detailed graphic
schedules and reports, including time scale logic dia- Integrated overall project schedule
grams, bar charts, precedence diagrams, labor graphs, Contract documents such as commercial terms and
conditions and technical scope
earned value curves and job completion percentages Final estimate including worksheets and specified
are derived from such systems. These outputs permit material quantities
the overall coordination of several items: the work to Subcontract scope and commitments
be performed, labor by craft or specialty, erection Material and equipment delivery schedules and
equipment assignments, material deliveries, and criti- configurations
cal resource requirements. The goal of the planning Prior site reviews
session is to initially define the project in enough de- Customer/plant knowledge
tail to ensure that subsequent tracking and monitor- Labor agreements and availability
ing activities can effectively control all resources and
job progress, identify positive and negative deviations, Session Outputs
and prescribe necessary corrective actions. Detailed construction project management (CPM)
The level of detail developed in the work breakdown schedule and associated reports
structure is dependent on project complexity. Straight- Project safety plan
forward, short duration projects may be broken down Manpower loading and leveling
into less than fifty activities, whereas more complex, Equipment and critical resource loading and leveling
long-term projects may be defined by hundreds. Identification of subcontract work scope and schedule
requirements
Project work assignments for support disciplines
Construction project management Site organization chart
Earned value curves (measurement of performance
The successful completion of a large utility construc- against a detailed plan to predict final costs and
tion project requires a disciplined and proven approach schedule)*
for executing design, engineering, procurement, ex- Financial reporting
pediting, erection, inspection and commissioning. This Material delivery schedule
approach is required whether the project involves new Preferred material configuration
boiler erection, significant modifications to an exist- Modularization
ing unit, or the retrofit of environmental equipment. Field weld locations
Detailed project execution plans are developed to en- Maximum component rigging weight
Maximum component size
sure proactive control of scope, safety, quality, cost and Baseline weekly progress report format
schedule; report progress; identify deviations; forecast
trends; take corrective actions when necessary; pro- * Reference − Fleming, Quentin W. and Koppelman, Joel M.,
mote communications; and coordinate the activities of Earned Value Project Management, Project Management
all participants. The project team is responsible to Institute, Inc., Pennsylvania, September, 2000.
ensure that timely constructability reviews are per-

Steam 41 / Construction 39-3


The Babcock & Wilcox Company

controls required for the coordination and routing of project managers, superintendents, and construction
documentation, design and engineering information, engineers work hand-in-hand with the engineering
technical interfaces, and correspondence. groups early in a project’s development cycle.
Once the construction phase of a project begins, the Since construction costs for some projects can ex-
site organization serves as the primary conduit for ceed 50% of a total project, the cost of labor presents
communication. Regular project meetings keep all par- both the greatest opportunity and greatest risk for
ticipants informed. almost any project. A design for constructability seeks
The key element of the project management ap- to minimize impacts and improve productivity through
proach is the scope-of-work document. Each working the elimination of rework and/or corrective action,
group involved in the project will develop a definition improve material deliveries, and incorporate some type
of objectives, scope of work for their activities, data col- of modularization.
lection needs, methodology or approach to the work,
end products, responsibilities for all involved, time du- Implementation
rations and schedules. Typical barriers to constructability implementation,
An integrated project schedule and report is devel- as identified by CII, include lack of disciplined coordi-
oped to cover all activities by involved participants. nation, failure to dedicate an individual administra-
Monthly progress reporting and performance measure- tor, and improper funding for the overall program. For
ments are completed using the earned value concept. a constructability program to be effective, these bar-
Schedule trends/projections are evaluated with action riers must be recognized and overcome.
plans formulated to regain or advance the schedule
targets included in each progress report. Outstanding Evaluation
or new actions are included. Potential threats to the
project’s goals are identified with alternative sugges- To help evaluate constructability efforts, feedback is
tions to reduce or eliminate any negative impact. needed throughout the project. During construction, it
is important to obtain an objective assessment of the
design documents from contractors and subcontractors.
Design for constructability Coordination and distribution of design drawings
The Construction Industry Institute (CII) defines will be monitored and reviewed prior to issuance for
constructability as a process of optimum integration construction. Innovative approaches, erection se-
of construction knowledge and experience into project quences, and cost saving measures will be reviewed
planning, design, procurement, and field operations to assure that the final product exhibits construction-
to achieve overall project objectives.1 CII recognizes friendly components. Constructability will also con-
that maximum benefits are achieved when people tribute to minimizing interference with existing plant
with construction knowledge and experience are in- facilities, thereby minimizing the effects on the oper-
volved with the project from its inception, and continue ating facility.
throughout its duration. The significance of this phi- The benefits are most evident during the construc-
losophy is best illustrated by Fig. 4. The ability to in- tion phase of a project once engineering and procure-
fluence overall project costs is greatest at the begin- ment are essentially complete. If flexibility in the
ning of the project and diminishes asymptotically with project schedule has already been consumed by engi-
the progression of time. neering and procurement, the cost impact on the
In the past, the term constructability was gener- project becomes significant. The cost of a day’s delay
ally associated with the quality of the various engi- early in a project is minimal, whereas, once construc-
neering groups’ approaches to erecting components. tion has started, costs could exceed 100,000 U.S. dol-
Specifically, it referred to issues or potential assump- lars for each day of delay. Savings and benefits lie in
tions made in association with the designer’s intent the reliability and predictability provided to the con-
that could preclude a component from being satisfac- struction plan through the efficient use of labor and
torily built or inspected (including errors and omis- equipment. Every job will have its share of delays due
sions). Information that lacked clarity was typically to late deliveries, equipment failure, and acts of na-
resolved through various means including drawing ture. Therefore, the goal of constructability is to se-
revisions, requests for information, engineering memo- lect those attributes of the project that can be controlled
randa, and nonconformance reports. Resolution al- and then exercise maximum influence over those of-
most always increased cost as a result of rework and/ fering the largest payback. The proper utilization of
or field delays while awaiting the design engineers’ constructability minimizes project risks such as labor
disposition. Many long-term projects now implement availability and maximizes opportunities through
constructability reviews of these design outputs prior productivity improvements.
to the start of construction.
The endorsement of CII’s philosophy and recogni- Integrated design process for retrofits
tion of its inherent benefits provides the foundation The integrated design process requires close coor-
for a successful project. The common goal is to ensure dination of design, manufacture, shipping and con-
the timely delivery of quality steam generation and struction processes. Retrofit projects for complex util-
environmental control equipment that is erected ity systems are unique and therefore require a signifi-
safely, efficiently, and cost effectively, subject to spe- cant amount of design integration. Several key steps
cific project constraints. This is accomplished when the are critical when these retrofit projects are considered:

39-4 Steam 41 / Construction


The Babcock & Wilcox Company

1. Determine the detailed scope early in the process. High


2. Define the general arrangement of all components
in concert with existing structures and equipment. Conceptual Planning
3. Define the construction approach.
4. Perform joint project management, engineering

Ability to Influence Cost


Design
and construction reviews of the design.
5. Iterate the second, third, and fourth steps to ad-
vance and evolve the design. Procurement

The design/construction team must share a common


and detailed understanding of the defined scope as Construction

early as possible. This scope description and the re-


sulting assignment of responsibilities establish the Startup
direction of the project team.
Project definition for all members of the design and Low
construction team is not complete until participants Start
Time
Complete
have a clear spatial understanding of new equipment Fig. 4 The ability to influence cost diminishes as a construction
location within the existing facilities. Interferences are project progresses.
relatively inexpensive to resolve at the design stage,
but can be devastating to the project budget and
schedule if recognized during the construction process. schedule decisions are being defined and key subcon-
Large retrofit projects typically span 15 to 30 months tractors are being integrated into the project. Addi-
from award to startup. This span is dependent upon the tional resources are needed to focus on technical, com-
number of units to be retrofit, the complexity of the in- mercial and interface issues associated with subcon-
stallation, and the unit’s planned outage schedule. These tractors, architect-engineers, structural steel fabrica-
projects are impacted by numerous site-specific con- tors, and flue and duct fabricators. This support early
straints that may lengthen the overall project. in the project provides the necessary attention to ef-
When the total project and schedule integration fectively address schedule-critical activities during a
process is not followed, project management and en- time frame when resources are typically overloaded.
gineering will typically initiate the design process and Once these specialized functions are executed, these
begin the fabrication of materials well before the in- resources are dismissed and project team members
volvement of the construction manager and/or super- then consult as required.
intendent. This approach generally results in project
delays and increased costs after mobilization of the
construction team. Joint planning and an ongoing re- Construction technology
view of the design by team members from project man- The construction of steam and power generation
agement, engineering and construction have fre- facilities, and all associated equipment, is a complex
quently been shown to result in a high quality, safe, and challenging undertaking. Each project presents
economical, and on-schedule project. a unique set of objectives, subject to specific con-
Integrating the different perspectives, knowledge straints and opportunities. Successful projects are the
and concerns of these three key project disciplines result of detailed planning and forethought, as well
yields significant benefits. The first joint review only as the creative application of construction means and
begins the process. Ongoing reviews generate the methods to deal with the constraints, and to take ad-
greatest long-term benefits. Significant design and vantage of the opportunities. Critical decisions regard-
construction decisions must be made in ways that ing product configuration, constructability, construc-
balance the scope, schedule, and cost triangle to ben- tion equipment selection and labor issues must be
efit the overall project. made early and followed throughout the project.
Some of the key decisions that need to be addressed Traditionally, the construction site supervisor has
by the team are: acquired the necessary skills through experience, and
1. the best physical arrangement of the equipment, therefore is well-qualified. Technological advances in-
2. supports for the new equipment, cluding computer-aided design, global positioning sys-
3. utilization of existing or new steel, tems, and more powerful lift cranes have enabled con-
4. defined and scheduled pre-outage, outage, and struction engineers and technicians to support super-
post-outage activities, vision by refining the planning process and expedit-
5. planned outage schedule, ing the work in the field.
6. definition of the erection sequence, Aggressive schedules, improved financial perfor-
7. existing access limitations and additional require- mance, increased scrutiny, and regulations regarding
ments, safety and quality require that projects are executed
8. shop or field modularization, and with increasingly refined margins for error, both tech-
9. field labor availability. nically and economically. The goals established for
these projects include: 1) reduced field operations costs,
A critical period occurs early in a project when scope, 2) a minimal project time span, 3) the construction of
general arrangement, construction approach and a quality product, and 4) provision for a safe working

Steam 41 / Construction 39-5


The Babcock & Wilcox Company

environment. The integration of technology into the ing and compacting at the site. Other concurrent site
construction process increases the opportunity to ac- activities must be evaluated when planning for
complish these goals through the proper, effective and modularization.
innovative application of means, methods, techniques, Construction participation by all involved parties is
tooling and equipment. required in planning any project to enhance
A construction technology group normally supports constructability and identify intended erection methods.
the field construction program. These engineers pro- The erection method is influenced by the following factors.
vide construction engineering services, construction Retrofit versus new plant installation The construc-
logistics, and constructability reviews for each specific tion logistics associated with retrofitting, repairing or
product and configuration. Typical outputs include altering an existing unit are much different from those
recommended shipping sizes and configurations, rig- required for constructing a new unit. Logistics for new
ging weight and center of gravity calculations, crane plant construction are further diversified, depending
placement drawings, heavy lift and hauling plans, on whether the unit is to be built on an existing plant
and structural analyses of existing facilities for im- site, adjacent to existing units, or on a new site. Ret-
posed construction loads. rofit operations are generally performed in a pre-out-
age/outage/post-outage mode.
Approaches to construction – In planning retrofit work, an erection method that
erection methodology permits performing many tasks concurrently is cho-
There are three basic approaches that may be used sen. This optimizes equipment and labor and mini-
in a construction project: 1) knocked down, the tradi- mizes outage times. When constructing on an exist-
tional method, 2) field modularization, and 3) shop ing plant site, the erection method must maintain a
modularization. The knocked down approach is based productive interface between construction activities
on the erection of shop fabricated, standard-sized ship- and ongoing plant operations. Construction on a new
ping units that readily fit on a truck/trailer or rail car. site offers a contractor the greatest amount of freedom
The standard shipping units are erected one piece at in selecting the most cost-effective, efficient method for
a time in stick fashion. Field modularization combines executing the work; however, potential obstructions in-
these traditional ship units into larger components, or clude those areas of work occupied by other contractors.
modules, at the construction site for final installation. Plant arrangement The overall plant arrangement
Off-site assembly, shop modularization, or prefabrica- plays a key role in establishing the sequence for erect-
tion combine the traditional ship units into subassem- ing components and equipment. Plant arrangement
blies at the manufacturer’s plant. defines the available access routes for material flow
Modularization is an integrated approach to power from the laydown and storage areas to the final in-
plant construction whose concepts must be incorpo- stallation points.
rated at the earliest possible stages of a project’s plan- Scope The scope of work directly affects the con-
ning. The most successful projects have continued com- struction plan and completion of the construction.
mitment to this approach by the customer, the equip- Tools and equipment needed for one phase of the
ment supplier, and the erecting contractor. project may also be influenced by the requirements
While modularization may be cost effective, the ex- of other phases.
tent of effective modularization is site specific. Parameters Product and component parameters,
Modularization divides plant materials into subsets, including size, weight and shipping configurations,
or modules, that are assembled before being brought dictate the type and size of material handling equip-
to the construction site. (See Fig. 5.) The degree and
extent of modularization can vary considerably. In its
simplest form, a structural steel beam with shop-at-
tached clip angles is a module. At the opposite end of
the scale, a shop-assembled boiler complete with all
trim piping, instrumentation, and insulation and lag-
ging, or a 50-ton section of ductwork insulated and
lagged is also considered a module.
Boiler components have been modularized for some
time. Fig. 6 depicts furnace wall panels in which loose
boiler tubing and membrane stock are welded to form the
panels. Large modularized scrubber components are
shown in Fig. 7.
A modularized project requires more engineering
and design time than a conventional project. Planning
must consider the water and land routes used for ship-
ping the modules. Construction sites located on navi-
gable waterways have the greatest potential for ship-
ment of large modularized components. (See Fig. 8.)
Module unloading, site movements and erection
procedures must be carefully considered. Special con-
sideration must also be given to foundations, backfill- Fig. 5 Large scrubber modular components on a barge.

39-6 Steam 41 / Construction


The Babcock & Wilcox Company

tractors is required to achieve certain location toler-


ances and to complete the erection.
Schedule The project schedule, including customer-
specified start, finish and milestone dates, dictates the
required erection sequence, labor needs and timing for
project completion. The quality and skills of the local
labor force play major roles in the erection plan and
overall sequencing of the work.
Because cost is an important criterion governing
selection of the erection method, the economic advan-
tages and disadvantages of the other selection crite-
ria must also be evaluated. Costs of construction op-
erations versus component shipping configurations are
often arranged in a matrix. The shipping configura-
tion reflecting the lowest total cost is considered to be
the most effective approach and becomes the preferred
choice for erection. Tabulated construction costs are
coupled with corresponding costs for component en-
gineering, shop fabrication and assembly, and ship-
ment to the job site to identify the most effective over-
all approach for a specific project.
Extent and location of field welds Overall product
quality and constructability are enhanced by minimiz-
ing the number of field welds. The required welds must
be readily accessible to allow the use of state-of-the-
art equipment and processes.

Fig. 6 Raising furnace wall section into position.

ment and the need for special handling procedures,


methods, jigs and fixtures. Material type, thickness,
and required erection tolerances are considered in es-
tablishing methods for component alignment, weld-
ing, post weld heat treatment, stress relieving, and
nondestructive examination.
Site conditions Existing site conditions and acces-
sibility play major roles in determining the size, weight
and configuration of the components to be shipped.
Water accessibility represents the greatest opportunity
for shipping large shop-assembled modules; otherwise,
rail or truck shipments are required. If multiple trans-
portation modes are used, the size of the component
is limited by the most restrictive shipping method.
Shipping accessibility only partially controls the
extent of material and equipment shipments to the job
site. Upon arrival, the material must be off-loaded and
transported to its storage area or final installation
point. Material off-loading schemes depend upon the
mode of shipment and the site conditions at the off-
loading area. Transportation of the material is then
limited by the width, overhead clearances and load
limitations of existing roadways.
Contractor interface Interface with other contrac-
tors is an important part of a construction project. Once
portions of the project have been completed by indi-
vidual contractors, effective interfacing between con- Fig. 7 Modular components for an environmental control installation.

Steam 41 / Construction 39-7


The Babcock & Wilcox Company

5. temporary structures and construction facilities,


6. civil/site work, and
7. specialized tooling, machining and equipment.

Material handling and setting considerations


Like any phase of a construction project, material
handling operations must be planned and integrated
into the total construction plan. The size, weight and
shipping schedules of material and components to be
received and installed must be known in order to plan
for storage area needs and to schedule crews and equip-
ment. Special handling provisions and special inspection
and storage requirements must be known and accom-
modated. In addition, the plant structure must be de-
signed to support the loads involved during construction
Fig. 8 A barge carrying SCR components is positioned for off-loading.
and the clearances required to get equipment in place.
Material handling plans must reflect actual site con-
The scope of work to be performed and the compo- ditions including rail and truck access, locations and
nent configuration influence the extent and location condition of haul roads, and availability and location
of field welds. The construction engineer must provide of laydown areas and warehouses. Although most ma-
input regarding preferred field weld locations, sug- terial shipped to a construction site can be handled
gested component configurations for these weld loca- with conventional construction equipment, material
tions, and intended welding processes. handling plans must identify any special equipment or
fixtures required to handle large or unusual components.
Equipment used for material handling operations
Construction engineering and may generally be grouped by function into two cat-
rigging design egories: 1) transporting, and 2) lifting.
Equipment for transporting material is limited to
Background that intended for on-site application, and does not in-
Babcock & Wilcox Construction Co., Inc. (BWCC) clude trucks, railroad cars or barges listed for mate-
takes an engineered approach to the execution of rial delivery to the job site.
heavy lifts. Specialized tools, equipment, rigs, jigs and A wide range of equipment is available for mate-
fixtures are provided for each project. rial transport and lifting on the job site. Selection and
Modern construction includes modularized compo- use depend on the configuration and weight of the
nents that are erected on short timetables. To reduce material to be handled and the relative distance be-
construction and shipping costs, the weight of support tween transport points and available site clearances.
steel components has been reduced. As a result, the Selected techniques and types of equipment that can
calculation of imposed erection loads is critical. be utilized for material transport and lifting are shown
In recent years, customer specifications have required in Figs. 9 through 11.
the submittal of engineered rigging drawings and pro- While this listing is intended to provide an idea of
cedures prior to construction. These submittals often the range of tools, methods and equipment available
require the stamp of a licensed professional engineer. for material handling, it is not all inclusive. Various
suppliers and manufacturers maintain and supply
Engineering principles their own version of the generic equipment identified.
The construction engineer involved with product The selection, specification and use of this equipment
erection must be familiar with the product’s construc- require a thorough construction engineering effort
tion details and function as well as responsible for the from the planning phase of the project through the
engineering, design and specification of all systems, execution of the work.
tools, equipment, devices and mechanisms required for
erection. This requires a command of engineering fun-
damentals and knowledge of principles taken from
civil, structural, mechanical and electrical engineer-
ing disciplines.
Engineered systems
Engineered systems required to support construc-
tion operations may generally be identified by:
1. material handling (discussed below),
2. rigs, jigs and fixtures,
3. temporary supports, shoring and reinforcement of
existing structural components,
4. access and protection structures, Fig. 9 Hydraulic platform trailer.

39-8 Steam 41 / Construction


The Babcock & Wilcox Company

Depending on the equipment selected or available,


various operations are involved to get the components
to their final in-place position. These operations, rep-
resented in Fig. 12, may be accomplished by use of a
single hydraulic crane or may require a sophisticated
handling system custom designed for the application.
(See Fig. 13.)
Serviceability
The serviceability of a material handling system is
a measure of how well the system performs its in-
tended function subject to conditions produced in its
work environment.
Imposed loads and forces
The weight of the component being handled is a Fig. 10 Hydraulic gantry system.
major consideration in the design and selection of the
material handling system; however, component The coefficients of static, rolling and sliding friction
weight is not the only load imposed. All systems oper- define friction loads. Depending on the arrangement
ate dynamically while simultaneously generating and of load handling components, friction may become a
being acted upon by forces that include steady-state significant part of the total design load.
and time-varying components. Forces are introduced Impact loads are associated with sudden shocks
by the operating environment, by the work being that occur during a load handling operation. An im-
done, by the inertia of the masses put into motion, and pact allowance (25% of the handled load) is typically
by the weights of the load and the system components.2 applied in the direction of load movement. Minimal
Imposed loads are generally categorized as gravity impact loading is achieved by moving components at
or nongravity. Furthermore, both loadings may be constant, slow speeds.
static or dynamic. While dynamic loading must be Nongravity loading conditions include wind load-
recognized in designing the material handling system, ing, seismic loading and stabilization. Most applicable
the magnitude of acceleration/deceleration loads is codes and specifications have reduced these dynamic
small in most cases. As a result, static loading gener- conditions to static load equivalents. For the purpose
ally governs the system design. of material handling system design, these conditions
Static gravity loading conditions are categorized as are therefore treated as such.
lifted load, dead load, live load, friction or impact. Wind loading, when imposed on material handling
The lifted load is the calculated rigging weight of system components, is evaluated and applied in ac-
the component being handled. This calculation must cordance with Uniform Building Code (UBC) or Ameri-
account for manufacturing variability and normally can National Standards Institute (ANSI) guidelines.
includes a safety factor. Shapiro suggests multiplying Seismic loading is not a major design consideration for
the calculated weight by 1.03 for mass produced items most material handling systems. Nevertheless, seismic forces
and by 1.07 for singular devices.2 may be evaluated with UBC or ANSI specifications.
Dead load is defined as the weight of the material Stabilization forces are those forces required to
handling system components themselves, independent maintain lateral stability of compression and flexural
of the component being lifted. In calculating this structural members. This force is arbitrarily consid-
weight, the same considerations must be made with
regard to potential dimensional variations in compo-
nents. The suggested weight parameters act as mul-
tipliers as they relate to imposed loading or induced
stress and as divisors as they provide stability or up-
lift resistance. The imposed dead load is the cumula-
tive weight of all other components supported from the
component being designed.
The live load is an allowance that accounts for the
weight of construction personnel, scaffolding, ash (slag
or dust accumulations), and snow or ice accumulations
on the handled component. Because these loads are
frequently unknown when the material handling sys-
tem is designed, they are applied on the basis of a speci-
fied unit weight per surface area or a specified den-
sity per volume.
Friction loads are those associated with a body’s
resistance to movement. Friction takes on various
forms depending on the system arrangement and load
handling application. Fig. 11 Manitowoc crane.

Steam 41 / Construction 39-9


The Babcock & Wilcox Company

Tower Crane maintained throughout the course of load handling


with Main
Tower operations. The specific conditions of equilibrium are
and Boom stable, unstable, and neutral.
Load control
Load control is an assurance that the load will as-
sume a predetermined, expected orientation without
Counterbalancing
Crane with Main
deviation throughout the course of handling opera-
Boom and Mast tions or at any point in those operations.
Load distribution
Crawler Crane Throughout the load handling operation, the com-
with Main Boom
and Luffing Jib ponent being handled seeks a position of static equi-
librium. A lifted load always vertically aligns its cen-
ter of gravity with the centerline of the lifting hook.
Prudent arrangement and design of the material han-
Ringer Crane
with Mast, dling system is based on knowledge of the component’s
Main Boom
and Fixed Jib center of gravity as well as the magnitude of the re-
sultant loads and forces acting on the system.
Depending on the handling operations involved,
the relative position of a component’s center of grav-
ity with respect to its supports can vary with time. This
variation produces a time-dependent variation in the
magnitude of the support reactions, and thereby, the
Conventional
Crawler Crane Truck Crane with
load imposed on the material handling system. Con-
with Telescoping sider the steam drum illustrated in Fig. 15. Two sepa-
Main Boom Hydraulic Boom
rate sets of load blocks and rigging are used for rais-
Fig. 12 Configurations of typical lift cranes.
ing the drum to its final position in the boiler support
steel. Throughout the course of the raising operation,
it may be necessary to incline the drum to clear local
ered to be 2% of the total force developed in the com- interferences with boiler support steel. As the drum is
pression zone of the member being stabilized. In the inclined at some angle θ from the horizontal, the load
case of compression members, the compression zone imposed on each set of blocks varies in accordance with
is the total cross section; for flexural members, this the following expressions:
zone is limited to the compression flange.
 Y 
WL1 = 1 1 + tan θ  WL (1)
Load stability 2  L 
Load stability is the inherent tendency of a load in
equilibrium, either static or dynamic, to remain in
equilibrium and to minimize any translational or ro-
tational effects produced via the imposition of unfore- Guy Derrick
seen forces and/or moments throughout the course of
W
load handling operations. A rigging system (see Fig.
14) must be configured to ensure that load stability is
Stiffleg Derrick W

“Chicago Boom”
W
W
Monorail
Hoist and Load
W Blocks

Track System
on Rollers W
Taut Line or Cableway
System

Fig. 13 Site-specific handling system for an environmental control


installation. Fig. 14 Typical rigging configurations.

39-10 Steam 41 / Construction


The Babcock & Wilcox Company

ready access to support the construction effort. Gen-


erally, a numbered grid system is used in laydown
yards and warehouses to identify specific storage lo-
cations. Fig. 17 shows a typical storage layout.
To support the planned construction activities, ma-
terial must not only be on site and available, but must
be in good condition. In addition to inspection of the
material upon receipt, the material and the storage
areas are inspected periodically to satisfy specific stor-
age requirements and to ensure proper protection of
the material.
With the amount of material involved in most con-
struction projects, it is essential that an effective docu-
mentation system be used. A complete listing of items
to be received is needed to ensure that a complete in-
ventory is maintained. For each item, material receiv-
ing and storage records must effectively document
receipt and disbursement status, condition of the ma-
Fig. 15 Steam drum lift and support arrangement.
terial, and current storage location.
Construction of a fossil fuel unit
 Y 
WL 2 = 1 1 − tan θ  WL (2) The installation of a top-supported steam generat-
2 L  ing unit is unique in that the heaviest components are
at or near the top and most other major components
where are hung from steel rods. Field assembly of the boiler
WL1 = portion of WL supported by high end blocks begins by positioning the major upper components in
WL2 = portion of WL supported by low end blocks a manner that provides a design deflection after com-
WL = weight of component being raised pleting the boiler installation. While the following dis-
Y = 2 × (transverse distance between longitudi- cussion is primarily concerned with top-supported
nal centerline of drum and centerline of lift- units, many of the basic procedures apply to all units.
ing lugs)
L = center-to-center spacing between lifting lugs Structural supports
The design of the supporting structural steel must
Per these expressions, when the drum is horizontal, consider the loading and stresses encountered during
i.e., θ = 0 deg: the installation of the boiler. The major construction-
WL
WL1 = WL 2 = (3)
2
That is, the rigging weight of the drum is shared
equally by each set of load blocks. However, as the
angle θ is increased, the load transferred to the blocks
on the upper end of the drum is increased. Therefore,
each set of load blocks, rigging and drum lifting lugs
are conservatively sized to accommodate the total rig-
ging weight of the drum (Fig. 16).
Design loading
The material handling system design loading is es-
tablished by identifying the maximum of several criti-
cal load combinations and then multiplying this value
by a safety factor of 1.10. Typical combinations include:
lifted load + dead load + live load + impact,
lifted load + dead load + live load + friction, and
lifted load + dead load + live load + impact +
greatest of wind, seismic or stabilization load.
Friction and impact loading are mutually exclusive
events, and therefore are never considered to be a vi-
able combination.
Other site considerations – storage
Storage is also a critical issue. Storage areas must
be laid out and material placed in storage to provide Fig. 16 Typical utility boiler steam drum lift.

Steam 41 / Construction 39-11


The Babcock & Wilcox Company

Drums Drums for the largest boilers may weigh


more than 400 t (363 tm); they may be 100 ft (30.5 m)
in length and may be located more than 200 ft (61 m)
above the ground. To clear supporting steel, the drum
may be inclined by as much as 60 deg (1.05 rad) dur-
ing the lifting operation. Capacity and safety of the
drum rigging are of primary importance in selecting
the equipment and methods.
Fig. 16 shows a typical drum lifting arrangement us-
ing lugs that are shop-welded to the drum. Attachment
pieces for the top of tackle blocks are located on tempo-
rary steel members above the boiler structure. These
blocks should permit simple linkage connections at the
top support and drum attachments. The capacity of the
hoisting engine and the sizes of tackle blocks and wire
rope are determined with ample safety factors.
When the drum is in its final position, it is supported
from the top structural steel by U-bolts that permit lin-
ear movement with temperature variations. Fig. 18
shows a typical drum and support arrangement. The
drum is a major anchor point for other boiler compo-
nents and, for this reason, accurate location is impor-
tant. The structural members, platforms and stairways
that were omitted for drum erection are then installed.
Downcomers, headers and large pipes Plant access
consideration is important and the sequential plan
should be carefully followed in the erection of down-
comers, loose headers and large pipes. These compo-
nents are shipped in the longest lengths possible to
avoid costly field welds. Large downcomers are often
placed in the boiler cavity while steel is being erected
Fig. 17 Site laydown area.
and are moved to their final location when convenient.
Without proper integration into the planning se-
quence, these components must be shipped in shorter
imposed loads must be evaluated. Because certain lengths or additional structural steel must be omitted
structural members may be temporarily omitted to to provide clearances during erection.
permit access for large subassemblies, the associated Tube walls To reduce cost and the time required for
additional structural loads must also be considered. field erection, a large percentage of furnace enclosure
Before erection is started, all foundations must be tubes are shop-assembled into membrane panels.
completed and checked for specification compliance. B&W’s preference is to furnish wide, long panels. How-
Because most large units are top-supported, as discussed ever, as with any modularization approach, shipping
in Chapter 26, erection of the structural supporting steel and field conditions determine the panel sizes that can
is the first step in building the unit. This is done by con- be provided. The wall panels are erected as-received
ventional methods, using cranes and derricks. Stairways from the supplier or, if conditions permit, the construc-
and walkways are completed to the fullest possible ex- tion plan may include on-site assembly into larger wall
tent to provide safe access to all parts of the unit. sections. Panels may even be ground-assembled into
Because many of the structural members govern complete walls with headers, casing, buckstays and
the location of boiler and auxiliary components, sup- doors attached.
porting steel must be aligned with established build- Superheater, reheater and economizer These com-
ing centerlines. After the structure has been aligned ponents can be furnished with loose headers and in-
and plumbed, the members are rigidly connected with dividual elements or in shop-assembled modules with
high tensile bolts or by welding before supporting any or without headers. Again, the design features of the
structural loads. particular unit and project determine the degree of
field or shop modularization. When large, heavy sur-
Assembly of pressure components face modules are to be erected, the construction plan
The construction schedule and plan include a timely normally includes early installation while access and
sequence for installation of boiler components. The hoisting clearance are available.
steam drum is usually the first major assembly placed Tube connections Tubes are attached to drums or
in the structure. All large or heavy components, su- headers by welding, expanding, or a combination of
perheater modules, top headers, interconnecting pipes the two (see Fig. 19). Generally, tubes that withstand
and wall tube panels are positioned, following the plan, pressures greater than 1500 psi (10,342 kPa) are ex-
in the boiler cavity while unrestricted space is avail- panded and seal-welded or welded to shop-attached
able to access and hoist them. stubs. Shop-assembled tube-to-header connections, such

39-12 Steam 41 / Construction


The Babcock & Wilcox Company

Fig. 19 Expanding tube connections.

ments. ASME IX provides the requirements for quali-


fication of procedures and welding personnel.
Various conditions make field welding different in
many respects from welding in the shop (discussed in
Chapter 38). A typical field welding environment in-
cludes dust, wind, variable temperature, rain, high
scaffolding, locations remote from supply and main-
tenance facilities, and a mobile labor force. Under
these conditions, it is important to consider the selec-
tion of the welding processes and equipment. Key fac-
tors include simplicity, reliability, portability, ease of
Fig. 18 Radiant boiler steam drum in position.
maintenance, and availability of spare parts. Equally
important are the skills and availability of the
workforce.
as those in wall panels and superheater modules, are Manual and semiautomatic welding methods are
usually welded directly into the headers. (See Fig. 20.) therefore preferred for field erection of standard boiler
Design standards permit expanded tubes for low-pres- components. While there is a continuing search for and
sure boilers. Tube expanding, or rolling, is a process of evaluation of reliable automated welding equipment
cold-working the end of a tube into contact with the metal for field erection and repair, it is seldom used. For ex-
of the drum or header tube hole or seat. The end of the ample, use of orbital gas tungsten arc welding (GTAW)
tube is inserted into the hole and then plastically ex- or gas metal arc welding (GMAW) have seen limited
panded by internal pressure; relieving of the pressure applications due to the precise weld joint fitup require-
leaves the tube tightly seated in the drum or header. ments, development and tight control of welding param-
A typical roller expander is shown in Fig. 21. This eters and technique, limited space restriction for the
tool contains rolls set at a slight angle to the body of equipment, lack of highly trained operators and the as-
the expander, causing the tapered mandrel to feed sociated cost and maintenance of the welding systems.
inward when it is turned. For conditions of widely fluc-
tuating temperatures and bending loads, the ex-
panded joint must be seal-welded or replaced by a
shop-attached tube stub.
Field welding
The welds that are made in the erection of a steam
generating unit can be divided into two classes – those
for assembly of plate and structural materials to sup-
port the unit and those for assembly of tubes, pipes
and other pressure parts making up the steam gen-
erating unit. Welding on plate and structural materi-
als is performed in accordance with the Structural
Welding Code AWS D 1.1.
Welding that involves boiler pressure parts must
conform to the requirements of the American Society
of Mechanical Engineers (ASME) Boiler and Pressure
Vessel Code, The fabrication Codes reference ASME
IX for Welding and Brazing Qualification require- Fig. 20 Headers with shop-assembled stubs.

Steam 41 / Construction 39-13


The Babcock & Wilcox Company

Seal welds Seal welds are used to make mechani-


cal joints fluid-tight. Joint strength is developed by pipe
threads, tubes rolled into drum holes containing
grooves, or header master handholes fitted with spe-
cially-designed plugs (see Fig. 22). The maximum size
of seal welds made without post weld heat treatment
is 0.375 in. (9.5 mm).
Special precautions are required to obtain sound
seal welds; welding over pipe threads is not permit-
ted. After seal welding, tubes should be lightly re-
rolled. Handhole plug seal welds should be thoroughly
cleaned and are preheated to avoid cracking.
Qualification of welding procedures
and personnel
Fig. 21 Position of expander and mandrel after tube is expanded and flared. Welding qualification requirements are contained in
the ASME Code, Section IX. The ASME fabrication
Codes and the National Board Inspection Code (NBIC),
Processes and equipment published by the National Board of Boiler and Pressure
Manual GTAW, shielded metal arc welding (SMAW), Vessel Inspectors, references this Code for qualification
and flux core arc welding (FCAW) are the most common of repairs and alterations to in-service boilers.
processes used in the field. (See Chapter 38, Table 1.) A welding procedure qualification test verifies that
These processes are versatile and can be used on all field- required mechanical properties are obtained when
weld materials utilizing equipment that is simple and designated materials are welded by following a spe-
easily maintained. In addition, most field welders are cific technique. BWCC has established many proce-
qualified for the GTAW and SMAW processes. dural qualification records based upon the ASME
For welding non-pressure parts or making non-pres- Code. These procedure qualifications support hun-
sure attachments to pressure parts, there is increas- dreds of welding procedure specifications.
ing use of semiautomatic welding. Welders trained and A welder qualification test is required to verify that
qualified in GMAW or FCAW processes can make an individual has the skill to deposit sound weld metal
quality welds at significantly higher deposition rates in a given position while following an established
compared to the GTAW or SMAW process. welding procedure. Welders are qualified in accordance
As with the GTAW process, adequate precautions with ASME IX standards either at the job site or at si-
must be taken to protect the weld area from the elements, multaneous testing sites by participating organizations.
especially excessive wind. When a flux core welding elec-
trode that is self-shielded, i.e., does not require external Thermal treatment
gas for protection of the molten weld puddle, is used for Preheat Preheating the weld metal is the most ef-
erecting boiler casing and other structural components, fective way of preventing cracks in low alloy steel
excessive wind must still be avoided. welds because it reduces the cooling rate of the weld
and base metal. The required minimum preheat tem-
Applications perature is specified in the field weld schedule and on
Pressure welds Welds joining dissimilar metals are BWCC’s welding procedure specifications (WPS). Pre-
typically made in the shop because they are often dif- heating methods include the use of electric-resistance
ficult to make under field conditions and require spe- blankets and oxy-gas or oxy-fuel torches. Special tem-
cial qualification. Field butt welds in tubes and pipes perature-indicating crayons are used to assure that
are made using pre-machined weld joints that have the proper preheat temperature has been attained.
been covered with a protective cap. Thorough inspec- (See also Chapter 38.)
tion and cleaning are still required before fitup and Post weld heat treatment Requirements for post weld
welding to avoid weld defects. stress relief are also specified in the field weld sched-
Butt welds may be made with an open groove joint ule. Electric resistance heaters are commonly used for
or with a backing ring that is left in place. When an field post weld heat. These heaters offer the advantages
open groove joint is used, the root pass is typically of ease of application and precise temperature control.
made with the GTAW process because of the inherent
better control of the inside weld surface contour. The Codes, inspections and examinations
groove is completed using the SMAW process. The ASME Code requires a valid ASME Certifica-
When the weld joint contains a backing ring, the tion of Authorization to install power boilers. To ob-
entire weld is usually made with the SMAW process. tain an ASME Certificate of Authorization, an orga-
This method is normally used for the original erection nization is required to maintain a Quality Control
of riser and downcomer piping. Rings are never used System that addresses the Code requirements. A re-
for furnace walls. However, they may be used for other view is performed by ASME to evaluate the Quality
pressure boundary tube welds depending upon engi- Control System and verify implementation. Once is-
neering or customer requirements, and, if permitted, sued, the Certificate of Authorization is renewed tri-
is the preferred method of fabrication. annually by review. A boiler installed in accordance

39-14 Steam 41 / Construction


The Babcock & Wilcox Company

with the ASME Code must be inspected by an autho- cant dividends over stick-built construction at the job
rized inspector at various stages of assembly to assure site. The project benefits in both labor savings and in
that all Code requirements are met. the potential for a reduced site completion schedule
Section I of the ASME Code contains requirements when high-cost field labor is replaced with lower-cost
for the installation of power boilers. ASME B31.1 con- shop labor.
tains requirements for the installation of boiler and The construction principles utilized for environmen-
non-boiler external piping. The state or jurisdictional tal equipment are the same. However, the method of
authority maintains rules and regulations that gov- construction differs significantly. SCR projects predomi-
ern the installation of boilers and establishes the ap- nantly consist of structural steel and fabricated plate,
plicable governing Codes. Section I of the ASME Code while FGD system projects consist of fabricated plate,
has been adopted by law in most states or jurisdictions. structural steel, process equipment and piping. There is
Whereas ASME governs new construction, the NBIC little in the way of operating equipment with the excep-
governs repairs and alterations to boilers and other tion of dampers, sonic horns or sootblowers, ammonia
pressure-retaining items. The NBIC requires the repairs vaporization equipment, and some piping and instru-
and/or alterations to comply, to the extent possible, with mentation. In these installations, the chemical process
the original Code of construction. As with the ASME required to support the operation utilizes additional
Code, the NBIC is mandatory only when adopted by a equipment to handle the lime or limestone reagents and
state or other jurisdictional authority. gypsum removal and drying.
Section I of the ASME Code specifies the nonde- Most SCR projects are designed with the reactor
structive examination (NDE) requirements for new and flues bottom-supported off structural steel. The
construction of power boilers. ASME B31.1 specifies primary component of FGD systems is the absorber
the NDE requirements for boiler and non-boiler ex- tower which is independently bottom-supported on a
ternal piping. NDE requirements for repairs and al- separate foundation. For SCR systems, close coordi-
terations are specified in the NBIC. The type and ex- nation is required between steel erection activities and
tent of NDE must be considered during the proposal, the installation of the interconnecting flues and reac-
planning and scheduling processes. For all construc- tor. Complicating matters on a retrofit project is the
tion, the applicable regulations and any additional space available for the SCR. The process temperature
NDE requirements exceeding the Code should clearly for most SCR systems requires the boiler flue gas to
be specified in contract documents. The nondestruc- be taken from an area immediately downstream of the
tive technologies are discussed in more depth in Chap- economizer, and before the air heater inlet. On large
ters 38 and 45. boilers, this tie-in point can be more than one hun-
dred feet (tens of meters) above ground level. Also,
since a reactor can contain nearly a million pounds
Construction of environmental equipment (450,000 kg) of catalyst at a significant elevation
Regulatory requirements associated with the Clean above grade, concerns for overturn and uplift forces
Air Act Amendments of 1990 caused many fossil fuel- may require a complex foundation design.
fired electric generating plants in the United States At many sites constructed decades ago, little con-
(U.S.) to install, or plan for the installation of, emis- sideration was given to future expansion and there-
sion reduction equipment. Many stations installed fore, current space limitations are a serious concern.
sulfur dioxide (SO2) scrubbers in the early 1990s which Many projects are faced with a significant rerouting
were then followed in the early 2000s by the installa- of the boiler exit gas to a point where space is avail-
tion of selective catalytic reduction (SCR) systems for able for either an SCR or FGD system. The flue gas must
nitrogen oxides (NOx) removal. then be routed back to continue its path through the air
While erection of environmental equipment is sig- heater for SCR applications or to the stack for FGD sys-
nificantly different from boiler erection, many of the tems. Each project poses a unique set of circumstances.
same principles and attributes of boiler erection ap-
ply. A modularized approach generally pays signifi- Sequencing and modularization
Early in the project, specific information about the
weight of ductwork sections and equipment must be
estimated. Many times the module boundaries are eas-
ily identified, due to equipment terminal points or ex-
pansion joint locations. Other times, sound judgments
must be made, based on experience. The erector is the
prime contributor to determining splice locations that
are best from a variety of standpoints, including ac-
cess, crane capacity and geometry.
The resulting erection sequence can then be used
in establishing schedule priorities for detail design,
material procurement and fabrication. To allow maxi-
mum flexibility for installation, schedule priorities
should be developed in accordance with erection plans.
Receiving materials far in advance of the time re-
Fig. 22 Welded handhole fitting for higher pressure boilers. quired at the job, or in a sequence that does not sup-

Steam 41 / Construction 39-15


The Babcock & Wilcox Company

port planned erection, results in increased handling quires dampers and blanking plates to allow the bal-
costs. Without the proper materials, the constructor is ance of construction to take place subsequent to the tie-
forced to work on activities that deviate from the in- in. The blanking plates allow safe entry to the flues
tended plan, increasing overall project cost. during plant operation. However, this approach gen-
The erector should complete a constructability re- erally impacts the erection sequence and potentially im-
view prior to the issuance of key design outputs. This pacts the total construction cost. A second, shorter out-
review often uncovers missing or incorrect informa- age is then required to make the final tie-in of fluework.
tion. Early identification of potential problems can al-
leviate costly field rework or production delays due to
additional engineering evaluations and the resulting Construction safety
drawing revisions. A comprehensive safety program must be imple-
Once modules are identified and an erection se- mented at each construction site. The objective is to pro-
quence is established, the project team interacts with mote an awareness of safety among personnel and cre-
plate fabricators for delivery options. A modular con- ate a safe working environment to prevent injuries.
struction approach provides the project team with the BWCC has developed a Safety Program Manual in sup-
opportunity to review and approve the manufacturer’s port of a construction site safety program. The manual
plan for component fabrication. This process may re- has been specifically designed for construction and in-
sult in on-site productivity improvements as the con- cludes the requirements of 29 CFR 1926 Safety and
structor advises on alternative shipping configurations Health Regulations for Construction by the Occupa-
and rigging requirements, and gains valuable infor- tional Safety and Health Administration (OSHA). The
mation about the material to be received, thus help- contents of the Safety Program Manual include, but are
ing to identify the extent of preparatory work that will not limited to, the safety procedures outlined in Table 2.
be required on site prior to erection.
Fig. 23 is a typical arrangement for an SCR retro-
fit project. Identified in the figure are module bound- Internal cleanliness of pressure parts
aries utilized for design, procurement, planning and
erection activities. The individual modules are installed Manufacturing and shipping
in a defined sequence to maximize efficiency and mini- Many problems can develop during operations be-
mize erection time. This sequence, which usually starts cause of dirt or other foreign matter in the circulating
from the lowest to the highest point, builds from the system of a boiler. During the fabrication of drums,
reactor back to the boiler and involves the erection of tubes, headers, pipes or other pressure parts, precau-
sufficient steel to set the outlet or bypass flues. Once tionary measures must be taken to assure internal
the initial flues are set, steel progresses again to the cleanliness. For boilers that use welded stub construc-
point where additional flue sections can be set and the tion, the ends of all tubes and pipes, as well as the
reactor built. Ideally, horizontal runs of ductwork are stubs in the drums and headers, are closed with metal
bottom-supported, and require that the support steel caps and sealed with plastic tape. This usually makes
is first installed beneath the duct. Structural engineers it unnecessary to clean these components in the field.
should be aware of the construction/erection plan so Inevitably there are a few closure caps displaced dur-
that the steel erection sequence and requirements ing shipping, unloading and handling. In such in-
support the equipment’s erection sequence. These ac- stances, the construction crew must examine the com-
tivities require close coordination with the design en- ponents involved, perform any necessary cleaning,
gineers to ensure that the uncompleted steel structure and replace the caps as soon as possible.
is adequate to support the initial duct sections as they
are installed. Cover-plating the existing steel is fre- Field assembly
quently required prior to imposing additional loads Boiler pressure parts should be searched before
from the new structure and can be a time-consuming handhole and manhole closure fittings are installed.
and costly effort. If present, lead-based paint must be Reasonably straight tubes between headers or drums
abated from existing steel prior to any welding or may be probed by passing a ball through them. Bent
grinding operations. The use of bolt interface connec- tubes that will not clear themselves of foreign material
tions rather than welded connections could minimize by gravity may be probed by blowing a tight-fitting
lead abatement requirements. Close coordination with sponge through them. The butt welds in small diam-
plant operations is also required as a result of the eter tubes are examined radiographically for misalign-
numerous interferences with plant utilities supported ment or obstructions that may cause flow restrictions.
from the columns or beams being modified. Headers are checked with a light and mirror immedi-
Tie-in to the unit is the last activity phase, accom- ately before the end handhole fittings are installed.
plished during a planned unit outage. Depending No foreign material may enter the pressure part sys-
upon planned unit outages, however, there is flexibil- tem during assembly. Closures are left in place until re-
ity in the erection sequence. Many times a tie-in out- moval for welding or positioning equipment. If shop-in-
age occurs before construction of the SCR is initiated, stalled closures are removed to permit installation, tem-
especially if the plant has a major outage scheduled porary closures are placed over the openings to prevent
well in advance of the SCR completion. In these in- debris from entering the equipment. Prior to flushing or
stances, a gas bypass flue is installed which allows the final closing of equipment, a visual inspection is made
construction of the SCR during unit operation. This re- and foreign objects are removed from the equipment.

39-16 Steam 41 / Construction


The Babcock & Wilcox Company

Expansion Joint

Flue installed before outage


Catalyst
Flue installed during outage Block
Required temporary support
Tier 2 steel Catalyst
Sonic Block
Tier 3 steel Horn

Tier 4 steel Catalyst


Expansion Block
Joint

Damper Catalyst
Block

Future
Expansion Joint Catalyst
Sonic
Damper Damper Horn Block

Expansion
Joint

Economizer
Expansion
Joint

Expansion
Expansion Joint
Joint

Damper

Expansion
Joint

Air Heater

Fig. 23 Typical arrangement for an SCR retrofit project.

Removal of tube sections during repair or alteration at least 70F (21C). Nondrainable superheaters and
must be performed in a manner that prevents foreign reheaters are filled with demineralized water or con-
material from entering the tubes during the cutting densate, if available. As a boiler is being filled, it is
operation. Ends of existing tubes are plugged before vented at every available connection to allow water
machining new weld preparations. to reach every circuit.
Hydrostatic pressure is applied after the boiler is
filled. If a boiler feed pump or other high capacity
Post-construction testing pump is used, precautions must be taken to control the
pressure at all times. While water is being pumped into
Hydrostatic testing the boiler, continuous inspection is made to detect any
When all pressure part connections have been com- leakage. During hydrostatic testing, safety precau-
pleted, the steam generating unit is tested at a pres- tions must be observed, and nonessential personnel
sure specified by the applicable code; this is usually must be kept away from the test area.
1.5 times the maximum allowable working pressure The test pressure must be held long enough to al-
(MAWP). Before the test is applied, a final inspection low minute leaks to be detected. Following this hold-
is made of all welding. External connections, including ing period, pressure is reduced to MAWP and retained
all fittings, are completed within Code requirements. for an inspection period. During final inspection, ev-
Connections for flange safety valves are usually blanked. ery area of the pressure system is viewed for leakage
Welded safety valves are closed with an internal plug. and repaired if necessary.
Hydrostatic testing water must be clean and warm After inspection, the unit is drained and all
enough to bring pressure part metal temperatures to nondrainable parts are protected from freezing, if nec-

Steam 41 / Construction 39-17


The Babcock & Wilcox Company

essary. The refractory, insulation and casing work are Refractory materials
then completed in areas left open for inspection. The furnace and other wall areas of modern fossil
Air testing fuel boilers are made almost entirely of water-cooled
tubes. The increased use of membrane walls has re-
Gas-bearing components, such as the boiler, flues duced the use of refractory in these areas. However,
and ducts are field-tested for leakage and tightness. castable and plastic refractories may still be used to
All boilers are tested by one of two procedures. Boil- seal flat studded areas, wall penetrations, and door
ers designed to operate with a positive pressure, and wall box seals. (See Chapter 23.)
wherein furnace leaks would emit gases from the Other than membrane wall construction, when
boiler setting, are tested following a pressure-fired tubes are tangent or flat studded, several types of plas-
procedure. Units designed for suction or balanced tic refractory materials are applied to the outside of
draft are tested following the balanced draft procedure. tubes for insulation or sealing purposes. When an
The pressure-fired air test procedure is a pressure inner casing is to be applied directly against the tubes,
drop test. A test is considered satisfactory when the the refractory serves principally as an inert filler
pressure is raised to 15 in. wg (3.74 kPa) maximum material for the lanes between tubes. It has a binder
and does not drop more than 5 in. wg (1.25 kPa) in that cements it to the tubes and it is troweled flush
ten minutes. If pressure can not be maintained, leaks with the surface of the wall.
are sought and corrected and the test is rerun until Smaller boilers may have furnaces constructed of
satisfactory tightness is achieved. On large units, it is tubes on wide-spaced centers backed with a layer of
common to install temporary bulkheads in flue and brick or tile. Brickwork of this type is supported by the
duct runs for individual tests. pressure parts and held in place by studs. The brick
The balanced draft testing procedure is commonly is insulated and made air-tight by various combina-
performed by pressurizing the system with the forced tions of plastic refractory, plastic or block insulation
draft fan while throttling the dampers at the downstream and casing.
test terminal. With the system pressurized, all field welds High quality workmanship is mandatory in the ap-
are inspected by sight and sound to detect leaks. plication of refractory material. Construction details
are clearly outlined on drawings and instructions that
Assembly of nonpressure parts also designate the materials to be used. These mate-
rials must be applied to correct contour and thickness
and auxiliaries without voids or excessive cracking. Skilled mechan-
While pressure parts are being assembled and ics and close supervision are essential.
tested, work is in progress on nonpressure parts and
auxiliary equipment. These components, including air Casing
heaters, fuel equipment, fans, duct work, refractory, In general, inner or outer boiler casing is used in
insulation and casing, require a large portion of the areas that are not membraned. Outer casing is applied
construction labor. They must be scheduled with con- outside of insulating materials and has, for the most
sideration for items that must be assembled in a pre- part, been replaced by sheet metal lagging. Inner cas-
scribed sequence. For example, air heaters are fin- ing is positioned inside of insulation and may be pres-
ished prior to erection of flues and ducts. Pulverizers sure or nonpressure casing.
are placed early enough for piping, drives and other The primary purpose of pressure inner casing is to
auxiliaries to be completed. prevent air and gas leakage from a steam generating
unit. The inner casing is seal welded to prevent leak-
age from the boiler setting and also serves as a base
for the application of insulation and lagging.
Table 2 In most cases, modern boiler casings feature welded
Selected BWCC Safety Procedures construction. For pressure casing, it is essential that the
for Construction strength of the weld equal the strength of the plate, that
the welds be free of cracks and pinholes, and that they
Posting requirements Welding, thermal cutting and present a good appearance. For pressure casing, tight-
Medical facilities and compressed gas cylinders ness is checked by a pressure drop air test. Nonpressure
treatment Fire protection casings are given a thorough visual inspection.
Safety training Steel erection
Hazard communication Confined space entry Insulation
Accident and personal Lockout/tagout
injury reporting Excavation and trenching Selecting the type and thickness of insulation applied
Personal protective Radiation protection to boiler surfaces is an essential part of the design work.
equipment Documentation and record- Specifications are written and drawings are made to indi-
Job safety analysis keeping cate the applied materials and the method of attachment.
Housekeeping Project site safety inspections Typical standards specify insulation blocks or insu-
Operator pre-qualification Subcontractor safety lation blankets. Some plastic insulation is used for fill-
Lifting equipment Material safety data sheets ing voids. The thickness of the insulation for all sur-
Hand tools Fall protection
faces is selected to give a specific surface temperature,
Electrical Floor, wall openings and
Scaffolds and ladders stairways e.g., 130F (54C) with 80F (27C) ambient air tempera-
ture and 50 ft/s (15.2 m/s) surface velocity. The prime

39-18 Steam 41 / Construction


The Babcock & Wilcox Company

requisites for installing boiler insulation are that the is reasonable and it is extensively used in both indoor
material be tight, free of voids, well anchored, and re- and outdoor installations.
inforced where necessary.
Ductwork with heavy stiffeners at frequent inter-
vals presents a difficult insulating job. With the stiff- Pre-operational inspection
eners outside the flue and duct plate, the insulation A final inspection is made after erection work is com-
thickness is often increased over minimum require- pleted and the unit is ready for operation. This is the
ments to assure adequate coverage of the stiffeners. combined responsibility of the erection, service and
If the stiffeners are placed in a manner where stan- operating organizations.
dard insulation coverage is too costly, the insulation Externally, all components of the unit are checked
may be placed over the stiffeners. As an alternative, for expansion clearances. Obscure corners are exam-
inner lagging may be applied over the stiffeners and ined for any construction blocking or bracing that
the minimum required insulation is placed over the might have been left in place. Points reviewed for ex-
lagging. When insulation is applied at an appreciable pansion clearances are platforms and walkways con-
distance from a hot surface with a long vertical run, structed adjacent to external members that move with
air may circulate in the void. This increases heat the unit.
transfer into the insulation, which is undesirable. Of special importance in fossil fuel units is the re-
Where vertical runs exceed 10 ft (3 m), horizontal moval of combustible materials that may present an
barriers are installed between the duct and/or tube explosion hazard during initial firing. Internal cavi-
wall and insulation. ties are checked to ensure that all debris has been re-
moved. Tubes are given a final inspection for align-
Sheet metal lagging ment, particularly those that might interfere with
Outdoor boilers require the use of a durable water- sootblower operations. Movable connections between
proof lagging. A light gauge metal lagging (galvanized tubes are examined for expansion clearances and to
steel or aluminum) or outer casing is used on walls, see that all attachments are properly anchored.
flues, ducts, air heaters, vestibules, windboxes, down- On most units, construction schedules do not per-
comers, steam/water lines and other exposed compo- mit completion of insulation before the unit is fired. It
nents. The metal covering does not seal against air is important that this work be completed in areas that
infiltration but serves as a barrier to protect the insu- will be inaccessible or cause a safety hazard when the
lation against water and physical damage. The cost unit is in operation.

References
1. Constructability: A Primer, Publication 3-1, the Con- 2. Shapiro, H.I., Shapiro, J.P., and Shapiro, L.K., Ed.,
struction Industry Institute, Constructability Task Force, Cranes & Derricks, McGraw-Hill Education, November,
Bureau of Engineering Research, The University of Texas 1980.
at Austin, Austin, Texas, Third Printing, April, 1990.

Steam 41 / Construction 39-19


The Babcock & Wilcox Company

Central station utility steam generating unit under construction.

39-20 Steam 41 / Construction

You might also like