Texas A&M University

Agriculture Headquarters
Weekly Report: 5/10/10-5/14/10

Southeast View of HQ Window Framing at 5th Floor One Siding Walls in HQ

North View of HQ West Curtain Wall Framing @ Stairs Gutter Extension Support

• Safety Cook-out held today for all workers along with a raffle give-a-way.
• The installation of main feeders to the switch gears are nearly complete.
• Metal panel installation on the southeast side of the HQ is ongoing.
• Scaffold is being erected at the main entrance of the HQ.
• Sheathing of the eyebrow is 100% complete.
• Damproofing and window frame installation is ongoing along the north side of the HQ..
• Started hanging sheetrock on all partitions to deck on the first floor..
• MEP above ceiling rough-in is ongoing at the VC.
• Started installing the misc steel supports for the Herculite doors.
• Layout of radius furdowns and diffusers in the VC has started.
• The curtain wall steel supports at the VC will be painted next week.