Professional Documents
Culture Documents
Management
Technique
Class
Exercises:
MPM-PMT
K.Povenesan
List of Project Management activities by priority:
ranking (myself)
Column 1b:
Column 1a:
Column 2:
Student B
Student A
Combine
Ranking
Activity
ranking
Description
1. Develop linear responsibility chart 17 6 6
2. Negotiate for qualified functional personnel 16 17 16
3. Develop specifications 1 1 2
4. Determine means for measuring progress 20 20 20
5. Prepare final report 26 26 26
6. Authorize departments to begin work 22 22 22
7. Develop work breakdown structure 4 2 4
8. Close out functional work orders 25 25 25
9. Develop scope statement and set objectives 5 2 3
10. Develop gross schedule 2 3 1
11. Develop priorities for each project element 11 11 13
12. Develop alternative courses of action 10 12 12
13. Develop PERT network 18 18 18
14. Develop detailed schedules 19 19 19
15. Establish functional personnel qualifications 15 16 17
16. Coordinate ongoing activities 23 23 23
17. Determine resource requirements 14 10 15
18. Measure progress 24 24 24
19. Decide upon a basic course of action 9 13 11
20. Establish costs for each WBS element 7 7 7
21. Review WBS costs with each functional manager 8 9 9
22. Establish a project plan 21 21 21
23. Establish cost variances for base case elements 12 14 14
24. Price out WBS 6 8 8
25. Establish logic network with checkpoints 3 5 5
26. Review "base case" costs with director 13 15 10
All the yellow-highlighted steps in project planning which differences are been found between
my member and me. Then we came to a conclusion after discussions.
We found the Activity 3, 9, 10, 7 is the most important documents required for project
definition in the early project planning stage.
[Activity 10] this is the summary or milestone schedule needed at project initiation in
order to define the scope, objectives, specification, WBS for the project. Milestones will
flag all the important points along the way which will act as checkpoints, especially
milestones that represent “begin” or “complete”. In a way, this will encourage functional
managers to examine their activity schedule.
[Activity 3, 7, 9] can be done simultaneously as it is important to state the overall
project purposes ( i.e., “to do this or that”) and the end results (what will be delivered
on completion & inclusive of quality grades). Projects will come with time constraint &
overall budget allowances.
Normally, if to be followed textbook theory, objectives needed to be stated first and
then talk about all the work has to be done to achieve those objectives. However, most
of the time it is difficult to get a clear idea of objectives (outputs or deliverable) to start
with, and time is wasted just to trying to get the idea what is to be accomplished.
In any case people find it easier to “work the problem” by thinking of all the things that
have to be done. Typically, every team members can think of pieces or parts of the
work need to be done. This gets people warmed up, and we can a better definition of
the project objectives. (This happens during our class exercises as well)
Personally, I believe WBS shall come as 2nd activity.
[Activity 25] Is often used as the basis for developing both the WBS and later
PERT/CPM network.
[Activity 1] we can allocate the functional department with related task; it’ll be easier to
make decision for the selection of qualified personnel for each task at later stage.
[Activity 24] to start with method studies or cost evaluations, all work items will
eventually have to be estimated, but it is important to ask what significant calculations
need to be done in relation to each work items.
[Activity 26] We found that it is important to review the base costs on WBS earlier to
the stakeholders for approval to begin detail planning. A common problem discovered
at this point is when a project has an imposed delivery deadline from the sponsor that
is not realistic based on our estimates.
[Activity 19] With the rough estimation for each WBS element, basic course of action
need to be determined so that team can think of alternatives that shall be considered
as part of the chosen work.
[Activity 12] This will help when PM comes to examine risks involved and how these
could be reduced (mitigated).
[Activity 11] We came aware that activity 12 might generate additional major work
items, and then the priorities will differs again. This only to be done before detailed
schedule generated.
[Activity 17] Initially, we thought this need to be done 1st, but it is tough without
approval of estimated base case cost as it surfaces the detail planning including HR for
further development of the project.
[Activity 2 & 15] This can be done at the same sequence as PM begins the detail
planning, qualified personnel for each task requirements and their function in the
project can be determined.
Project Network Diagram
Project Network Diagram above done using Mean Times:
a) The activities on the critical path?
Ans: A1→A4→A10→A11→A15
Project Cost: the total cost for each duration is the sum of the indirect and direct
costs. Indirect costs continue for life of the project, any reduction in project duration
means a reduction in direct costs. Direct costs reduce from the project original planed
duration; the sum of the costs of all the work packages or activities represents the
total direct costs for the project.
Application: Depend on the situation of the company (resources available) and the
industry, the project manager have decision to manage his project. The project
duration can be extended or reduced base on the profit and the costs according to
that project.
Crashing may be taken as a war against time. It may fire back. Inducting new workers
may result in classic conflict between old and new. Moreover, the new workers may
not be well oriented with job and the environment. In a worst scenario, this may
lengthen the project schedule instead of reducing it.
As a thumb rule, more you crash, more you spend. In some cases, this would not pass
the traditional cost & benefit test. Unless there are clear cut advantages, a manager
should not resort to crashing as some important aspects may be ignored in haste.
The project manager flexible to make decision to get the optimal profits with the
lowest costs in the limit times.
PV/EV
Activity Link
Critical Path
150
100
BAC
50 EAC
ACWP
0
1 3 5 7 9 11 13